EICR COMMON DEFECT

EICR: No Main Protective Bonding — The Classic C2

Across UK domestic EICRs, "no main protective bonding to incoming gas / water / oil services" is the single most common C2 observation. It makes the report unsatisfactory and triggers urgent remedial action under PRS Regs 2020 in rented properties. This guide explains what BS 7671 actually requires, how to identify the defect at inspection, and the exact remedial work that clears the C2.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

11 min readUpdated 2026-06-10Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer — DP Electrical

Key Takeaways

  • 1Main protective bonding to extraneous-conductive-parts is required by Regulation 411.3.1.1 and the bonding conductor is sized per Regulation 544.1.1 (and Table 54.8 on PME supplies).
  • 2Extraneous-conductive-parts that must be bonded: metallic gas installation pipes, metallic water installation pipes, metallic oil installation pipes, structural steel where applicable, lightning protection systems, other metallic services that could introduce a potential.
  • 3Missing bonding is a C2 observation in almost all cases — danger could become present under fault conditions when the missing bonding allows touch voltage to appear on metalwork accessible throughout the dwelling.
  • 4PME supplies require LARGER bonding conductors than non-PME TN-C-S — typically 10 mm² minimum on a 100 A service, going to 16 mm² on larger supplies. Refer to Table 54.8.
  • 5Plastic pipes ARE NOT extraneous-conductive-parts and do not require bonding. The bonding requirement is for METALLIC pipework where the metal continues outside the building.
  • 6Remedial work: install a 10 mm² (or 16 mm² PME-supply dependent) earthing conductor from the Main Earthing Terminal at the consumer unit to the service pipe within 600 mm of the meter or first point of entry into the building.
01 · EICR Common Defect

What BS 7671 Actually Requires

BS 7671 Regulation 411.3.1.1 requires main protective bonding to be applied to extraneous-conductive-parts as part of the Automatic Disconnection of Supply (ADS) protective measure. The bonding ensures that, under a fault condition that places a potential on the installation's exposed metalwork, the metallic services entering the dwelling are also raised to (approximately) the same potential — preventing dangerous touch-voltage differences across the building.

  • **Regulation 411.3.1.1** — main protective bonding requirement: extraneous-conductive-parts shall be connected to the main earthing terminal.
  • **Regulation 544.1.1** — sizing of main protective bonding conductors.
  • **Table 54.8** — minimum main protective bonding conductor CSA on PME supplies, by PEN conductor size of the supply.
  • **Regulation 411.3.1.2** — sets the maximum disconnection times (Table 41.1) that apply to socket-outlet and fixed-load final circuits under ADS.

What counts as an extraneous-conductive-part

An extraneous-conductive-part is metalwork that is liable to introduce a potential — typically earth potential — that's not part of the electrical installation. The metallic gas service pipe, metallic water service pipe, metallic oil service pipe are the classic examples. Central heating and air conditioning systems with metallic pipework or ductwork can also be extraneous-conductive-parts. Structural steel that runs to ground level can be an extraneous-conductive-part. Plastic pipes are NOT extraneous-conductive-parts.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · EICR Common Defect

How to Identify Missing Bonding at Inspection

Verifying main protective bonding during EICR is a methodical walk-through of the service entry points:

  1. Locate the Main Earthing Terminal (MET) — typically at or near the consumer unit, sometimes in the meter cupboard or a separate earth block.
  2. Identify each metallic service entering the dwelling: gas meter (within 600 mm of the meter), water service (typically at the rising main / stop tap), oil tank supply (if applicable).
  3. Trace each bonding conductor from the MET to the service pipe. The conductor must be visible / continuous (no joints unless in an accessible enclosure with the joint protected).
  4. Verify the bonding clamp at the service — BS 951-compliant clamp with a permanent "Safety Electrical Connection — Do Not Remove" label.
  5. Verify the bonding conductor CSA against Table 54.8 for the supply earthing arrangement.
  6. Test continuity between the MET and the bonded service (typically R₂ method): a low-resistance reading (< 0.05 Ω is typical for a sound installation).

Common ways "missing bonding" is hidden

Bonding sometimes appears to exist but is non-compliant: bonded to a plastic-pipe section (no electrical continuity), undersized conductor for the supply rating, broken/corroded clamp, conductor terminated at the wrong side of an insulating coupling, bonding conductor disconnected at the MET. Each of these is still a C2 observation — the conductor is not providing the required equipotential connection.

03 · EICR Common Defect

Why It's C2 (Not C1 or C3)

BS 7671 / IET GN3 give a strict hierarchy for observation coding (see the dedicated EICR Code C1, C2, C3 and FI guides). Missing main bonding is almost always C2 because:

  • **Not C1** — danger is not actively present under normal conditions. Touch voltage between the unbonded service and the installation's metalwork is only dangerous DURING a fault. The condition is potentially dangerous, not currently dangerous.
  • **Not C3** — the condition is NOT merely a departure from BS 7671 with no danger implication. Under foreseeable fault conditions, dangerous voltage can appear on metalwork accessible throughout the dwelling. C3 ("Improvement recommended") shall not be used where C2 evidence exists.
  • **Therefore C2** — "Potentially dangerous — urgent remedial action is necessary."

The single exception: where the structure has NO extraneous-conductive-parts (e.g., all-plastic plumbing from the boundary, no gas service, no metallic structural steel) — but the inspector MUST verify this and document the rationale on the EICR.

04 · EICR Common Defect

Sizing the Main Bonding Conductor

Main bonding conductor CSA depends on the earthing arrangement:

  • **Non-PME TN-S and TT supplies (single building)** — main bonding CSA shall be not less than half the cross-sectional area of the earthing conductor of the installation (Regulation 544.1.1). There is no 6 mm² floor for a single building on non-PME; the half-earthing-conductor rule applies directly.
  • **Non-PME supplies serving more than one building** — the 6 mm² minimum applies (and the CSA is based on the distribution circuit protective conductor for that building), with an upper practical limit of 25 mm² copper (Regulation 544.1.1).
  • **TN-C-S (PME) supplies** — main bonding CSA is dictated by Table 54.8, based on the PEN conductor size of the distributor's supply. Typical 100 A domestic PME service: minimum 10 mm² main bonding. Larger services: 16 mm² or higher.
  • **TN-C-S (PNB) supplies** — sized per the standard non-PME rules where downstream of the PEN-to-PE split, but the upstream private network may have specific design requirements.

PME supply: always check with the DNO

Before finalising the bonding conductor CSA on a PME supply, check with the local Distribution Network Operator — their network conditions may require a larger conductor than the Table 54.8 minimum. This is a mandatory procedural step per Regulation 544.1.1; failure to check may result in an undersized bonding conductor that does not meet the DNO's requirements.

Common UK domestic sizing

Most UK domestic installations on a 100 A PME service install 10 mm² green-and-yellow conductor with a BS 951 clamp at each service. On larger services (e.g. 200 A) or three-phase domestic supplies, 16 mm² becomes the standard.

Record test results hands-free on site

AI board scanner, voice test entry, and automatic BS 7671 validation — finish the certificate before you leave the property. From £6.99/mo.

Try the certificate tools free
Download on the App StoreGet it on Google Play
05 · EICR Common Defect

Remedial Work — What Actually Fixes a C2

The remedial action for missing main bonding is straightforward: install the missing conductor(s). The specifics:

  1. Confirm the supply earthing arrangement (PME, PNB, TN-S, TT) — this dictates the bonding conductor CSA.
  2. Select the conductor — 10 mm² 6491X green-and-yellow for most PME domestic; 6 mm² for non-PME where appropriate; or larger per Table 54.8.
  3. Route the conductor from the Main Earthing Terminal at the consumer unit to the service pipe, by the shortest practicable route, protected against mechanical damage.
  4. Terminate at the MET with the existing earthing arrangement (typically a brass terminal bar).
  5. Terminate at the service with a BS 951 clamp, applied to bare metal pipe within 600 mm of the meter or first point of entry into the building. Apply the clamp to a continuous run of metallic pipe — never to a section that has a plastic insert downstream.
  6. Affix the BS 951 "Safety Electrical Connection — Do Not Remove" label adjacent to each clamp.
  7. Test continuity between the MET and the bonded service — should read sub-ohm.
  8. Issue an EIC or MEIWC for the remedial work; provide a copy to the responsible person (and, for rented properties under PRS Regs 2020, to the tenant within 28 days).
06 · EICR Common Defect

Special Cases

  • **All-plastic plumbing** — no main bonding required to a service that doesn't exist. Document the absence in the EICR Section D ("Extent and Limitations") and note in the schedule that no extraneous-conductive-parts were identified.
  • **Meter remote from the dwelling** — bonding clamp goes within 600 mm of the FIRST point of entry of the metallic pipe into the building, not necessarily at the meter. For meters in outhouses or detached meter cupboards, this typically means at the point where the pipe enters the main dwelling.
  • **Lightning protection systems** — if the dwelling has a lightning protection system, the system's earth termination network connects to the MET via main bonding. Consult BS EN 62305 for the specific arrangement.
  • **Special locations** — bathrooms (Section 701), swimming pools (Section 702), agricultural premises (Section 705) have additional supplementary equipotential bonding requirements beyond the main bonding. Missing supplementary bonding in special locations is also typically a C2.
  • **Domestic with shared services** — flats / HMOs may have communal gas / water with bonding at the service entry to the building, not to each flat. Verify the bonding arrangement at the building level matches BS 7671.
  • **Incoming metallic-sheathed telecoms cables** — bonding shall only be applied with the consent of the owner or operator of the telecoms cable (Regulation 411.3.1.1). In practice this means contacting the network operator (e.g. Openreach, Virgin Media) before bonding old lead-sheathed or metal-screened cables. If consent is refused and bonding cannot be applied, the details shall be recorded in the description section of the EICR or other electrical certification — do not leave the situation undocumented.

Frequently Asked Questions

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-Day Free Trial — Cancel Anytime, No Hassle

Convert C2 observations into remedial quotes

Elec-Mate's digital EICR has a curated C2 observation library — pick "no main protective bonding", set the service, and the tool auto-generates the remedial quote with materials, labour and certification cost. 7-day free trial.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical

From £6.99/mo after trial — less than a coffee a week

or download the app
Download on the App StoreGet it on Google Play
7 days free, then from £6.99/moCancel in one tap — no calls, no hassleiOS, Android & WebBS 7671 compliant
16
Certificate Types
70+
Calculators
46+
Training Courses
8
AI Agents

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy