GUIDE

Consumer Unit Change UK
Cost, Regulations & Complete Guide

Replacing a consumer unit is one of the most common — and most regulated — jobs in domestic electrical work. This guide covers everything: when replacement is needed, current regulations, Part P requirements, typical costs, and what the job involves from start to finish.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

16 min readUpdated 2026-06-10Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer — DP Electrical

Key Takeaways

  • 1Replacing a consumer unit is notifiable work under Part P of the Building Regulations — it must be self-certified through a competent person scheme or notified to building control.
  • 2All new consumer units in domestic premises must have a metal enclosure compliant with BS EN 61439-3 (Regulation 421.1.201).
  • 3A full Electrical Installation Certificate (EIC) is required — a Minor Works Certificate is not appropriate for a consumer unit change.
  • 4Typical cost for a like-for-like consumer unit replacement is £500 to £1,200 depending on the number of circuits, board type (RCBO vs split-load), and any additional work required.
  • 5A straightforward like-for-like consumer unit replacement typically takes around four hours for the board change and testing alone; allow a full day when including the survey, DNO coordination, and EIC completion.
  • 6Domestic lighting circuits now require 30 mA RCD additional protection under Regulation 411.3.4 (BS 7671:2018+A4:2026) — this applies to all AC final circuits supplying luminaires and must be provided at the consumer unit.
01 · Guide

When Does a Consumer Unit Need Replacing?

Not every consumer unit needs replacing. A well-installed, modern unit with adequate protection for the circuits it serves can remain in service for decades. However, several conditions make replacement necessary or strongly advisable.

Old Rewirable Fuse Board

If the property still has a rewirable fuse board (with porcelain or Bakelite fuse holders and fuse wire), it should be replaced. Rewirable fuses offer limited overcurrent protection, provide no RCD protection, and the fuse wire can be replaced with the wrong rating by an unqualified person. The board itself may also be a plastic enclosure, which no longer meets current regulations for domestic premises.

No RCD Protection

If the existing consumer unit has no RCD protection at all, it does not meet the current requirements of BS 7671, which require 30 mA RCD protection for almost all circuits in a domestic installation, including all socket-outlet circuits and cables concealed in walls. While there is no legal requirement to upgrade an existing installation retrospectively, the safety benefit of adding RCD protection is substantial — an RCD can prevent fatal electric shock and reduce the risk of electrical fires.

Additional Circuits Needed

When new circuits are being added — for an EV charger, a kitchen extension, a garden office, or additional sockets — and the existing consumer unit has no spare ways, a replacement with a larger board is necessary. This is often combined with upgrading the RCD protection architecture at the same time.

Physical Damage or Overheating

Scorch marks, melted plastic, loose connections producing heat, or physical damage to the enclosure all require immediate replacement. These conditions indicate that the board has been subjected to fault conditions or has deteriorated to the point where it presents a fire risk. An electrician discovering these conditions during an EICR would typically classify them as C1 (Danger Present) or C2 (Potentially Dangerous).

Plastic Enclosure (Pre-2016 Board)

Consumer units installed before January 2016 may have plastic enclosures. While there is no requirement to replace them solely because of the enclosure material, if the board is being replaced for any reason, the new unit must have a metal enclosure compliant with BS EN 61439-3. Many electricians recommend replacing older plastic boards proactively, particularly where they are mounted on combustible surfaces.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Guide

Current Regulations for Consumer Unit Changes

A consumer unit change in 2026 must comply with BS 7671:2018+A4:2026 — the 18th Edition of the IET Wiring Regulations with Amendment 4. The key regulatory requirements are:

Key Regulatory Requirements

  • Metal enclosure (Regulation 421.1.201) — The consumer unit must comply with BS EN 61439-3 and be manufactured from non-combustible material. In practice, this means a steel enclosure.
  • 30 mA RCD protection for all circuits including lighting (Regulations 411.3.3, 411.3.4) — BS 7671:2018+A4:2026 requires 30 mA RCD additional protection for socket-outlet circuits and cables concealed in walls (Reg 411.3.3), and — new in A4:2026 — for AC final circuits supplying luminaires in domestic premises (Reg 411.3.4). Every lighting circuit in a domestic consumer unit change must now be RCD-protected. This is achieved with individual RCBOs or by placing lighting circuits under an RCD in a split-load arrangement.
  • Type A RCDs minimum; Type B where required (BS 7671 Section 531, OSG Reg 3.6.4.5) — RCDs must be at least Type A for circuits supplying equipment that produces pulsating DC fault currents, which covers most domestic circuits. Where the installation includes an EV charger, PV inverter, or battery storage system capable of producing smooth DC or complex residual currents, a Type B RCD is required for that circuit (OSG Reg 3.6.4.5). This is particularly relevant when a consumer unit change is being driven by the addition of an EV charger.
  • SPD provision (Section 443) — A risk assessment for surge protection is required. In most domestic installations, a Type 2 SPD should be fitted within or adjacent to the consumer unit.
  • Bidirectional devices (BS 7671:2018+A4:2026, Section 530) — Introduced by Amendment 4 (A4:2026). Where the installation includes battery storage, solar PV with battery backup, or V2G EV chargers, protective devices must be suitable for bidirectional fault current flow.
  • Circuit labelling (Regulation 514.9.1) — Every circuit must be identified with a durable label at the consumer unit. Labels must be accurate, legible, and identify the circuit purpose.

For full details on the regulatory framework, see the Consumer Unit Regulations guide.

BS 7671 Compliance Built Into Every Certificate

Elec-Mate's EIC form is structured around BS 7671:2018+A4:2026 requirements. Every test result is validated against the correct limits…

Try it free for 7 days
Download on the App StoreGet it on Google Play
03 · Guide

Part P Building Regulations Notification

Replacing a consumer unit is always notifiable under Part P of the Building Regulations (England and Wales). This applies regardless of whether it is a like-for-like replacement, an upgrade, or part of a larger project. There are no exceptions — even if the old board is being replaced with an identical unit, the work is notifiable.

There are two routes to compliance with Part P:

Route 1: Competent Person Scheme

The electrician is registered with an approved competent person scheme — NICEIC, NAPIT, ELECSA, BRE, or equivalent. The electrician self-certifies the work and notifies building control through the scheme. This is the most common route and avoids the need for a separate building control inspection. The scheme provider issues a building regulations compliance certificate to the homeowner.

Route 2: Building Control Notification

If the electrician is not registered with a competent person scheme, the work must be notified to the local authority building control department before the work begins. A building control officer will inspect the completed work and issue a completion certificate. This route is more expensive (building control fees typically £200-£400) and takes longer.

A full Electrical Installation Certificate (EIC) is required for a consumer unit replacement. A Minor Works Certificate is not appropriate — the work involves the replacement of a distribution board, which is defined as requiring a full EIC in BS 7671. The EIC must include the design, construction, and inspection and testing sections, together with a complete schedule of test results for every circuit.

04 · Guide

Arc Fault Detection Devices (AFDDs)

Arc Fault Detection Devices (AFDDs) are an additional layer of protection that detect dangerous electrical arcing — sparks caused by damaged cables, loose connections, or deteriorated insulation that can start fires. Unlike RCDs (which detect earth leakage) and MCBs (which detect overcurrent), AFDDs use electronic monitoring to identify the characteristic waveform signatures of series and parallel arcs.

Regulation 421.1.7 of BS 7671:2018+A4:2026 recommends the installation of AFDDs to BS EN 62606 in AC final circuits of a fixed installation to mitigate the risk of fire due to arc fault currents. The regulation uses "recommends" rather than "shall", so AFDDs remain advisory rather than mandatory — but A4:2026 is already the current edition of BS 7671 and this is live regulatory text. Many competent person schemes and building control bodies treat AFDD provision on bedroom and high-risk circuits as strong best practice.

Where AFDDs are fitted, on-completion verification is required: Regulations 421.1.7, 532.6, and 651.2(e) require the installer to confirm that each AFDD shows the correct operational indication and can be tested in accordance with the manufacturer's instructions. This confirmation must be recorded on the EIC schedule of inspections.

The cost of an AFDD RCBO is typically £80–£120 per circuit compared to £30–£50 for a standard RCBO. When specifying a consumer unit for a replacement, it is worth discussing AFDD provision with the customer — particularly for bedroom circuits and any circuits in locations with a higher fire risk such as roof spaces or areas with combustible structural materials.

Try Elec-Mate free for 7 days

16 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.

Start free trial
Download on the App StoreGet it on Google Play
05 · Guide

How Much Does a Consumer Unit Change Cost in 2026?

The cost of a consumer unit change depends on several factors: the size of the board, the type of protection (RCBO vs split-load), the condition of the existing wiring, and whether any additional work is needed.

Typical UK Costs (2026)

Basic split-load replacement

6-8 ways, dual RCD, standard circuits

£500 - £700

Full RCBO board

10-14 ways, individual RCBOs, SPD

£700 - £1,000

RCBO board with AFDDs

12-16 ways, AFDDs on bedroom circuits

£900 - £1,200

Additional work

New tails, meter tails upgrade, earth rod

£100 - £300 extra

These prices include the consumer unit, all protective devices, labour, testing, the EIC, and Part P notification through a competent person scheme. VAT is typically included for domestic work. Prices vary by region — London and the South East tend to be at the higher end, while the North and Midlands are typically lower.

Price Jobs Accurately with AI Cost Engineer

Elec-Mate's AI Cost Engineer prices consumer unit changes based on your specific specification — board type, number of ways, RCBO vs split-load, SPD…

Try it free for 7 days
Download on the App StoreGet it on Google Play
06 · Guide

What Is Involved in a Consumer Unit Change?

A straightforward consumer unit replacement typically takes one day for a competent electrician. The process involves isolating the supply, removing the old board, installing the new board, reconnecting all circuits, testing every circuit, and producing the EIC. Here is what happens at each stage:

1

Survey and Assessment

Before the day of the change, the electrician should survey the existing installation. This includes noting the number of circuits, identifying the cable sizes and types, checking the condition of the meter tails and earthing, and assessing whether any circuits need modification. This is also when the new board is specified and ordered.

2

Isolation and Old Board Removal

On the day, the supply is isolated at the main fuse (by the DNO if a sealed cut-out is involved, or by the electrician if an isolator is available). The old board is disconnected — each circuit is carefully labelled and recorded before disconnection. The old board is then removed from the wall.

3

New Board Installation

The new consumer unit is mounted and the meter tails connected. Each circuit is reconnected to its designated protective device (RCBO or MCB), following the design for the new board layout. The SPD is installed and connected. Earth and bonding connections are made up.

Torque tightening is essential. Every terminal — main switch clamp, RCBO/MCB screw terminals, neutral bar connections, and earth connections — must be tightened to the manufacturer's specified torque value. Under-torqued terminations are the leading cause of loose connections, overheating, and premature board failure. Use a calibrated torque screwdriver and consult the consumer unit manufacturer's data sheet for each terminal type.

4

Testing Every Circuit

Once all circuits are connected and the supply is restored, every circuit must be tested. The full testing sequence includes continuity of protective conductors (R1+R2), insulation resistance, polarity, earth fault loop impedance (Zs), prospective fault current (Ipf), and RCD testing on every RCD/RCBO.

5

Certification and Handover

The electrician completes and issues the Electrical Installation Certificate (EIC) with all test results. The circuit chart is printed and fixed inside the consumer unit door. The Part P notification is submitted through the competent person scheme. The homeowner receives copies of the EIC and the building regulations compliance certificate.

Board Scanner — Photograph the Old Board

Elec-Mate's Board Scanner photographs the existing consumer unit and uses AI to extract all circuit data — circuit numbers, MCB ratings, RCD types…

Try it free for 7 days
Download on the App StoreGet it on Google Play

How to Change a Consumer Unit — Step-by-Step Process

1

Survey the existing installation

Record all existing circuits, cable types, cable sizes, and the condition of the meter tails and earthing. Check the DNO cut-out and confirm whether a temporary disconnection is needed. Photograph the existing board for reference. Specify the new consumer unit based on the number of circuits, RCD architecture (RCBO or split-load), and any additional requirements (SPD, AFDD, spare ways for future circuits).

2

Isolate the supply

Isolate at the main switch and, if necessary, pull the DNO fuse or arrange a temporary disconnection. Carry out safe isolation procedure — prove-test-prove using a GS38-compliant voltage indicator. Lock off and apply warning labels. Inform the occupants that the supply will be off for the duration of the changeover.

3

Remove the old board and install the new one

Disconnect all circuits from the old board, labelling each cable clearly. Remove the old board. Mount the new metal consumer unit. Connect the meter tails (typically 25mm² for 100A supply). Install the main switch, SPD, and all RCBOs or MCBs. Reconnect each circuit to its designated protective device following the design layout. Torque all terminals — main switch clamp, RCBO/MCB screws, neutral bar, and earth connections — to the manufacturer's specified values using a calibrated torque screwdriver. Under-torqued terminations are the most common practical failure mode on consumer unit replacements.

4

Test every circuit

Restore the supply and carry out the full testing sequence on every circuit: continuity of protective conductors (R1+R2), insulation resistance at 500V DC, polarity verification, earth fault loop impedance (Zs), prospective fault current (PSCC and PEFC), and RCD operating time for every RCBO. Record all results in the schedule of test results.

5

Complete the EIC and Part P notification

Complete the Electrical Installation Certificate with all design, construction, and test data. Apply the circuit chart inside the consumer unit door. Submit the Part P notification through your competent person scheme. Issue copies of the EIC to the homeowner and retain your own copy for at least six years.

Frequently Asked Questions

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-Day Free Trial — Cancel Anytime, No Hassle

Certify Consumer Unit Changes on Your Phone

EIC forms, test result validation, Board Scanner, and Part P notification — all built into Elec-Mate. 7-day free trial, cancel anytime.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical

From £6.99/mo after trial — less than a coffee a week

or download the app
Download on the App StoreGet it on Google Play
7 days free, then from £6.99/moCancel in one tap — no calls, no hassleiOS, Android & WebBS 7671 compliant
16
Certificate Types
70+
Calculators
46+
Training Courses
8
AI Agents

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy