EV LEGISLATION GUIDE

EV Charging Regulations UK 2026: Laws & Standards for EV Chargers

The complete legal framework for EV charging in the UK — the Electric Vehicles (Smart Charge Points) Regulations 2021, Building Regulations Part S, BS 7671 Section 722, the IET Code of Practice, and the Public Charge Point Regulations 2023 — explained clearly for electricians, businesses, and property developers.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

14 min readUpdated 2026-06-10Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

Do I need to notify an EV charger installation?

Yes. Installing an EV charge point is notifiable electrical work — it normally adds a new dedicated circuit, so it must be notified under the Building Regulations (Part P in England) and certified to BS 7671. It must comply with Section 722, including a dedicated RCD with DC fault detection, and is registered either through a competent person scheme or via building control.

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer — DP Electrical

Key Takeaways

  • 1The Electric Vehicles (Smart Charge Points) Regulations 2021 (SI 2021/1467) make smart functionality mandatory for all new AC charge points up to 22kW sold or installed in Great Britain from 30 June 2022.
  • 2Building Regulations Part S (England) requires new non-residential buildings with more than 10 parking spaces to have at least one active charge point per 5 spaces, and cable ducting for all remaining spaces, from 15 June 2022.
  • 3BS 7671:2018+A4:2026 Section 722 sets out the electrical installation requirements for EV charging installations, including earthing, protective devices, cable sizing, and testing requirements. A4:2026 was issued 15 April 2026 (may be implemented immediately) and replaces A2:2022+A3:2024 from 15 October 2026.
  • 4The IET Code of Practice for Electric Vehicle Charging Equipment Installation (5th Edition, 2023) is the authoritative installation guidance document referenced by OZEV, NICEIC, and NAPIT for EV installer certification.
  • 5The Public Charge Point Regulations 2023 require publicly accessible charge points above 8kW to support contactless payment and meet 99% availability requirements — enforced by the Office for Zero Emission Vehicles.
01 · EV Legislation Guide

Electric Vehicles (Smart Charge Points) Regulations 2021

The Electric Vehicles (Smart Charge Points) Regulations 2021 (SI 2021/1467) were made under powers in the Automated and Electric Vehicles Act 2018. They came into force on 30 June 2022 and apply to all new privately-owned AC charge points up to 22kW sold or installed in Great Britain from that date.

  • Scope — applies to charge points at homes, workplaces, and private destinations (e.g., hotel car parks, supermarkets) that are not publicly accessible and are AC Mode 3 up to 22kW. Does not apply to public charge points (covered by PCP Regulations 2023) or DC charge points.
  • Mandatory smart functionality — all qualifying charge points must support: scheduled charging, randomised startup delay (up to 10 minutes), demand-side response capability, energy metering and monitoring, and minimum cybersecurity standards.
  • Default off-peak setting — charge points must be pre-configured to charge during off-peak hours (midnight to 8am Monday to Friday, midnight to 11am Saturday and Sunday) unless the user actively changes this. This 'smart default' aims to shift demand away from peak grid periods.
  • Enforcement — OZEV can issue financial penalties to manufacturers and importers of non-compliant charge points. Electricians who install non-compliant charge points risk losing OZEV-approved installer status.

See our full guide to smart EV charging for a detailed explanation of each smart functionality requirement and how it affects installation and commissioning.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · EV Legislation Guide

Building Regulations Part S — EV Infrastructure

Part S of Schedule 1 to the Building Regulations 2010 (England) was introduced by the Building Regulations etc. (Amendment) (England) Regulations 2021 (SI 2021/1392) and came into force on 15 June 2022. It requires EV charging infrastructure in new and certain renovated buildings.

  • New residential dwellings with parking — each dwelling must have an EV charge point (minimum 7kW) or, where a charge point is not possible due to the electrical supply, a cable route (ducting) to enable future installation. This includes houses, flats, and houses converted into flats.
  • New non-residential buildings (more than 10 spaces) — at least one active charge point per 5 parking spaces (rounded down), plus cable routes for all remaining spaces. The charge point must be a minimum 7kW and must meet the Smart Charge Points Regulations.
  • Major renovation of non-residential buildings — where the renovation includes the car park or the car park has more than 10 spaces and the total cost of the renovation exceeds 25% of the building's value, the same charge point ratio applies. Buildings completed before 15 June 2022 are not retrospectively required to comply.
  • Approved Document S — the technical guidance for Part S compliance is set out in Approved Document S (2021 edition). It covers the minimum charge point specification, cable route requirements, metering, and documentation requirements for building control sign-off.

Wales and Scotland have separate building regulations with similar but not identical provisions. Northern Ireland follows the Building Regulations (Northern Ireland) 2012 (as amended), which currently has more limited EV infrastructure requirements.

03 · EV Legislation Guide

BS 7671:2018+A4:2026 Section 722 — EV Charging Installations

Section 722 of BS 7671:2018+A4:2026 (the 18th Edition IET Wiring Regulations, Amendment 4) sets out the specific electrical installation requirements for EV charging equipment. A4:2026 contains significant changes to Section 722 — installers working to A2:2022 should review the revised regulation text before certifying new work. A4:2026 was issued 15 April 2026 and may be implemented immediately; A2:2022+A3:2024 will be withdrawn on 15 October 2026.

  • Regulation 722.411.4 — Earthing (TN-C-S/PME) — a PME earthing facility shall not be used directly for the protective conductor contact(s) of an outdoor charging point. One of four compliant alternatives must be used: (b) an installation earth electrode connected to the MET, sized so that the voltage between the MET and Earth does not exceed 70 V RMS under an O-PEN (open-circuit PEN conductor) fault — Annex A722.3 gives the calculation method; (c) a device that disconnects the vehicle from live conductors and from protective earth within 5 s if the CPC-to-Earth voltage exceeds 70 V RMS; (d) a device that disconnects within 5 s if the line-to-neutral voltage falls outside 207–253 V RMS; or (e) equivalent protective functionality within the charging equipment. Note: 200 Ω is not the normative criterion — the actual requirement is the 70 V RMS voltage limit. For TN-S systems, a separate electrode is not required but is best practice.
  • Regulation 722.531 — Protective devices — EV charging circuits must be protected by an RCD with rated residual operating current not exceeding 30mA. Additionally, protection against DC fault currents is required, either by using a Type B RCD or an RCM (residual current monitor) with appropriate disconnection. Most dedicated EV chargers incorporate internal DC fault current protection, removing the need for a Type B RCD at the distribution board.
  • Regulation 722.533 — Overcurrent protection — the circuit protective device must be rated for the maximum continuous operating current. For a 32A (7.4kW) charger, the circuit is typically protected by a 32A Type B or Type C MCB. For 40A (9.6kW, uncommon in UK), a 40A MCB is required.
  • Section 537 (applied via Section 722) — Isolation — a means of isolation must be provided for the EV charging installation, capable of isolating both live conductors (L and N on single-phase). This is typically provided by a double-pole MCB or isolator at the consumer unit.
  • Regulation 722.311.201 — Load curtailment (A4:2026) — load curtailment, including automatic or manual load reduction or disconnection, may be taken into account when determining the maximum demand of the installation or part thereof. This is the regulatory basis for dynamic load management systems on multi-charger commercial or fleet sites, allowing the supply to be sized for managed simultaneous demand rather than worst-case peak load.
  • Section 722 certification — EV charging installations must be inspected, tested, and certificated in accordance with Part 6 of BS 7671. Use the Elec-Mate EV charging certificate to complete the required documentation on site.
04 · EV Legislation Guide

IET Code of Practice for EV Charging Equipment Installation

The IET Code of Practice for Electric Vehicle Charging Equipment Installation (5th Edition, 2023) is the definitive installation guidance document for UK EV charger installers. Published by the Institution of Engineering and Technology, it is co-sponsored by BEAMA, the Electrical Contractors' Association, and the Electricity Network Association.

  • Status — not statutory law, but recognised by OZEV, NICEIC, NAPIT, and the EV installer certification bodies as the authoritative guidance. Following the Code of Practice is the standard method of demonstrating competence and compliance with BS 7671 Section 722.
  • 5th Edition coverage — the 2023 edition covers Mode 2 and Mode 3 AC charging, DC charging, smart charging requirements under the 2021 Regulations, load management, solar integration, energy storage, earthing arrangements for all system types, cable sizing, protective devices, and documentation requirements.
  • OZEV installer assessment — the OZEV-approved installer qualification (required for grant-funded installations) tests knowledge of the Code of Practice. Installers must demonstrate understanding of earthing, protective device selection, load management, and certification requirements.
  • GN3 inspection requirement — when inspecting EV charging installations, GN3 (IET Guidance Note 3: Inspection and Testing, 9th Edition) requires that the inspector shall consult the IET Code of Practice to determine appropriate inspection items, tests, and acceptance criteria specific to EV equipment. Inspectors cannot rely solely on the standard Appendix 6 schedule for EV work.
  • Chapter 82 — Prosumer's Electrical Installations (A4:2026) — EV installations that incorporate solar PV generation, battery storage, or bidirectional (V2G) charging must also comply with Chapter 82 of BS 7671:2018+A4:2026. Chapter 82 is a new chapter covering design, erection, and verification of all low-voltage installations where local production or storage of energy is present (Prosumer's Electrical Installations). This is increasingly relevant given the growth of solar-integrated and energy-storage-backed EV installations covered by the IET Code of Practice 5th Edition.
  • Purchasing the Code of Practice — the 5th Edition is available from the IET Shop (theiet.org) in print and digital formats. The digital edition includes hyperlinked cross-references and is updated between print editions when regulations change.

Try Elec-Mate free for 7 days

16 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.

Start free trial
Download on the App StoreGet it on Google Play
05 · EV Legislation Guide

Public Charge Point Regulations 2023

The Public Charge Point Regulations 2023 (SI 2023/1168) set standards for publicly accessible EV charge points in Great Britain above 8kW. These regulations apply to operators of charge points accessible to the general public, including retail car parks, motorway service areas, and on-street charging.

  • Contactless payment — publicly accessible charge points above 8kW must accept contactless payment (debit and credit card) without requiring a subscription, app download, or pre-registration. This ended the practice of network-only charging that locked out drivers without a specific RFID card.
  • Transparent pricing — prices must be displayed clearly per kWh before the session starts. Session fees, connection fees, and time-based fees must be disclosed. Hidden fees or unclear pricing are prohibited.
  • Availability — operators of rapid chargers (50kW+) must maintain 99% annual availability and publish availability data. Failure to maintain availability exposes operators to enforcement action by OZEV or the CMA.
  • Data reporting — operators must submit data to the National Charge Point Registry (NCPR), including charge point location, power rating, connector type, status, and pricing. This data is publicly accessible and used by navigation apps.
06 · EV Legislation Guide

Enforcement & Penalties

Multiple bodies have enforcement powers over different aspects of EV charging legislation. Understanding the enforcement landscape helps electricians and charge point operators avoid costly penalties.

  • OZEV — Smart Charge Points Regulations — OZEV can issue civil penalties to manufacturers and importers of non-compliant charge points. Maximum penalty of £10,000 per non-compliant unit. OZEV-approved installer status can be revoked for repeated installation of non-compliant equipment.
  • Building control — Part S — failure to comply with Part S during new construction or renovation can result in building control refusing to issue a completion certificate, preventing the building being occupied. Retrospective regularisation is possible but costly.
  • CMA — Public Charge Point Regulations — the Competition and Markets Authority enforces the Public Charge Point Regulations 2023. The CMA has powers to issue compliance notices and ultimately seek court orders requiring compliance. Financial penalties are available for continued non-compliance.
  • Local authorities — planning — installing an EV charger without required planning permission can result in enforcement notices requiring removal. Listed building consent violations can result in criminal prosecution.
07 · EV Legislation Guide

For Electricians: Staying Compliant with EV Legislation

EV charging legislation is evolving rapidly. Electricians who keep their knowledge current and maintain OZEV-approved installer status are well-positioned to capture a growing market. The key obligations are straightforward: install only OZEV-approved smart chargers, follow BS 7671 Section 722 and the IET Code of Practice, and certify every installation correctly.

Certificate Every Installation Correctly

Use the Elec-Mate EV charging certificate app to complete a BS 7671-compliant electrical installation certificate for every EV charger you install. The app covers supply details, earthing arrangements, protective device ratings, RCD type, insulation resistance, earth electrode resistance, and all required test results — then exports a professional PDF for the client and OZEV records.

Apply WCS Grants for Your Clients

As an OZEV-approved installer you can apply for WCS grants on behalf of your business clients, deducting £350 per socket from your invoice. Use the Elec-Mate quoting app to show grant deductions clearly and increase your quote acceptance rate.

EV Charger Installation Regulations UK (BS 7671 Section 722)

EV charge point rules explained: BS 7671 Section 722, PEN-fault protection, RCD type and DNO notification. What every installer must get right.

Try it free for 7 days
Download on the App StoreGet it on Google Play

Frequently Asked Questions About EV Charging Regulations UK

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-Day Free Trial — Cancel Anytime, No Hassle

Complete EV Charging Certificates on Your Phone

Join 1,000+ UK electricians using Elec-Mate for EV charging certificates, quoting, and job management. Stay compliant and win more work. 7-day free trial, cancel anytime.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical

From £6.99/mo after trial — less than a coffee a week

or download the app
Download on the App StoreGet it on Google Play
7 days free, then from £6.99/moCancel in one tap — no calls, no hassleiOS, Android & WebBS 7671 compliant
16
Certificate Types
70+
Calculators
46+
Training Courses
8
AI Agents

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy