Surge Protective Devices Section 443 — under BS 7671:2018+A4:2026
Section 443 of BS 7671 governs the protection of low-voltage electrical installations against transient overvoltages of atmospheric origin or due to switching. Since Amendment 2 (2022) the rule has been simple: surge protection is required unless the owner of the installation declares, and accepts the risk, that it is not wanted. The old Calculated Risk Level (CRL) calculation was deleted, and Amendment 4:2026 keeps that position. This guide walks UK electricians through the regulation cite-by-cite, sets out Type 1, Type 2 and Type 3 selection, explains the Section 534 installation rules that decide whether the device actually works in practice, and shows how to code missing or failed SPDs at EICR.
“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”
Key takeaways
01Section 443 of BS 7671:2018+A4:2026 governs protection against transient overvoltages — atmospheric (lightning) and switching origin. Section 534 covers how the SPDs that deliver that protection are installed and coordinated.
02There is no risk calculation any more: the Calculated Risk Level (CRL) method in the 2018 text was deleted by Amendment 2 (2022), and A4:2026 keeps the simpler Regulation 443.4.1 rule.
03Regulation 443.4.1 requires transient overvoltage protection where the consequence of the overvoltage could result in (a) serious injury to, or loss of, human life, or (c) significant financial or data loss — limb (b) was deleted by the BS 7671:2018+A2:2022 Corrigendum (May 2023). For all other cases, protection shall be provided unless the owner of the installation declares it is not required because any loss or damage is tolerable and they accept the risk.
04Type 1 SPDs (10/350 µs waveform) are required at the origin where the structure has an external lightning protection system or protection against direct lightning (Regulation 534.4.1.3). Otherwise Type 2 SPDs (8/20 µs) go at the origin (534.4.1.4). Type 3 SPDs sit close to sensitive equipment in addition to upstream protection.
05Section 534 imposes strict installation rules: total connecting-conductor length preferably no more than 0.5 m and never more than 1.0 m (534.4.8), earthing conductors of at least 6 mm² for Type 2 or 16 mm² for Type 1 at the origin (534.4.10), and a backup overcurrent device to the SPD manufacturer's instructions.
06For solar PV and battery storage, the DC side needs its own DC-rated SPDs (BS EN 61643-31 for PV), separate from the AC origin device, following the PV and battery manufacturers' instructions and Section 712.
07Missing surge protection in an existing installation is usually coded C3 (improvement recommended) on an EICR. A C2 is a judgement for the inspector where the absence creates a real risk, for example to life-safety systems.
01 · BS 7671 A4:2026
What Section 443 Actually Does
Section 443 of BS 7671:2018+A4:2026 sits inside Part 4 — Protection for Safety — and deals exclusively with one threat: transient overvoltages. A transient overvoltage is a short-duration spike, typically lasting microseconds, that travels along the supply cables or down the equipotential bonding system and lands on the terminals of equipment connected to the installation. The two sources Section 443 cares about are atmospheric (a lightning strike to the distribution network, the structure or nearby ground) and switching (high-current breaks elsewhere on the network, large inductive loads cycling, capacitor switching).
Regulation 443.4.1 says protection shall be provided where the consequence of an overvoltage could be serious injury or loss of life, or significant financial or data loss, and in all other cases unless the owner declares it is not required and accepts the risk. The mechanism that delivers that protection is then governed by Section 534 of the standard — how the SPD is selected, where it is installed, how it is connected, and how multiple SPDs are coordinated.
Section 443 vs Section 534 — the split
Section 443 (Part 4, Protection) tells you when an SPD is required and what overvoltage category equipment falls into. Section 534 (Part 5, Selection and Erection) tells you how to install it so it works. You need both regulations side by side on any job that touches surge protection.
In BS 7671:2018+A4:2026 the requirement sits in Regulation 443.4.1 (transient overvoltages from indirect lightning) and 443.4.2 (switching overvoltages from equipment such as motors, transformers and capacitor banks), with the rated impulse voltages of equipment in Table 443.2. Regulation 443.5, which carried the old risk calculation, was deleted by Amendment 2 (2022). Amendment 4 deleted Annex B443 but did not reintroduce a calculation.
For a fuller picture of how A4:2026 affects the rest of the standard, see our BS 7671 A4:2026 summary. For the SPD device itself in isolation — what it is, how it clamps, and how it differs from an MCB — see our SPD guide and the broader power surge protection explainer.
Free download · PDF
Get the BS 7671 A4:2026 Cheat Sheet — free
Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.
Every regulation change summarised
New model forms (EIC + MEIWC)
Free PDF — no subscription
02 · BS 7671 A4:2026
What Happened to the Risk Calculation (CRL)
BS 7671:2018 as first published let the designer decide by calculation. Regulation 443.5 set out a Calculated Risk Level (CRL), based on the supply length, the environment and the lightning flash density, and SPDs were only needed where the CRL fell below a set threshold. Many electricians used it to justify leaving SPDs out of domestic consumer units.
Amendment 2 (2022) deleted Regulation 443.5, its figures and Table 443.1. What replaced it is the rule now in Regulation 443.4.1, and Amendment 4:2026 keeps it unchanged:
Protection against transient overvoltages shall be provided where the consequence could result in (a) serious injury to, or loss of, human life, or (c) significant financial or data loss. Limb (b) was deleted by the A2:2022 Corrigendum (May 2023).
For all other cases, protection shall be provided unless the owner of the installation declares it is not required, because any loss or damage is tolerable and they accept the risk of damage to equipment and any consequential loss.
Separately, Regulation 443.4.2 asks for protection against switching overvoltages to be considered where equipment such as motors, transformers, capacitor banks, storage units or high current loads could produce disturbances above the rated impulse voltages in Table 443.2.
Omitting SPDs is the owner's decision, not the designer's
There is no calculation that lets the electrician decide SPDs are not needed. If they are left out, it should be because the owner has declared they do not want them and accepts the risk. Record that declaration with the certificate.
03 · BS 7671 A4:2026
When SPDs Are Mandatory and When They Are Optional
Putting Regulation 443.4.1 into plain English for working electricians: protection is mandatory where the consequence of an overvoltage could result in serious injury or loss of human life, or significant financial or data loss. For all other cases, SPDs must still be fitted unless the owner declares the risk tolerable in writing.
Mandatory by consequence — limb (a): installations where the consequence of an overvoltage could result in serious injury to, or loss of, human life (e.g. medical locations to Section 710, fire detection and alarm systems, emergency lighting central battery systems, safety-related industrial control).
Mandatory by consequence — limb (c): installations where the consequence of an overvoltage could result in significant financial or data loss (e.g. data centres, server rooms, commercial premises holding critical records).
For all other cases — protection against transient overvoltages shall be provided unless the owner of the installation declares it is not required because any loss or damage is tolerable and they accept the risk of damage to equipment and any consequential loss. Only the owner's declaration permits omission.
Practical default — most modern domestic installations: a typical new-build or full rewire with a long supply, a mix of mains-connected smart electronics, solar PV, battery storage and EV charging will be fitted with SPDs by default, because the owner-declaration route makes discretionary omission harder to defend.
In domestic practice, the practical answer for most A4:2026 consumer unit replacements is: fit SPDs unless the client has been told what they protect against and has declined them in writing. That position lines up with what most insurers and CPS schemes are now expecting on a 2026-onwards installation, and it means the documentation trail at handover is clean.
TT systems deserve special attention
TT-earthed installations sit at higher risk from transient overvoltage events because the earth return path is via a local rod rather than a low-impedance network earth. The same Regulation 443.4.1 rule applies, so an SPD should be fitted unless the owner declines it; on TT installations, check the SPD arrangement the manufacturer specifies for TT systems.
04 · BS 7671 A4:2026
Type 1, Type 2 and Type 3 SPDs
BS 7671:2018+A4:2026 retains the three-tier classification of low-voltage SPDs, tested and declared to BS EN 61643-11. The Type number is not a quality grade — it describes the test waveform the device is qualified against, and therefore the kind of event the device is designed to handle and the position in the installation where it is meant to live.
Type 1 SPD — tested with a 10/350 µs current waveform that simulates a partial direct lightning current. Required as close as possible to the origin where the structure has an external lightning protection system or protection against the effects of direct lightning (Regulation 534.4.1.3). Typically declared with an Iimp (impulse current) rating in kA.
Type 2 SPD — tested with an 8/20 µs current waveform that simulates an induced transient, including the residual of a strike further away on the network. This is the standard origin-of-installation device for the vast majority of UK installations and is declared with an In (nominal discharge current) and Imax (maximum discharge current). Most consumer-unit-mounted SPDs are Type 2.
Type 3 SPD — tested with a combination waveform and intended for the finer level of protection close to sensitive equipment. Type 3 devices live downstream of the main Type 2 device — at a sub-board, in an equipment rack, or as a socket-outlet or plug-in unit serving an item of high-value electronics.
Combined-type devices — many modern SPDs are declared as Type 1+2 or Type 1+2+3. These are convenient at the origin of an installation that has an LPS overhead, because one chassis covers the impulse and the induced events.
Selecting the right Type starts with the question: is there a Lightning Protection System? If yes, you need Type 1 (or combined 1+2) at the origin. If no, you typically need Type 2 at the origin. Then, separately, decide whether you also need Type 3 close to sensitive equipment. The two decisions are independent — fitting Type 3 alone, without a Type 2 upstream, leaves the Type 3 device exposed to events well beyond its rating and will not deliver compliant protection.
Don't buy Type 3 without Type 2
A Type 3 SPD installed at a sub-board without a Type 2 device upstream at the origin is not Section 443 compliant. Type 3 devices are co-ordinated downstream protection — they assume an upstream Type 2 device has already clamped the bulk of the event.
For a deeper dive into device construction and how the metal-oxide varistor (MOV) or spark-gap technology actually clamps the transient, see our SPD surge protection article.
05 · BS 7671 A4:2026
Overvoltage Categories (Regulation 443.4)
Table 443.2 sets out four overvoltage categories (OVC I to OVC IV) that describe the level of transient overvoltage a piece of equipment must withstand at its terminals before it is considered damaged. The categories are progressive: OVC IV equipment is built to withstand more than OVC III, which is built to withstand more than OVC II, and so on. Selecting the right SPD at the origin is then a matter of clamping the transient down to a residual voltage Up at the equipment terminals that is below the equipment's declared withstand category.
OVC IV — equipment for use at the origin of the installation (service entrance side). Electricity meters, ripple-control equipment, primary overcurrent protective devices.
OVC III — equipment for use in the fixed installation. Distribution boards, fixed wiring, socket outlets, fixed motors, industrial control gear.
OVC II — equipment intended to be supplied from the fixed installation. Domestic appliances, portable tools, most consumer electronics.
OVC I — equipment intended for connection to a circuit where measures have been taken to limit transient overvoltages to a specifically low level. Computer logic and electronic equipment whose internal supply has its own filtering or isolation.
The practical relevance for SPD selection is that the residual voltage Up declared on the device must be lower than the impulse withstand voltage Uw of the equipment it protects, with an appropriate margin for the connecting conductors. For a 230/400 V installation, Table 443.2 gives 6 kV for category IV, 4 kV for III, 2.5 kV for II and 1.5 kV for I. An SPD with a declared Up of 1.5 kV at the origin, plus a well-controlled installation with short connection conductors, will sit comfortably below that limit.
06 · BS 7671 A4:2026
Section 534 — Installation Requirements
Section 534 ("Devices for protection against transient overvoltages") is where the regulation gets unforgiving. A perfectly specified Section 443 SPD will deliver no protection at all if it is installed with the wrong conductor length, the wrong topology, or the wrong upstream device. The headline rule electricians need to remember:
Total connecting-conductor length must be short
Regulation 534.4.8 says the total wiring length between the connection points of the SPD assembly should preferably not exceed 0.5 m and in no case exceed 1.0 m. If it exceeds 0.5 m you must choose an SPD with a lower voltage protection level, add a second coordinated SPD near the equipment, or use the Figure 534.9 arrangement with an intermediate earthing terminal. A 1 m conductor carrying 10 kA (8/20) adds about 1,000 V.
Use parallel ("V-shape") connection at the busbar — the SPD is teed off the live conductor and bonded to the main earthing terminal with the shortest practicable conductors. Do not loop the live or neutral through the SPD; tee it.
Keep the total lead length preferably within 0.5 m and never over 1.0 m (Regulation 534.4.8). Earthing conductors must be at least 6 mm² copper for a Type 2 SPD at the origin, or 16 mm² for Type 1; line connections at least 2.5 mm² (Type 2) or 6 mm² (Type 1) (Regulation 534.4.10).
Provide a backup overcurrent device upstream of the SPD, selected according to the SPD manufacturer's declared maximum backup overcurrent rating. This protects the SPD against end-of-life short-circuit failure and ensures the installation's prospective fault current does not exceed the SPD's declared Iscr (short-circuit current rating).
Where the upstream device is shared with the installation supply, confirm that the discrimination between the backup OCD and downstream devices is acceptable — an SPD failure should not trip the entire supply.
Earth the SPD to the main earthing terminal of the installation, not to a separate rod or to a structural steel that has not been confirmed as bonded to the MET. The SPD only works if its earth reference is the same as the equipment it is protecting.
Coordinate the SPD with RCD protection: where the SPD is on the load side of an RCD, that RCD must have a surge current immunity of at least 3 kA 8/20 (Type S RCDs meet this), and Type 1 SPDs downstream of an RCD are not recommended (Regulation 534.4.7).
Bury the length issue at first fix
On a consumer unit replacement, decide where the SPD will live before you punch the gland holes. Putting the SPD on the far side of the board from the meter tails almost guarantees you exceed the 0.5 m practical target. Mount it as close to the incoming way as the consumer unit layout allows.
07 · BS 7671 A4:2026
SPD Coordination and Cascade
For installations that need protection at multiple levels — origin, sub-board and equipment — Section 534 requires that the SPDs be coordinated. Coordination means that when a transient arrives at the origin, the upstream device clamps the bulk of the current and the downstream device handles only the residual that gets past. The two devices must share the load in a way that is consistent with both manufacturers' declared performance.
Energetic coordination — the let-through energy of the upstream device must be below the survivability rating of the downstream device. Most SPD manufacturers publish coordination tables for their own product family that an electrician can lift directly.
Voltage coordination — the residual voltage Up at each stage steps down progressively. Type 2 at the origin typically clamps to around 1.2 to 1.5 kV; a downstream Type 3 then clamps further to around 0.7 to 0.9 kV at the equipment.
Distance coordination — the cable length between two SPDs affects how they share the surge. Follow the manufacturer's coordination data for the minimum separation, or use a declared coordinated pair.
Cross-brand coordination — if upstream and downstream SPDs are from different manufacturers, verify coordination using the published Up and let-through values rather than assuming compatibility. The safer path is single-manufacturer coordinated sets.
In domestic and small-commercial practice, most installations need only a single Type 2 (or combined Type 1+2) at the origin. Cascade only becomes a routine design question on larger sites with multiple sub-boards, in installations that include particularly sensitive electronics, or where part of the building has been retrofitted with on-site generation.
In the app
Try Elec-Mate free for 7 days
19 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.
Installations with solar PV, battery storage and bidirectional EV charging need surge protection thought through on both the AC and DC sides. The AC origin device is chosen under Regulation 443.4.1 and Section 534 like any other installation; the DC side follows Section 712 for PV and the equipment manufacturers' instructions.
AC side — install Type 2 (or Type 1+2 where a structural LPS is present or where the supply is overhead) SPDs at the origin of the AC installation. This is the same Section 534 device an electrician would specify on any other dwelling. Tested to BS EN 61643-11.
DC side — install DC-rated SPDs on the PV array DC cabling between the array and the inverter, selected and installed in accordance with BS EN 61643-31 (PV applications). On longer DC runs, an SPD is needed at both ends of the cable.
Battery DC — for BESS, the DC busbar between the battery and the hybrid inverter needs its own SPD, sized to the system DC voltage (rated Uc above the maximum continuous DC voltage of the array or battery), and as specified by the battery and inverter manufacturers.
EV charging — for a unidirectional charge point downstream of the consumer unit, the origin SPD usually covers the AC side. For vehicle-to-grid (V2G / V2H) installations the inverter's DC port may also need its own DC SPD; follow the inverter manufacturer's instructions and Section 722.
Lightning Protection System — where a structural LPS is fitted to the roof on which the PV is installed, the AC origin device should be Type 1 (or 1+2) and the DC SPDs on the array should be selected with the LPS Iimp share in mind. Coordinate with the LPS designer.
Section 534 length rules apply to DC too
The "as short as practicable, below 0.5 m where possible" Section 534 rule applies on the DC side as well as on the AC. On a roof-mounted array with cabling routed away from the inverter, an SPD mounted in the inverter enclosure will rarely sit within 0.5 m of the panel string. Mount the DC SPD at the array end as well, or use a combined SPD-equipped DC isolator close to the panels.
09 · BS 7671 A4:2026
EICR Coding for Missing or Failed SPDs
One of the most frequently asked questions from inspectors since Amendment 2 introduced strengthened SPD requirements has been: how do I code an installation that does not have surge protection? The answer under A4:2026 is unchanged in principle but tighter in practice. The codes available are C1 (immediate danger), C2 (potentially dangerous), C3 (improvement recommended) and FI (further investigation required). The right code depends on what the installation actually contains and what the consequence of a transient event would be.
C3 (improvement recommended) — the standard default for a domestic or small-commercial installation that has no SPDs where Section 443 would now require them. The consumer unit is older than A4:2026 and the absence is a non-compliance with the current edition, not an immediate danger. C3 communicates to the client that the absence should be remedied at the next opportunity (typically the next CU replacement).
C2 (potentially dangerous) — defensible where the consequence limbs in Regulation 443.4.1 apply. If the installation contains life-safety systems, medical equipment, fire detection central units, or other equipment whose failure during a transient event would create a real and present risk to people (limb (a)), C2 is the appropriate code.
C1 (immediate danger) — rarely the right code for the mere absence of an SPD. C1 is reserved for situations where danger to persons or property is present and immediate. An SPD that has visibly failed in a way that exposes live parts, or that has burned out the consumer unit, may justify C1.
FI (further investigation required) — appropriate where the inspector cannot determine without testing whether an installed SPD is still serviceable. Modern SPDs include a status window (green / red flag); if it is red, replace the device. If the window is missing or unreadable, FI is the honest call.
Notes on the schedule — whichever code is recorded, the inspector should reference Regulation 443.4.1 and Section 534 in the observation, and explicitly note whether the consequence limb (serious injury/loss of life, or significant financial or data loss) or the owner-declaration route drove the coding.
C2 or C3: use the consequence as your guide
There is no fixed code for a missing SPD, but the Regulation 443.4.1 consequence limbs are a sensible guide. Where an overvoltage could put lives at risk, many inspectors would code the absence C2; where neither limb applies, C3 is the usual code.
There is no fixed code for a missing SPD; the inspector judges the risk. Record why you chose the code, and note any owner declaration declining SPDs if one exists.
10 · BS 7671 A4:2026
What Specifically Changed in A4:2026
Pulling together the regulation-level changes A4:2026 introduces into Section 443 and Section 534:
Amendment 2 (2022) deleted the Calculated Risk Level calculation (Regulation 443.5 and Table 443.1). Since then Regulation 443.4.1 requires protection unless the owner declares it is not required; Amendment 4:2026 keeps that rule.
Amendment 4:2026 deleted Annex B443, the informative guidance that accompanied Section 443.
The Section 534 rules are unchanged in substance: lead length preferably within 0.5 m and never over 1.0 m (534.4.8), minimum conductor sizes (534.4.10) and RCD coordination (534.4.7).
The model forms have carried SPD fields since Amendment 2, so the presence, type and status of SPDs are recorded on EICs and EICRs.
Elsewhere, A4:2026 brings protective neutral bonding (PNB), Table 52.1 and a new Chapter 57 for batteries. The AFDD requirement in Regulation 421.1.7 dates from A2:2022, with A4:2026 only rewording the high rise premises entry. See our BS 7671 AFDD rules guide and the broader BS 7671 A4:2026 summary.
Audit your design library against A4:2026
Any template text (RAMS, EICR observation libraries, consumer unit specifications) that still refers to the Regulation 443.5 risk calculation is out of date. Replace it with the Regulation 443.4.1 rule and the owner declaration.
11 · BS 7671 A4:2026
Commissioning, Testing and Handover
An SPD is not a tested device in the same sense as an RCD — there is no equivalent of an RCD trip test that an electrician performs on energisation. What there is, however, is a body of checks at commissioning that confirm the device is fitted correctly, that the upstream backup OCD is in place and the right size, and that the SPD's status indicator is reading healthy. Those checks belong on the Schedule of Inspections.
Visual inspection — confirm the SPD is the correct Type (1, 2, 1+2 or 3) for its position in the installation, that its Uc (maximum continuous operating voltage) is appropriate for the system voltage, and that its status window reads healthy.
Connection inspection — confirm the live and earth connecting conductors are as short as practicable, parallel-connected at the busbar, and that the total length is below 1 m. Photograph the installation for the records.
Backup OCD verification — confirm the upstream backup overcurrent device is in place and sized in accordance with the SPD manufacturer's declared maximum backup OCD. Record the type and rating on the schedule.
Earth path verification — confirm the SPD's earth lead lands on the main earthing terminal of the installation, not on a separate rod or a non-bonded structural item.
RCD coordination — verify the SPD is upstream of the RCD/RCBO protection wherever this is achievable. Where the SPD is downstream of an RCD, confirm the RCD is Type S or otherwise rated for the SPD's discharge current and will not nuisance-trip.
Documentation — record the SPD make, model, Type, Uc, Up, In, Iimp (where applicable), and the backup OCD type and rating on the EIC schedule of inspections. Hand the client the SPD manufacturer's data sheet alongside the certificate.
For consumer-unit-mounted SPDs, the device is part of the same enclosure as the rest of the assembly, and the new A4:2026 EIC model form makes provision in the schedule of inspections for the SPD entry to be ticked off. Make sure this is captured at energisation rather than being treated as an extra item the electrician scribbles on the back of the form.
12 · BS 7671 A4:2026
SPD Lifespan, Status Indication and Replacement
Unlike most other parts of the installation, an SPD is consumable. Each transient event the device clamps degrades its internal varistors slightly, and large events can take the device out of service in a single hit. Section 534 therefore expects the device to have a clear status indicator visible without dismantling the enclosure, and Section 443 expects the installation's periodic inspection regime to check that indicator.
Status window — almost all current-generation Type 2 SPDs include a flag that reads green when the device is serviceable and red (or shows a fault symbol) when the device has reached end of life. The flag should be visible without removing the consumer unit cover.
Replacement — when the status flag indicates failure, the SPD module is replaced as a unit. Most manufacturers design the device as a plug-in cassette so the replacement is a five-minute job with the supply isolated.
Service life — in a quiet electrical environment, a Type 2 SPD will typically deliver 10+ years of service. In an exposed location with frequent overhead-supply switching events, the same device may need replacement after a single severe lightning season.
Whole-device end-of-life — when the consumer unit reaches end-of-life and is replaced under A4:2026, the SPD will be replaced as part of the new assembly; do not transplant a 10-year-old SPD into a new CU.
Periodic inspection — at every EICR, the inspector should photograph and record the SPD status. A failed indicator drives an FI (further investigation) or a recommendation to replace, depending on whether the inspector has confirmed the failure on site.
Client briefing matters
At handover, brief the client on the SPD status window. Show them where it is, what green means, what red means, and what to do (call you back) if it changes. A two-minute conversation at handover turns a passive device into something the householder is willing to glance at every few months.
13 · BS 7671 A4:2026
Building Section 443 Compliance into Daily Practice
For most UK electricians, the Section 443 / Section 534 workflow now sits inside the standard consumer-unit-replacement and EICR routines. The Elec-Mate platform supports this in three places:
EIC and EICR tools — the schedule of inspections includes A4:2026-aligned SPD line items, the schedule of test results captures the SPD make, model, Type and Uc, and the report rendering keeps the SPD entry visible at handover.
Circuit Designer — assists with selecting Type 1 vs Type 2 vs Type 3 at the origin and at sub-boards, and with sizing the upstream backup overcurrent device against the SPD's declared maximum backup OCD.
RAMS Generator — produces the safe-working method statement that wraps around any consumer unit replacement, including the safe isolation steps that precede the SPD installation and the energisation steps that follow it.
For the working electrician, the takeaway is simple: fit SPDs as standard, and only leave them out where the owner has declined them in writing and accepts the risk.
How to Apply Section 443 on a Consumer Unit Replacement
A practical six-step workflow that takes a working electrician from "is an SPD needed?" through to "SPD installed, tested and on the certificate" under BS 7671:2018+A4:2026.
1
Run the consequence check first
Apply the Regulation 443.4.1 consequence test: could the overvoltage result in (a) serious injury to, or loss of, human life, or (c) significant financial or data loss? If either limb applies, SPDs are required and the owner cannot opt out.
2
Otherwise, fit SPDs unless the owner declines
Where neither limb applies, SPDs are still required unless the owner declares they are not wanted because any loss or damage is tolerable and they accept the risk. If they decline, get the declaration in writing and keep it with the certificate.
3
Select Type 1, Type 2 or combined
If the structure has an external lightning protection system or protection against direct lightning, specify a Type 1 (or combined Type 1+2) at the origin (Regulation 534.4.1.3). Otherwise, specify a Type 2 at the origin. Where downstream sensitive equipment is present, add coordinated Type 3 at the equipment.
4
Plan the Section 534 installation
Locate the SPD as close to the incoming way of the consumer unit as the assembly allows. Plan parallel ("V-shape") connection at the busbar with total connecting-conductor length preferably within 0.5 m and never over 1.0 m. Confirm the upstream backup OCD type and rating against the SPD manufacturer's declaration.
5
Install, isolate, energise and verify
Carry out the consumer unit replacement under a safe isolation procedure. On energisation, confirm the SPD status indicator reads healthy, the backup OCD is in service, and the SPD earth lead lands on the main earthing terminal. Photograph the installation for the project record.
6
Certify and hand over
Tick the SPD line items on the schedule of inspections and capture the SPD make, model, Type, Uc, Up, In (or Iimp for Type 1) on the schedule of test results in the A4:2026 EIC. Brief the client on the status window and what to do if it changes. File the certificate, the schedule, and the photographs together.
Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.
Fantastic app for electricians
I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.
Absolutely amazing
I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.
Trusted by electricians across the UK
Real feedback from electricians and apprentices
“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”
Daniel Palmer
Sole Trader · DP Electrical
“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”
Nathan Perry
Electrician · NP Electrical Services
“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”
Jake Pizey