GUIDE

House Extension Electrics
Wiring & Regulations Guide

Wiring a house extension involves designing new circuits, connecting to the existing distribution board (or installing a sub-main), coordinating with the building project timeline, and ensuring compliance with Part P and BS 7671. This guide covers every aspect of extension electrics — from initial planning through to testing and certification.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

12 min readUpdated 2026-06-10Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer — DP Electrical

Key Takeaways

  • 1A house extension typically requires at least one new lighting circuit and one new socket circuit. Kitchen extensions, bi-fold doors with external lighting, and outbuilding supplies may need additional dedicated circuits.
  • 2The existing consumer unit must have sufficient spare ways for the new circuits. If not, a sub-distribution board fed by a sub-main cable from the main consumer unit is the correct solution — not doubling up circuits on existing ways.
  • 3All new electrical work in a house extension is notifiable under Part P of the Building Regulations. The electrician must either be registered with a competent person scheme or the work must be inspected by Building Control.
  • 4First fix electrical work should be coordinated with the builder — cables must be installed before plastering, insulation, and boarding. Late changes are costly because walls and ceilings must be opened up again.
  • 5External circuits for garden lighting, patio sockets, and security lighting must be protected by 30mA RCD, and cables must be rated for outdoor use or installed in suitable conduit.
01 · Guide

Planning the Electrics for a House Extension

The electrical design for a house extension should be planned at the same time as the architectural design — not as an afterthought once building work has started. The position of the consumer unit, cable routes through the existing house to the extension, socket and light positions, and external circuit requirements all affect the building work and must be agreed before the builder starts.

Start With the Homeowner's Requirements

Discuss what the extension will be used for. A kitchen extension has very different electrical requirements to a bedroom extension or a home office. Key questions: How many sockets are needed and where? What lighting style is preferred (recessed downlights, pendants, track lighting)? Are there any dedicated circuits required (cooker, dishwasher, boiling water tap, electric underfloor heating)? Does the homeowner want external lighting, outdoor sockets, or EV charger preparation?

Assess the Existing Installation

Before designing the extension circuits, assess the existing consumer unit. Count spare ways available. Check the condition of existing wiring — if the existing installation has significant deficiencies, these should be discussed with the homeowner before adding new circuits to it. Consider whether the incoming supply and main fuse are adequate for the additional demand. An EICR on the existing installation before starting extension work is strongly recommended.

Coordinate With the Builder

The builder needs to know where cables will run so that suitable chase routes, floor voids, and wall cavities are maintained. First fix electrical work must happen after the structure is weather-tight but before insulation, boarding, and plastering. Agree the programme with the builder and confirm your attendance dates for first fix and second fix. Late arrival for first fix delays the entire project.

AI Circuit Designer for Extension Planning

Elec-Mate's AI Circuit Designer generates a complete circuit specification for your extension.

Try it free for 7 days
Download on the App StoreGet it on Google Play
Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Guide

New Circuits Required for a House Extension

The number of new circuits depends on the size and use of the extension. As a guide, the following circuits are typically required:

Standard Extension Circuits

  • Lighting circuit — 1.0mm² or 1.5mm² twin-and-earth, protected by a 6A RCBO. One circuit typically serves the entire extension unless there are more than 10-12 lighting points. Consider separate circuits for the extension and any new external lighting.
  • Ring final or radial socket circuit — 2.5mm² twin-and-earth for a ring final (32A RCBO) or a radial circuit (20A or 32A RCBO depending on cable size). One circuit is sufficient for a single-room extension; larger extensions may need two.
  • Cooker circuit — 6.0mm² twin-and-earth, 32A RCBO, if the extension includes a kitchen with an electric cooker or hob. Use cable sizing calculations to confirm the correct size based on the cooker's rated current.
  • Underfloor heating circuit — If electric underfloor heating is specified, this typically requires a dedicated radial circuit sized for the heating mat's current draw. The thermostat is wired between the circuit and the heating mat.
  • External circuits — Garden lighting, external sockets, security lighting, and patio heaters may each require dedicated circuits depending on the load and cable run.

Smoke and heat detectors in the extension must be mains-powered and interconnected with the existing detection system in the main house — this is a Building Regulations requirement.

03 · Guide

Connecting to the Existing Distribution Board

The new circuits for the extension must connect to the property's electrical distribution. There are two main approaches, depending on the capacity of the existing consumer unit.

Option 1: Add to Existing Consumer Unit

If the existing consumer unit has sufficient spare ways (at least as many as the number of new circuits), the new circuits can be connected directly. Each new circuit gets its own RCBO. This is the simplest and most cost-effective approach. However, adding circuits to an existing consumer unit still requires a full Electrical Installation Certificate (EIC) for the new work, not just a Minor Works Certificate, because new circuits are being added.

Option 2: Install a Sub-Distribution Board

If the existing consumer unit is full, or if the extension is large enough to warrant its own distribution, a sub-distribution board can be installed in the extension. This is fed by a sub-main cable from a spare way in the main consumer unit (or a dedicated way added to the main board). The sub-main is sized to carry the maximum demand of all the extension circuits. A typical sub-main for a domestic extension is 10mm² or 16mm² twin-and-earth, protected by a suitably rated device at the main board.

What Not to Do

Never double up circuits on existing ways — connecting two circuits to one MCB or RCBO is not compliant with BS 7671 and creates an overload risk. Never spur new circuits from existing socket outlets as a way of avoiding adding circuits to the consumer unit — a spur is an addition to an existing circuit, not a new circuit. Each new circuit in the extension must have its own protective device at the distribution board.

04 · Guide

Lighting Design for House Extensions

The lighting design in a modern extension typically goes beyond simple pendant fittings. Homeowners expect a professional lighting scheme that creates the right ambience and provides task lighting where needed.

Common Lighting Arrangements

  • Recessed downlights — The most common choice for kitchen and living room extensions. Typically 5W-10W LED GU10 or integrated LED fittings. Space at 60-90cm centres for even coverage. Consider fire-rated downlight cans where the ceiling is a fire barrier (e.g., between floors).
  • Pendant lighting — Over kitchen islands, dining tables, and feature areas. Allow for separate switching from the main ceiling lights so the homeowner can create different lighting scenes.
  • Under-cabinet lighting — LED strip or puck lights under kitchen wall units for worktop task lighting. These can be on the main lighting circuit or on a separate switched fused connection unit.
  • External soffit lighting — Recessed or surface-mounted LED fittings in the extension's soffit or fascia. Provides ambience for outdoor entertaining and security lighting. Must be rated for outdoor use (IP44 minimum).
  • Dimming — Many homeowners want dimmable lighting in extensions. Ensure LED-compatible dimmers are specified — trailing-edge dimmers for LED, not leading-edge dimmers designed for halogen. Check the LED manufacturer's dimmer compatibility list.

All lighting switch positions should be agreed with the homeowner during the design phase. Consider wiring colour conventions for switched live and two-way switching installations.

Try Elec-Mate free for 7 days

16 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.

Start free trial
Download on the App StoreGet it on Google Play
05 · Guide

Socket Layout and Positioning

The number and position of socket outlets in the extension should be planned based on the room's intended use. BS 7671 does not specify a minimum number of sockets, but the IET Guidance Note 1 and the NHBC standards provide recommendations.

1

Kitchen Extension

Allow for 6-8 double socket outlets above the worktop, plus dedicated connections for fixed appliances (oven, hob, dishwasher, washing machine, boiling water tap, fridge/freezer). Position worktop sockets 150mm-200mm above worktop level. Consider USB charging sockets for at least one or two positions.

2

Living/Dining Extension

Allow for double sockets at each seating position, TV/media wall, and any likely desk or table locations. A minimum of 4-6 doubles for a typical single-room extension. Consider floor outlets for central positions away from walls (e.g., kitchen island power, central dining table).

3

Home Office Extension

Multiple doubles at desk level, at least one data point (CAT6 alongside mains), and consider a dedicated circuit for computing equipment if the homeowner has significant IT infrastructure. A separate lighting circuit with task lighting above the desk area is beneficial.

Standard socket mounting height is 450mm from finished floor level (centre of plate). Mounting sockets higher — at 600mm or even desk height (1050mm) — can be more convenient in some situations and improves accessibility. Discuss preferences with the homeowner during the design phase.

06 · Guide

External and Garden Circuits

House extensions often include new external circuits for garden lighting, patio sockets, and security lighting. These have specific requirements under BS 7671:

  • 30mA RCD protection — All outdoor circuits must be protected by a 30mA RCD. With RCBO boards, this is automatic. On dual-RCD boards, ensure external circuits are on an RCD-protected side.
  • Cable type — Cables buried in the ground must be SWA (steel wire armoured) cable or standard cable in suitable conduit. SWA cable must be buried at a minimum depth of 500mm (or deeper if subject to vehicle traffic). Mark the route with warning tape above the cable.
  • IP rating — External accessories must have a suitable IP rating. IP44 minimum for sheltered locations, IP65 or IP66 for exposed locations. Outdoor socket outlets should be IP66 rated with a weatherproof enclosure.
  • Part P notification — New outdoor circuits are notifiable under Part P and must be included on the EIC for the extension work.

Cable Sizing for Extension Circuits

Elec-Mate's cable sizing calculator handles every circuit in your extension project — ring finals, radials, lighting circuits, cooker circuits…

Try it free for 7 days
Download on the App StoreGet it on Google Play
07 · Guide

Part P Notification for Extension Electrics

All new electrical work in a house extension is notifiable under Part P of the Building Regulations. This includes every new circuit, the connection to the existing distribution, and any outdoor circuits. The work requires a full Electrical Installation Certificate (EIC), not a Minor Works Certificate.

There are two routes to compliance:

Route 1: Competent Person Scheme

If the electrician is registered with a competent person scheme (NICEIC, NAPIT, Elecsa, etc.), they can self-certify the work. The scheme provider issues a Building Regulations Compliance Certificate to the homeowner. This is the most common route for professional electricians — it avoids the need for a separate Building Control inspection and is faster and cheaper for the homeowner.

Route 2: Building Control Notification

If the electrician is not registered with a competent person scheme, the homeowner must notify Building Control before the work starts. Building Control will inspect the work and issue a completion certificate. This adds cost (Building Control fees) and time (waiting for inspection appointments). For extension projects, Building Control is usually already involved for the structural work, so this route can be coordinated with the overall building project.

The EIC for extension work must cover the design, construction, and testing of all new circuits. Use Elec-Mate's digital EIC form to complete the certificate on site with all test results validated automatically.

House Extension Electrics — Step-by-Step

Planning and installing electrics for a house extension from design to certification.

1

Design the circuit layout with the homeowner

Walk through the extension plans and agree every socket, light, and switch position. Identify all dedicated circuits (cooker, underfloor heating, external circuits). Design the circuit schedule and cable routes. Check the existing consumer unit for spare capacity. Use Elec-Mate's AI Circuit Designer for a compliant specification.

2

Coordinate with the builder and agree the programme

Confirm dates for first fix (after weather-tight, before insulation and boarding) and second fix (after plastering). Agree cable routes through the existing house if the consumer unit is not adjacent to the extension. Ensure the builder leaves suitable access for cable runs through floors and walls.

3

First fix — run cables and install back boxes

Run all cables from the consumer unit or sub-board position to every accessory point. Install back boxes in agreed positions. Clip cables at correct intervals per BS 7671. Install fire-rated downlight cans and any conduit runs. Label all cables at both ends. Install smoke and heat detector cables.

4

Second fix — fit accessories, connect, and test

After plastering is complete, fit all accessories (sockets, switches, light fittings, cooker connection). Connect all circuits at the consumer unit or sub-board. Carry out the full testing sequence — continuity, insulation resistance, polarity, earth fault loop impedance, prospective fault current, and RCD tests.

5

Complete the EIC and submit Part P notification

Complete the Electrical Installation Certificate with all design, construction, and test data. Submit Part P notification through the competent person scheme or coordinate with Building Control. Issue copies of the EIC to the homeowner. Provide the circuit chart for the consumer unit.

Frequently Asked Questions

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-Day Free Trial — Cancel Anytime, No Hassle

Design and Certify Extension Electrics With Elec-Mate

AI Circuit Designer, cable sizing calculator, digital EIC forms, and Part P documentation — everything for extension projects in one app. 7-day free trial, cancel anytime.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical

From £6.99/mo after trial — less than a coffee a week

or download the app
Download on the App StoreGet it on Google Play
7 days free, then from £6.99/moCancel in one tap — no calls, no hassleiOS, Android & WebBS 7671 compliant
16
Certificate Types
70+
Calculators
46+
Training Courses
8
AI Agents

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy