To fill in a Minor Works certificate: complete one certificate per circuit affected, record the work description, circuit reference, relevant test results, and any limitations, then sign only after every field is verified. Use an EIC instead if the job includes a new circuit or a consumer unit replacement.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

8 min readUpdated 2026-06-10Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer — DP Electrical

Key Takeaways

  • 1A good Minor Works certificate should describe the work clearly, match the actual installation, and show any important readings or limitations.
  • 2One Minor Works Certificate must be issued for each existing circuit affected — if you altered three circuits, three certificates are required (GN3 Reg 2.5).
  • 3If the job creates a new circuit or involves replacing a consumer unit or distribution board, an EIC is required — not a Minor Works Certificate (Reg 644.4.201).
  • 4Since A4:2026, the Appendix 6 model MWC form includes fields for SPDs and AFDDs — complete these where those devices are present.
  • 5A clear schedule of test results helps support the certificate where readings are needed.
  • 6A digital workflow can keep the certificate, follow-on quote, and handover together in one place.
01 · Certificate Guide

What the certificate needs to show

A Minor Works certificate should tell the client what was done, where it was done, and what changed. The description should be specific enough that someone can understand the scope later without guessing.

That means clear client details, a sensible description of the work, the circuit or accessory affected, and any readings or notes that support the work carried out.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Certificate Guide

How to fill it in properly

  • Write the work description as you go, not after the job details have gone stale.
  • Use a clear circuit reference or location so the certificate can be traced later.
  • Record the relevant test results or checks that support the work completed.
  • Note any limitation, defect, or existing issue that matters to the client.
  • Make sure the final wording matches the actual work, not a generic template phrase.
03 · Certificate Guide

When you may need an EIC instead

The big question is whether the work stayed as minor work on an existing circuit or became new installation work. If the job introduces a new circuit, you need to look at when an EIC is required rather than trying to force the job into a Minor Works form.

Consumer unit or distribution board replacement always needs an EIC

If the job includes replacing a consumer unit or distribution board, a full Electrical Installation Certificate is required regardless of whether new circuits were added (Reg 644.4.201). A Minor Works Certificate is not permitted for this work — GN3 Reg 2.5 explicitly excludes it.

If in doubt, match the document to the work

The certificate should reflect the real scope of the job. If the work went beyond minor alterations on an existing circuit, the paperwork should move with it instead of staying on the smaller form.

04 · Certificate Guide

Use the test results to back up the work

Where readings are required, make sure the schedule of test results supports the certificate and does not feel like a separate document. If you want a cleaner reference point for that part of the paperwork, schedule of test results explains the detail in more depth.

The goal is simple: one clear set of notes, one set of readings, one certificate that is ready to hand over.

Record test results hands-free on site

AI board scanner, voice test entry, and automatic BS 7671 validation — finish the certificate before you leave the property. From £6.99/mo.

Try the certificate tools free
Download on the App StoreGet it on Google Play
05 · Certificate Guide

Finish it on site and move on

The best workflow is the one that lets you complete the certificate while the job is still fresh. That means fewer missed fields, fewer late-night admin fixes, and a cleaner handover for the customer.

If the work leads straight into a quote or remedial discussion, a mobile workflow tied to the electrical quoting app helps you keep the next step in the same place.

06 · Certificate Guide

Common mistakes when filling in the MWC

Most Minor Works Certificate mistakes come from rushing — the certificate is short, so people treat it as a formality and finish it without checking. The result is missing supply details, incorrect circuit identification, or a declaration ticked before the test results are even in the boxes. None of those are technically illegal, but all of them weaken the legal value of the document.

One certificate per circuit — not one per job

This is the most commonly failed compliance point. If you altered three circuits, you must issue three separate Minor Works Certificates — one for each circuit modified (GN3 Reg 2.5). A single certificate covering multiple circuits is non-compliant.

The fix is a short pause before sign-off. After every test is in, before any signature, read the certificate end to end as if you were the client or an inspector. Does every field describe the work you actually did? Are the readings consistent with the circuit? Is the declaration honest? If any answer is "not quite", the certificate needs another two minutes before you hand it over.

  • Always identify the circuit by number AND description — never just "Circuit 5".
  • Record continuity, insulation resistance, polarity, EFLI, and RCD time for every modified circuit.
  • Date the certificate with the day of the work, not the day you fill in the paperwork.
  • Sign only after every box is filled and every value verified against the test instrument readout.
  • Where RCD protection has been omitted on a socket-outlet circuit (non-dwelling only), attach the documented risk assessment required by Reg 411.3.3 before sign-off.
  • Complete the SPD and AFDD fields on the A4:2026 Appendix 6 form where surge protective devices or arc fault detection devices are present — leaving these blank is non-compliant under the updated model form.

Frequently Asked Questions

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-Day Free Trial — Cancel Anytime, No Hassle

Complete Minor Works certificates faster and more cleanly

Keep the description, readings, and handover in one mobile-first workflow so the paperwork is ready before you leave site.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical

From £6.99/mo after trial — less than a coffee a week

or download the app
Download on the App StoreGet it on Google Play
7 days free, then from £6.99/moCancel in one tap — no calls, no hassleiOS, Android & WebBS 7671 compliant
16
Certificate Types
70+
Calculators
46+
Training Courses
8
AI Agents

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy