The page of the certificate that records what you actually measured. Here is what belongs on it, the order Regulation 643.1 requires, and what changed when A4:2026 split it into two schedules.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

9 min readUpdated 2026-08-07Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

The short answer

What is the schedule of test results on an electrical certificate?

It is the page of an EIC or EICR that records the measured value for every circuit — continuity, insulation resistance, polarity, earth fault loop impedance, prospective fault current and RCD disconnection time. Regulation 644.3 requires it on a Certificate and Regulation 653.2(f) on a Condition Report, based on the model forms in Appendix 6.

BS 7671:2018+A4:2026 split the old single-page generic schedule in two: a Schedule of Circuit Details for the design and device data, and a Schedule of Test Results for the measured values.

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5

Key takeaways

  1. 01The schedule of test results is the part of an EIC or EICR that records the measured value for every circuit, and it is what proves the testing was actually carried out.
  2. 02Regulation 644.3 requires an Electrical Installation Certificate to include Schedule(s) of Inspection and Schedule(s) of Circuit Details and Schedule(s) of Test Results, based on the models in Appendix 6. Regulation 653.2 imposes the same requirement on a Condition Report, at item (f).
  3. 03BS 7671:2018+A4:2026 redrafted the old single-page generic schedule into two pages: a Schedule of Circuit Details and a Schedule of Test Results. The Appendix 6 model forms also gained fields for recording SPD and AFDD details.
  4. 04A4:2026 was issued on 15 April 2026 and may be implemented immediately. A2:2022 + Corrigendum (May 2023) + A3:2024 remains current but is withdrawn on 15 October 2026.
  5. 05Regulation 643.1 fixes the order: the tests of Regulations 643.2 to 643.6 are carried out in that order before the installation is energised, along with the earth electrode test of 643.7.2 where an electrode is part of the installation.
  6. 06For RCDs, Regulation 643.8 requires verification with an alternating current test at rated residual operating current (IΔn). Regardless of RCD Type, effectiveness is deemed verified at 300 ms maximum for a general non-delay type, and between 130 ms and 500 ms for a delay "S" type.
  7. 07The single most common failing is inconsistency: copied values, vague circuit labels, or readings that do not line up with the protective device, the earthing arrangement, or the observations raised elsewhere on the certificate.

01 · Certificate Guide

What Is the Schedule of Test Results?

The schedule of test results is the section of an electrical certificate that records the actual measured results for each circuit. It is where continuity, insulation resistance, polarity, earth fault loop impedance, prospective fault current and RCD disconnection time are tied back to a specific circuit reference and protective device.

It is the evidence layer of the certificate. Regulation 644.3 makes it a condition of an Electrical Installation Certificate: the Certificate shall include details of the extent of the work covered, plus Schedule(s) of Inspection and Schedule(s) of Circuit Details and Schedule(s) of Test Results. Regulation 653.2 does the same for an Electrical Installation Condition Report, listing the schedules at item (f). In both cases the schedules shall be based on the models in Appendix 6.

On an EICR, the schedule works alongside the schedule of inspections to show both what was observed visually and what was measured by test.

What A4:2026 changed

One schedule became two

BS 7671:2018+A4:2026 redrafted the single-page generic schedule of test results used for the EIC and EICR. There is now a separate page for the schedule of circuit details and a separate page for the schedule of test results. The Appendix 6 model forms also gained fields for recording the details of SPDs and AFDDs, and the schedule of inspections was simplified for initial verification.

A4:2026 was issued on 15 April 2026 and may be implemented immediately. BS 7671:2018+A2:2022 + Corrigendum (May 2023) + A3:2024 remains current but will be withdrawn on 15 October 2026 — so the two-page format is the one to move onto now.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Certificate Guide

What Goes on Each Schedule?

The split is a clean one. Circuit details describe how the circuit was designed and protected; test results record what the instrument actually read. Between them they let a reader check every measured value against the thing it has to comply with.

Schedule of circuit details

Taken from the Appendix 6 model forms, the circuit-details side covers the distribution board and the circuit as designed:

  • Distribution board reference, location and type.
  • Circuit number and circuit description.
  • Reference method (see Table 4A2 of Appendix 4).
  • Cross-sectional area of the live conductors and of the circuit protective conductor.
  • Overcurrent protective device: BS (EN) number, type, rating and breaking capacity.
  • RCD: BS (EN) number, type, rated residual operating current (IΔn) and rated time delay.
  • SPD and AFDD details — fields added to the model forms at A4:2026.

“Ring final sockets”, “upstairs lights” or “EV charger radial” is a usable circuit description. “Sockets” on its own is not, because nobody re-testing the board in five years can tell which one you meant.

Schedule of test results

The test-results side records the measurements. The Appendix 6 forms use the standard symbols — R1 + R2 or R2 for protective conductor continuity, r1, rn and r2 for the three ring final circuit readings, Zs for earth fault loop impedance and Ipf for prospective fault current.

Recorded valueRegulationWhat it has to satisfy
Continuity — R1 + R2 or R2, and r1 / rn / r2 on ring finals643.2Continuity of protective conductors, including protective bonding conductors, and of live conductors on ring final circuits.
Insulation resistance, plus the test voltage used643.3The minimum values in Table 64. The model form has its own “test voltage” field — fill it in.
Polarity643.6Verified at the origin before energising, then throughout the installation.
Zs — earth fault loop impedance643.7.3The measured value shall comply with Chapter 41. A continuity test to 643.2 comes first.
Ipf — prospective fault current643.7.3.201Record the greater of the prospective short-circuit current or the prospective earth fault current.
RCD disconnection time at IΔn643.8Alternating current test at rated residual operating current — see the limits below.

Insulation resistance — Table 64

Circuit nominal voltageTest voltage DCMinimum insulation resistance
SELV and PELV250 V0.5 MΩ
Up to and including 500 V, other than the above500 V1.0 MΩ
Above 500 V1000 V1.0 MΩ

Regulation 643.3.3 adds a two-stage route where connected equipment is likely to influence the measurement or be damaged: test to Table 64 before the equipment is connected, then, once it is connected, apply a 250 V DC test between live conductors and the protective conductor connected to the earthing arrangement. That reading shall be at least 1 MΩ. Record which voltage you used — a bare “>299 MΩ” with no test voltage against it is not traceable.

RCD disconnection times

Regulation 643.8 requires the effectiveness of automatic disconnection of supply by RCDs to be verified with suitable test equipment to BS EN 61557-6. Its NOTE gives the acceptance criteria, and they apply regardless of RCD Type, using an alternating current test at rated residual operating current (IΔn):

RCDDisconnection time at IΔn
General, non-delay type300 ms maximum
Delay “S” typeBetween 130 ms minimum and 500 ms maximum

No half-times and five-times columns

A4:2026 deleted Appendix 3 Table 3A, which covered the tripping times of RCDs. BS 7671 sets no ½×IΔn or 5×IΔn installation test. Those are product-standard tests for the device manufacturer. Record the disconnection time at IΔn, note the test current you applied, and do not leave a bare “trip time” with nothing to interpret it against.

03 · Certificate Guide

Which Tests Are Recorded, and in What Order

Regulation 643.1 does not leave the sequence to preference. The tests of Regulations 643.2 to 643.6 shall be carried out in that order, before the installation is energised. Where the installation incorporates an earth electrode, the test of Regulation 643.7.2 is also carried out before energising. If a test shows a failure to comply, that test and any preceding test whose result may have been influenced shall be repeated once the fault is rectified.

TestRegStage
Continuity of conductors643.2Before energising
Insulation resistance643.3Before energising
Protection by SELV, PELV or electrical separation643.4Before energising
Insulation resistance / impedance of floors and walls643.5Before energising
Polarity643.6Before energising
Earth electrode resistance, where an electrode is fitted643.7.2Before energising
Earth fault loop impedance643.7.3Live
Prospective fault current643.7.3.201Live
Additional protection — RCD verification643.8Live
Check of phase sequence, on polyphase circuits643.9Live
Functional testing643.10Live
Verification of voltage drop643.11Where required by Chapter 52. Not normally required at initial verification.

Filling the schedule in this order is not just compliance housekeeping — it is the order that stops you energising a board you have not proved dead-safe first, and it means each row is completed while the circuit is still in front of you.

04 · Certificate Guide

How to Complete It Properly

A good schedule is built from methodical testing, not from filling boxes afterwards. Identify the circuit clearly, take the reading, and enter it directly against the correct circuit while you are still on site.

Follow the Appendix 6 column headings and structure. They are the format scheme assessors and clients recognise, and using them stops you omitting a required field such as the insulation resistance test voltage or the rated time delay of an “S” type RCD.

The values also have to agree with one another. An R1 + R2 recorded on a lighting radial should support the Zs you measured on the same circuit. A slow RCD disconnection time should be reflected in an observation or a remedial recommendation. The schedule is not an isolated spreadsheet; it has to hold up against the rest of the certificate.

One detail that catches people out on an EIC: the maximum prospective fault current recorded should be the greater of the prospective short-circuit current or the prospective earth fault current, not whichever you happened to measure first.

If you are working on an EIC or EICR in Elec-Mate, use the digital certificate workflow so readings, observations, and exported PDFs all stay linked to the same job.

In the app

Record test results hands-free on site

AI board scanner, voice test entry, and automatic BS 7671 validation — finish the certificate before you leave the property. From £6.99/mo.

05 · Certificate Guide

Common Mistakes That Undermine the Certificate

The schedule of test results is one of the easiest places for bad habits to show up. Small errors here can make an otherwise decent certificate look weak.

  • Copying previous readings forward without re-testing the actual circuit.
  • Mixing up circuit references, or leaving vague labels like “sockets” with nothing to distinguish one circuit from the next.
  • Entering values that do not match the protective device or the earthing system.
  • Leaving blanks with no limitation or explanatory note.
  • Recording readings on paper, then re-keying them later and introducing transcription errors.
  • Omitting the insulation resistance test voltage. The model form has a dedicated field for it, and where Regulation 643.3.3 has been used the reading was taken at 250 V DC against a 1 MΩ minimum, not at 500 V DC against Table 64 — without the voltage, nobody can tell which.
  • Recording an RCD trip time without stating the test current applied, or still using an old form with ½× and 5× columns that A4:2026 removed from BS 7671.
  • Still issuing a combined single-page generic schedule after A4:2026 split it into a schedule of circuit details and a schedule of test results.

The easiest way to tighten this up is to capture results once, in the right place, and let the software validate and format them consistently.

06 · Certificate Guide

Why a Digital Schedule of Test Results Is Better

A digital schedule of test results reduces friction at every stage: less duplicate data entry, fewer missed circuits, cleaner exports, and more confidence when the client or scheme assessor reviews the certificate.

Regulation 644.4.202 already allows certificates to be produced in any written or electronic form, provided their authenticity and integrity can be verified by a reliable process — so a properly built digital workflow is not a compromise on compliance.

In Elec-Mate, the schedule sits inside the certificate flow, so you can move from circuit entry to observations, signatures, PDF export, and even remedial quoting without losing context. That is particularly useful on larger EICRs where speed and consistency matter.

How to Complete a Better Schedule of Test Results

A five-step workflow that follows the Regulation 643.1 test order.

1

Fill in the circuit details first

Complete the schedule of circuit details — board reference, circuit number and description, reference method, conductor sizes, and the protective device, RCD, SPD and AFDD data — before any reading is taken.

2

Work through the dead tests in order

Regulation 643.1 requires the tests of 643.2 to 643.6 in that order before energising: continuity, insulation resistance, SELV/PELV/separation, floors and walls, then polarity. Add the earth electrode test of 643.7.2 where an electrode is fitted.

3

Record the insulation resistance test voltage

Enter the DC test voltage alongside the result — 500 V against a 1.0 MΩ minimum for most low voltage circuits, or 250 V against a 1 MΩ minimum where Regulation 643.3.3 applies after connecting sensitive equipment.

4

Enter the live results against the same circuit

Add Zs, prospective fault current and the RCD disconnection time at IΔn directly to the correct circuit row. On an EIC, record the greater of the prospective short-circuit and prospective earth fault current.

5

Check the values agree with the rest of the certificate

Confirm each reading is consistent with the protective device, the earthing arrangement, and any observation or remedial recommendation you have raised, then export the schedules attached to the certificate.

Frequently Asked Questions

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-day free trial

Complete Test Results Properly on Site

Use Elec-Mate to record circuit results once, validate them as you go, and export professional certificates without duplicate data entry.

Start your free trial

From £6.99/mo after the trial — no charge until day 8.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5
  • 7 days free, then from £6.99/mo
  • Cancel in one tap — no calls, no hassle
  • iOS, Android and web
  • Built to BS 7671:2018+A4:2026

Or download the app

Download on the App StoreGet it on Google Play
Certificate types
16Certificate types
Calculators
70+Calculators
Training courses
46+Training courses
AI specialists
8AI specialists

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy