TESTING GUIDE

Commissioning an Electrical Installation: From Testing to Handover

Commissioning is the final stage before an electrical installation is put into service. It covers initial verification testing, functional checks of every device, snagging, documentation, and formal handover to the client. This guide explains the complete process for domestic and commercial installations.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

10 min readUpdated 2026-06-10Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

What is commissioning an electrical installation?

Commissioning is the final stage before an installation is put into service. It combines initial verification (inspection and testing to BS 7671 Chapter 64), functional testing of every device under Regulation 643.10, snagging of minor defects, completion of all documentation, and formal handover. Testing confirms each circuit; commissioning confirms the whole installation works and is ready for the client to use.

On a simple domestic job the distinction is small — verification effectively is the commissioning. On commercial and industrial projects commissioning is a separate, programmed phase with its own records and sign-off.

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer — DP Electrical

Key Takeaways

  • 1Commissioning is the final stage before an electrical installation is put into service — it includes initial verification, functional checks, and handover documentation.
  • 2Commissioning goes beyond testing: it confirms every system, control, and device operates correctly as a complete installation, not just as individual circuits.
  • 3Functional checks cover all switchgear, interlocks, controls, emergency systems, and automation to confirm they operate as designed.
  • 4The handover package should include the EIC (or MEIWC), schedule of test results, as-built drawings, O&M manuals, and warranty documents.
  • 5Elec-Mate produces the EIC, schedule of test results, and professional PDF documentation needed for the commissioning handover — all from site.
01 · Testing Guide

What Is Commissioning an Electrical Installation?

Commissioning is the process of bringing an electrical installation from completion of physical installation through to handover as a fully tested, documented, and operational system. It is the final stage before the installation is put into service and the client takes ownership.

Commissioning includes initial verification (inspection and testing to BS 7671 Chapter 64), functional checks of all equipment and controls, snagging and rectification of minor defects, completion of all documentation (certificates, drawings, manuals), and formal handover to the client.

For a simple domestic job — such as a consumer unit replacement or a new circuit installation — commissioning is straightforward: test the installation, confirm everything works, issue the EIC, and hand it to the client. For a large commercial or industrial project, commissioning is a structured phase of the project with its own programme, team, and sign-off procedures.

Regardless of the scale, the principle is the same: do not hand over an installation until you have confirmed it works correctly, documented the evidence, and given the client everything they need to use and maintain it safely.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Testing Guide

Commissioning vs Testing: What Is the Difference?

Testing (initial verification) confirms that individual circuits meet BS 7671 requirements — continuity, insulation resistance, earth fault loop impedance, RCD operation, and so on. Commissioning confirms that the installation works as a complete system.

Testing Confirms...

  • Each circuit has correct continuity
  • Insulation resistance meets minimum values
  • Zs values are within limits
  • RCDs trip within required times
  • Polarity is correct throughout

Commissioning Also Confirms...

  • All lights, sockets, and fixed appliances work
  • Controls and automation operate as designed
  • Emergency systems function correctly
  • Interlocks and safety devices work
  • All documentation is complete

Testing answers the question: "Does each circuit meet BS 7671?" Commissioning answers the broader question: "Does the entire installation work as intended and is it ready for the client to use?"

03 · Testing Guide

How Long Does Commissioning Take?

Commissioning time scales with the complexity of the installation, not just its size. The instrument testing of initial verification is usually the largest single block of time, but functional checks, snagging and documentation all add to it. These are indicative planning figures, not a quote — always build commissioning into the project programme from the start rather than squeezing it into the final day.

Installation type
Typical duration
Main driver
Consumer unit change / single new circuit
2–4 hours
Dead and live testing
Full domestic rewire
Half a day to a day
Volume of circuits to test
Office / retail fit-out
2–5 days
Multiple boards, controls, emergency systems
Industrial / motor control
A week or more
MCC, PLC logic, standby power proving

For domestic work the documentation can be completed on site as you test — see the testing sequence guide for the order the tests are carried out. On larger projects the commissioning phase is planned, resourced and signed off in its own right.

04 · Testing Guide

Functional Checks: Testing the Complete System

Functional checks go beyond the instrument-based testing of initial verification. They involve physically operating every device in the installation to confirm it works correctly. BS 7671 Regulation 643.10 requires equipment — including switchgear and controlgear assemblies, drives, controls and interlocks — to be functionally tested as appropriate, to verify it is properly mounted, adjusted and installed and operates correctly.

Functional Checks Checklist

  • Switchgear. Operate every MCB, RCBO, RCD, and isolator. Confirm they trip and reset cleanly. Check that no-volt release devices operate correctly.
  • Emergency switching. Test fireman's switches, emergency stop buttons, and any emergency disconnection devices. Confirm they de-energise the correct circuits and can be reset safely.
  • Lighting controls. Test dimmer switches, occupancy sensors, daylight sensors, time switches, and scene-setting controls. Confirm each operates the correct luminaires.
  • Interlocks. Confirm that interlocked devices operate in the correct sequence — for example, an extractor fan that starts when a light switch is operated, or a contactor that energises only when a safety guard is closed.
  • Motor control. Start and stop motors. Check rotation direction. Verify overload protection operates. Confirm emergency stop buttons de-energise the motor.
  • Emergency lighting. Simulate a mains failure and confirm emergency luminaires illuminate. Check that maintained fittings switch from mains to battery supply seamlessly. Confirm exit signs are illuminated and legible.
  • Fire alarm integration. If the electrical installation interfaces with the fire alarm system (for example, cause-and-effect programming, fire damper controls, or stairwell pressurisation), confirm the interfaces work correctly.
  • AFDD verification. Under A4:2026, Regulation 421.1.7 makes AFDDs a requirement for socket-outlet final circuits rated up to 32 A in Higher-Risk Residential Buildings, Houses in Multiple Occupation, purpose-built student accommodation and care homes, and recommends them for single-phase AC socket-outlet final circuits up to 32 A in all other premises. Where AFDDs are fitted, confirm the operational indication (status LED) shows the device is active, then operate the manufacturer-specified test and confirm it resets correctly. Record the outcome on the schedule of test results.

Record the results of all functional checks. For domestic work, this is typically noted on the EIC. For commercial projects, a separate commissioning record sheet is used.

05 · Testing Guide

Documentation Required for Commissioning

Proper documentation is a core part of commissioning. The documentation package serves as evidence that the installation has been tested and is fit for purpose. It is also the reference that future electricians will use when maintaining or modifying the installation. For the full breakdown of what belongs in the pack, see the handover documentation guide.

  • Electrical Installation Certificate (EIC). The formal certificate issued under BS 7671 Regulation 644.1, based on the model in Appendix 6. Includes design, construction, and inspection signatures, plus the schedule of inspections and schedule of test results.
  • Schedule of test results. Every test value for every circuit — R1+R2, IR, Zs, PFC, RCD trip times — recorded on the Appendix 6 model form. Under A4:2026 this single-page schedule has been redrafted and split into a separate schedule of circuit details and a separate schedule of test results, and the operational status of any AFDDs is recorded here. Accompanies the EIC.
  • Circuit charts and labels. Clear identification of every circuit at the distribution board. Required by BS 7671 Regulation 514.9.1. Note: A4:2026 introduced an exception for domestic (household) premises — check the amended regulation text for the precise scope of that exception on residential jobs.
  • As-built drawings. For larger installations, updated drawings showing the actual installed layout, cable routes, distribution board locations, and key equipment positions.
  • Warning notices. All required warning labels fitted — RCD quarterly test notice, dual supply warning, periodic inspection notice (next inspection date), and any non-standard arrangements.

What actually needs handing over depends on the job. A consumer unit change needs the core certificate package; a commercial fit-out adds a full deliverables file. This matrix shows the typical split:

Handover item
Domestic
Commercial
EIC with schedules of inspections and test results
Required
Required
Circuit chart / distribution board labelling
Required
Required
Warning and user instruction notices
Required
Required
Manufacturer instructions for installed equipment
As applicable
Required
As-built drawings
Rarely
Required
O&M manual
Not usually
Required (contractual)
Specialist certificates (fire alarm, emergency lighting)
If installed
Required
Signed handover / training record
Optional
Required

For Part P notifiable work, the EIC must be registered with building control (either directly or through a competent person scheme). Failure to certify notifiable work is a building regulation offence.

Record test results hands-free on site

AI board scanner, voice test entry, and automatic BS 7671 validation — finish the certificate before you leave the property. From £5.99/mo.

Try the certificate tools free
Download on the App StoreGet it on Google Play
06 · Testing Guide

Handover to the Client

Handover is the formal point at which the client takes responsibility for the installation. A good handover ensures the client understands what has been installed, how to use it safely, and what documentation they should keep.

  1. Walk the client through the installation. Show them the consumer unit location, how to identify circuit breakers, how to reset an RCD, and where the main isolation point is.
  2. Explain the RCD test button. Advise the client to press the RCD test button quarterly to confirm the mechanical trip mechanism is working. This is a requirement noted on the warning label at the consumer unit.
  3. Provide all documentation. Hand over the EIC (or MEIWC), schedule of test results, circuit chart, and any relevant manufacturer instructions. Explain that the EIC should be kept with the property deeds or building records.
  4. Advise on the next periodic inspection date. Explain when the next periodic inspection is recommended and why it matters. The date is recorded on the EIC.
  5. Leave your contact details. Provide contact information for any queries or warranty issues. For domestic clients, a simple business card or invoice with contact details is sufficient.

For commercial projects, handover may involve a formal meeting with the client's facilities management team, structured training on specialist equipment, and a sign-off document confirming the client has received all documentation and is satisfied with the installation.

Send the EIC to the client instantly

Finished commissioning? Export the EIC as a professional PDF and send it to the client by email or WhatsApp — before you leave site.

Try it free for 7 days
Download on the App StoreGet it on Google Play
07 · Testing Guide

O&M Manuals: What They Are and When to Provide Them

Operation and Maintenance (O&M) manuals are detailed documents that describe how to operate and maintain the installed equipment. They are standard practice on commercial and industrial projects, and increasingly expected on larger domestic installations.

O&M Manual Contents

  • Installation description — an overview of the electrical system, its design basis, and its key components.
  • Equipment data sheets — manufacturer information, model numbers, ratings, and specifications for all major equipment.
  • Maintenance schedules — recommended maintenance intervals and procedures for each piece of equipment (for example, annual thermographic survey of distribution boards, quarterly RCD test button operation).
  • Spare parts lists — critical spare parts and their suppliers, so replacements can be sourced quickly.
  • Warranty information — warranty periods, conditions, and contact details for each manufacturer.
  • Test certificates — copies of the EIC, schedule of test results, and any specialist certificates (fire alarm, emergency lighting).

For domestic work, a formal O&M manual is not usually required — the EIC, circuit chart, and manufacturer instructions are sufficient. For commercial projects, the O&M manual is a contractual deliverable and must be provided before practical completion is certified under the building contract.

08 · Testing Guide

Commissioning Checklist

Use this checklist to ensure nothing is missed during commissioning. Tick off each item as it is completed:

  • Visual inspection completed per BS 7671 Part 6, Chapter 64 (Reg 641)
  • All dead tests completed: continuity, IR, polarity, earth electrode (if TT)
  • All live tests completed: Zs, PFC, RCD operation, phase sequence (if 3-phase). Remember the tabulated maximum Zs values assume the conductor at its normal operating temperature, so apply the appropriate temperature/rule-of-thumb correction before comparing them against your measured cold values.
  • All test results within BS 7671 limits — no failures outstanding
  • Functional checks completed on all switchgear, controls, and interlocks (Reg 643.10)
  • AFDD operational status confirmed where fitted — manufacturer test operated, reset verified, and outcome recorded on the schedule (Reg 421.1.7 / 643.10)
  • Emergency systems tested (emergency lighting, fire alarm interfaces)
  • Circuit charts installed at distribution boards
  • All warning notices and labels fitted
  • EIC completed and signed
  • Snagging items rectified and signed off
  • Documentation package complete and handed to client
  • Client walkthrough and demonstration completed

Pro tip: Take photographs of the completed installation — the consumer unit (cover on and off), cable routing, earthing and bonding connections, and any concealed wiring before it is covered. These photos are invaluable for future maintenance and can be attached to the EIC in Elec-Mate.

09 · Testing Guide

Commissioning with Elec-Mate

Elec-Mate handles the certification and documentation side of commissioning so you can focus on the testing and functional checks. Here is how it fits into your commissioning workflow:

AI Board Scanner

Photograph the new consumer unit. The AI reads MCB/RCBO ratings and circuit labels from the image. The EIC schedule pre-fills with circuit descriptions and protective device details.

Voice Test Entry

Speak your test results as you work through the test sequence. Dead test results and live test results populate the schedule automatically. AI compares every value against BS 7671 limits.

Instant PDF Handover

The completed EIC exports as a professional PDF. Send it to the client by email or WhatsApp from site. Attach the invoice. The client has the commissioning documentation before you leave the property.

Commission and certify from one app

AI board scanner, voice test entry, automatic BS 7671 compliance checking, and instant PDF export. Complete the EIC on site and hand it over digitally.

Try it free for 7 days
Download on the App StoreGet it on Google Play

Frequently Asked Questions About Commissioning

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-Day Free Trial — Cancel Anytime, No Hassle

Commission and Certify from Your Phone

Elec-Mate handles the EIC, schedule of test results, and PDF export so you can focus on the testing and functional checks. Join 1,000+ UK electricians. 7-day free trial, cancel anytime.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical

From £5.99/mo after trial — less than a coffee a week

or download the app
Download on the App StoreGet it on Google Play
7 days free, then from £5.99/moCancel in one tap — no calls, no hassleiOS, Android & WebBS 7671 compliant
16
Certificate Types
70+
Calculators
46+
Training Courses
8
AI Agents

1,000+ electricians · From £5.99/mo after trial

Cookie Preferences

Manage your privacy settings

We use cookies to enhance your experience and analyse platform usage. Cookie Policy