If the 3-phase installation includes generation equipment — solar PV, wind turbines, or battery storage — Engineering Recommendation G99 applies. This is the DNO's process for managing connections of generation equipment to the distribution network.
For single-phase generation up to 3.68 kW, or 3-phase generation up to 3.68 kW per phase (11.04 kW total), the simpler G98 notification process applies. For anything above these thresholds, G99 application and approval is required before the system can be energised.
G99 applications require detailed technical information about the generation equipment, inverter specifications, protection settings, and the proposed connection arrangement. The DNO will assess whether the local network can accommodate the generation and may require network upgrades or impose export limitations.
For electricians installing 3-phase solar PV or battery storage systems, understanding the G99 process is essential. The application should be submitted early in the project timeline as DNO approval can take 4 to 8 weeks.