RAMS for a Consumer Unit Replacement — Method Statement & Risk Assessment

A consumer unit replacement is one of the highest-risk routine jobs an electrician carries out — work close to the distributor's cut-out, total loss of supply to the customer, and a hard compliance deadline once the new board is energised. This guide walks through a fully BS 7671:2018+A4:2026 aligned RAMS: hazards specific to a board change, control measures, safe isolation procedure, the DNO seal question, PPE, A4:2026 compliance opportunities and the test sequence that produces an EIC at the end of the day.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

12 min readUpdated 2026-05-18Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer — DP Electrical

Key Takeaways

  • 1A consumer unit replacement RAMS must address hazards that are specific to working at the origin of the installation — proximity to the DNO service head, total customer power-off, dust and debris, and bonding continuity disturbed mid-job.
  • 2Under the Electricity at Work Regulations 1989, Regulation 14, live working is prohibited unless three tests are met. A consumer unit change is planned work — there is no justification for working live on the meter tails or the new board.
  • 3You shall not cut the distributor's cut-out seal without prior authorisation. Notify the DNO (or supplier where the meter is sealed) and use their isolation service or temporary seal procedure — record the authority in the RAMS.
  • 4Every consumer unit replacement under BS 7671:2018+A4:2026 is also a compliance opportunity: Reg 421.1.201 (non-combustible enclosure for domestic CUs), Reg 411.3.4 (RCD protection for lighting circuits where AFDD is not provided), and the A4:2026 AFDD recommendations for socket-outlets up to 32 A.
  • 5The job ends with an Electrical Installation Certificate (EIC) — not a Minor Works Certificate. A CU replacement is an alteration to the distribution circuit and requires full initial verification under BS 7671 Part 6.
  • 6CDM 2015 applies to most domestic CU changes the moment a second worker is on site, or any time the work is non-domestic. The principal contractor / contractor duties are not optional.
01 · Method Statement & Risk Assessment

Why a Consumer Unit Change Needs Its Own RAMS

A generic electrical RAMS doesn't cover a consumer unit replacement properly. The hazards stack up at the origin of the installation: you are working a few millimetres from the un-isolated supply tails, the customer is losing all power for the day, the cabling is often old and brittle, and you have a hard deadline — the board must be back on and tested before you leave.

Under the CDM 2015 framework and the Electricity at Work Regulations 1989 (EAWR), the duty holder is required to plan the work, assess the foreseeable risks and document the control measures before work begins. The Elec-Mate RAMS Generator builds a CU-specific RAMS pack in two minutes — but whether you generate it or write it yourself, the document must reflect what you will actually do on the day, not a copy-pasted template.

Domestic doesn't mean exempt

A domestic consumer unit change is still notifiable work in England and Wales (Part P), still subject to EAWR for the electrician, and once a second person is involved (apprentice, mate, scaffolder, builder) it becomes CDM 2015 work. The RAMS is not paperwork for the file — it is the legal record of how the danger was controlled.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Method Statement & Risk Assessment

Hazards Specific to a Consumer Unit Replacement

A risk assessment is only useful when it identifies the real hazards in front of you. For a consumer unit change in a UK property the principal hazards are:

  • Working in close proximity to live conductors at the DNO cut-out. The service head, the meter tails between cut-out and meter, and (until the supplier isolates) the tails into the consumer unit are all live and cannot be isolated by the electrician.
  • Inadvertent contact with un-isolated meter tails when removing the old CU enclosure — particularly if the tails are short, brittle PVC, or routed tightly against the wall.
  • Loss of supply to the customer for several hours — vulnerable occupants (medical equipment, refrigerated medication, elderly, very young children) must be identified in advance.
  • Disturbance of main protective bonding and the main earthing conductor during board removal — earth continuity may be broken mid-job, leaving exposed-conductive-parts unbonded.
  • Dust, debris and asbestos risk from removing the old enclosure, especially where the back box is fixed into pre-2000 masonry or plasterboard.
  • Working at height where the CU is mounted high on a wall, in a loft, in a cupboard with poor access, or in a stairwell.
  • Manual handling of the new consumer unit (often 8–15 kg with components fitted) into a confined cupboard or loft hatch.
  • Live testing during initial verification — the new board must be energised and tested before you leave, which means controlled live work under EAWR Reg 14 conditions.
  • Fire risk if a poor termination at the meter tail connections leads to thermal runaway after re-energisation.
  • Lone working — most domestic CU changes are single-electrician jobs, which has implications for emergency response.
03 · Method Statement & Risk Assessment

Control Measures

For each identified hazard the RAMS must record the control measure, who is responsible, and how it will be verified on the day. The non-negotiable controls for a consumer unit replacement are:

  • Safe isolation following the GS38 + IET sequence: identify, isolate, lock-off, prove dead at the point of work using an approved voltage indicator, verify the voltage indicator before and after on a known live source.
  • DNO / supplier notification if the cut-out seal must be cut — request a temporary isolation visit or an authorised seal-break, and record the reference number in the RAMS.
  • Customer pre-notification in writing at least 48 hours in advance with the off-supply window, vulnerable-occupant questions answered, and a UPS / generator arrangement agreed for any medical equipment.
  • Bonding continuity maintained during the change — main protective bonding and main earthing conductor either left in place at the MET or temporarily linked via a labelled, terminated conductor of equivalent CSA.
  • PPE appropriate to the task (see section below) and an insulated mat where there is any risk of contact with the floor while working near the cut-out.
  • Dust control — sheeting laid, hoover with HEPA filter on hand, customer's belongings covered or removed from under the board.
  • Pre-work asbestos check on the substrate behind the board for pre-2000 properties.
  • Working-at-height controls — proper step or platform, not a stack of boxes, and never on the customer's furniture.
  • Mobile phone or radio for lone-worker check-ins at agreed intervals, with a nominated person who knows the address and expected finish time.
  • A defined emergency response: nearest A&E address, what to do if the customer feels unwell during the off-supply period, location of the on-site first-aid kit.
04 · Method Statement & Risk Assessment

Safe Isolation Procedure and the DNO Seal Question

The biggest single control measure for a consumer unit change is the isolation step. This is where almost every serious incident on a board change comes from — and it is the area where DIYers and inexperienced installers make the most dangerous decision: cutting the distributor's seal without authority.

Never cut the distributor's seal without authority

The seal on the service cut-out and on the meter belongs to the DNO and to the supplier respectively. Cutting them without prior authority is theft of electricity and a criminal offence under the Theft Act 1968 and the Electricity Act 1989. It also voids your professional indemnity cover if anything goes wrong. The correct route is to call the DNO's priority services or the customer's supplier and request either: (a) a free isolation visit, (b) authority to cut the seal under their temporary seal procedure with a re-seal callback booked, or (c) a smart-meter remote isolation if the meter supports it.

Once the distributor has isolated upstream (or you have isolated at the main switch of the existing CU where the new board is being swapped without disturbing the tails), follow the standard safe-isolation sequence:

  1. Identify the point of isolation — main switch on the existing CU, or upstream isolator fitted by the DNO.
  2. Switch off, withdraw any plug-in fuses, and apply a personal lock-off device and a "Danger — Do Not Switch" caution notice. The key stays in your pocket. If a customer has access to the area, brief them and barrier off.
  3. Prove your approved voltage indicator (GS38) on a known live source — a proving unit or a separate live point.
  4. Test for absence of voltage at the actual point of work — between phase and neutral, phase and earth, and neutral and earth, on every conductor you are about to disconnect.
  5. Re-prove the voltage indicator on the same known live source to confirm it is still functioning.
  6. Record the isolation in the RAMS / permit-to-work, sign and time-stamp.

A formal permit-to-work for electrical isolation is overkill for a single-electrician domestic CU change, but in any commercial or HMO setting it is the right paperwork — and the RAMS should reference it. For more detail on the working-near-live-mains element, see our guide on hazard control near live mains.

Try Elec-Mate free for 7 days

16 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.

Start free trial
Download on the App StoreGet it on Google Play
05 · Method Statement & Risk Assessment

PPE for a Consumer Unit Replacement

PPE is the last line of defence after every other control — but a CU change has specific PPE requirements that a generic site PPE list doesn't cover:

  • Insulated safety footwear with an electrical hazard rating, and clean dry soles for any work close to the cut-out.
  • Class 0 or Class 00 electrically-insulating gloves rated for 500 V working voltage, worn over thin liner gloves, for any movement near un-isolated tails.
  • Safety glasses with side shields — the risk of an arc flash during a fault on re-energisation is small but the consequence is severe.
  • Arc-rated long-sleeve top for any work close to the service head where un-isolated conductors are within arm's reach.
  • FFP3 dust mask where the existing back box is fixed into pre-2000 masonry or where the customer's board sits in a dusty cupboard.
  • Head protection where the CU is mounted in a loft, low-headroom cupboard or under stairs.

PPE doesn't replace isolation

Class 0 gloves are a backstop. They are not an authorisation to work live. Under EAWR Reg 14 the work must be dead unless live working is unavoidable, the person is competent for live work, and suitable precautions are in place. A consumer unit replacement does not meet the Reg 14 test for live working.

06 · Method Statement & Risk Assessment

A4:2026 Compliance — Every CU Change is a Compliance Opportunity

BS 7671:2018+A4:2026 came into force during 2026 and a consumer unit replacement is the one job where you have full design control over the new installation. The RAMS should reference these compliance points so the customer is aware the new board will exceed the bare minimum:

  • Reg 421.1.201 — consumer units and similar switchgear assemblies in domestic premises shall have their enclosure manufactured from non-combustible material (typically steel). This means the old plastic CU comes out and a steel-enclosed board goes in. See our EICR plastic consumer unit in HMO guide for the wider context.
  • Reg 411.3.4 — additional protection by an RCD not exceeding 30 mA shall be provided for lighting circuits in domestic (household) premises. The A4:2026 wording aligns with the new AFDD recommendations. See A4:2026 luminaire RCD protection for the full text and acceptance criteria.
  • AFDD recommendations under A4:2026 — arc fault detection devices are now recommended for final circuits supplying socket-outlets rated up to 32 A in higher-risk premises (HMOs, care homes, student accommodation, premises with combustible construction). See A4:2026 AFDD changes for the precise scope.
  • Reg 526.1 — every connection between conductors and equipment shall provide durable electrical continuity and adequate mechanical strength and protection. At the new board this means torqued-to-spec terminations on every line, neutral and earth, and a recorded torque value on the EIC.
  • Surge Protection Device (SPD) — Section 443 requirements continue under A4:2026; an SPD shall normally be installed in domestic premises unless the risk assessment justifies omission and the customer accepts the omission in writing.

Quote the compliance up front

A surprising number of customer disputes after a CU change are about the price difference between a like-for-like swap and a full A4:2026-compliant board (with AFDDs, SPD, and metal enclosure). Quote the compliant board first, note the per-line cost of each compliance item, and let the customer decline in writing if they want a cheaper option — this protects you on both EAWR and the consumer contract.

07 · Method Statement & Risk Assessment

Post-Installation Test Sequence and the EIC

A consumer unit replacement is an alteration to the distribution circuit at the origin of the installation. Under BS 7671 Part 6 it requires full initial verification — not a Minor Works Certificate. The output document is an Electrical Installation Certificate (EIC) signed by the designer, constructor and inspector (often all the same competent person on a domestic job).

The test sequence on a CU change follows BS 7671 Reg 643 and IET GN3 Section 2. Dead tests first, then live tests after energisation:

  1. Continuity of protective conductors (R1+R2 on every final circuit, plus continuity of main protective bonding).
  2. Continuity of ring final circuit conductors (line, neutral and CPC end-to-end and cross-connected).
  3. Insulation resistance — between line conductors and earth, and between line and neutral, at 500 V DC, with electronic equipment disconnected or tested at 250 V where damage is a concern.
  4. Polarity dead — confirm correct connection of every line conductor at every accessory.
  5. Earth electrode resistance where the earthing arrangement is TT (not common on a CU replacement unless the supply earth has been refused).
  6. Energise the installation (this is the live-working step — controlled, brief, with no terminations being touched while live).
  7. Earth fault loop impedance (Zs) at every final circuit, recorded on the schedule of test results, with the measured value plus the calculated maximum from Table 41.x.
  8. Prospective fault current at the origin (Ipf).
  9. RCD operating-time tests at the rated 1× and 5× residual operating currents, including the supplementary 6 mA DC test for Type A/B RCDs as required.
  10. Functional testing of every protective device (RCD test button, AFDD self-test, main switch operation).
  11. Phase sequence on three-phase installations.

Every result lands on the schedule of test results, which is appended to the EIC. The customer receives the EIC and a copy is retained for six years for liability cover. Generate the EIC digitally with the Elec-Mate EIC Certificate tool — it auto-populates the schedule columns updated under A4:2026 and exports a Building Regulations Part P compliant PDF.

How to work through the consumer unit replacement RAMS on the day

A condensed five-step sequence that maps the RAMS to the on-site reality. Use this as your final pre-start check before tools come out of the van.

1

Pre-arrival checks and DNO authority

Confirm the customer is expecting you, the off-supply window is agreed in writing, no vulnerable occupants are at risk, and the DNO / supplier has either authorised seal-break or scheduled an isolation visit. Confirm the new CU specification matches the quote (metal enclosure, AFDDs / RCBOs to A4:2026, SPD if specified).

2

Walk the job and verify the RAMS still applies

On arrival, confirm the working environment matches the assumptions in the RAMS — access, cupboard size, distance to the cut-out, condition of the meter tails, asbestos signs, vulnerable occupants. If anything is different, update the RAMS on the spot before any work starts.

3

Isolate, lock off and prove dead

Carry out the full safe-isolation sequence at the agreed point of isolation. Lock off, apply the caution notice, prove the voltage indicator on a known live source, test for absence of voltage at the point of work, re-prove the voltage indicator, sign and time-stamp the RAMS.

4

Remove, install, maintain bonding

Remove the existing board, maintaining bonding continuity throughout (link the main protective bonding and main earthing conductor at the MET via a temporary terminated conductor if the MET is being moved). Install the new enclosure, dress the meter tails, terminate every conductor to the recorded torque value, label every circuit.

5

Energise, full initial verification, EIC

Carry out every dead test, energise carefully, complete every live test, run every protective device through its functional test. Issue the EIC and schedule of test results, hand over the customer pack, register the work under Part P. File the RAMS, EIC and DNO authority reference together for the six-year retention period.

Frequently Asked Questions

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-Day Free Trial — Cancel Anytime, No Hassle

Generate a CU-specific RAMS in two minutes

The Elec-Mate RAMS Generator builds a consumer-unit-replacement Risk Assessment & Method Statement with the right hazards, control measures, isolation procedure, PPE, A4:2026 compliance notes and test sequence — pre-filled, site-specific, signed and exported as PDF. Start your 7-day free trial; cancel anytime.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical

From £6.99/mo after trial — less than a coffee a week

or download the app
Download on the App StoreGet it on Google Play
7 days free, then from £6.99/moCancel in one tap — no calls, no hassleiOS, Android & WebBS 7671 compliant
16
Certificate Types
70+
Calculators
46+
Training Courses
8
AI Agents

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy