BS 7671 A4:2026 — SECTION 712

Section 712 — Prosumer’s LV Installations under A4:2026 — Battery, Solar PV & Microgeneration

BS 7671:2018+A4:2026 substantially expanded Section 712 to deal with the modern household electrical installation that no longer just consumes — it generates, stores, and exports. This guide covers the prosumer definition, the amended Section 712 regulations, battery energy storage system (BESS) design, AC vs DC coupling, isolation and earthing rules, EREC G98/G99 notification, Loss of Mains protection, and prosumer-specific inspection and testing.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

18 min readUpdated 2026-05-18Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer — DP Electrical

Key Takeaways

  • 1A "prosumer" is a consumer who is also a producer — taking energy from the public supply and exporting back (or storing and re-exporting). Section 712 of BS 7671:2018+A4:2026 governs the LV installation that does both.
  • 2A4:2026 expanded Section 712 to address battery energy storage systems (BESS), AC and DC-coupled topologies, islanded operation, and the interaction between solar PV, battery and EV charging.
  • 3Battery energy storage systems must comply with the relevant product standards (BS EN 62909 series and the IEC 62933 family) and, for grant-eligible or MCS-certified installations, with MCS 020. The wiring installation itself is governed by Section 712.
  • 4AC-coupled batteries connect on the AC side of the consumer unit as a separate microgeneration source; DC-coupled batteries share the PV inverter DC bus. The two have different isolation, earthing and protection implications under Section 712.
  • 5Grid-connection of any prosumer source is governed by Engineering Recommendation G98 (up to 16 A per phase, "connect and notify") or G99 (everything larger, "apply and connect"). DNO notification is before energisation for G99, within 28 days for G98.
  • 6Section 712.411 covers protection against electric shock, 712.421 covers protection against thermal effects, and 712.531 covers devices for protection against overcurrent and isolation specific to prosumer installations.
  • 7Loss of Mains (LoM) protection is mandatory — the inverter must disconnect from the grid within milliseconds of a supply failure to prevent islanding onto a dead network. Settings are defined by G98/G99 and verified at commissioning.
  • 8Prosumer-specific inspection and testing extends beyond the standard schedule — inverter shutdown tests, DC isolation verification, anti-islanding confirmation and the A4:2026 microgeneration columns on the Schedule of Test Results.
01 · BS 7671 A4:2026 — Section 712

What a Prosumer Installation Actually Is

The term "prosumer" — producer and consumer combined — entered the UK Wiring Regulations vocabulary formally with Section 826 of BS 7671 (definitions and energy-related terminology) and was given dedicated technical treatment in Section 712. A prosumer’s installation is a low-voltage electrical installation that both draws energy from the public distribution network and generates, stores or exports energy back. The classic 2026 example is a household with rooftop solar PV, a battery energy storage system, an EV charge point and a smart meter — all behind one cut-out and one earthing arrangement.

Before A4:2026, the relevant regulations were spread across Section 712 (solar photovoltaic power supply systems), the now-superseded Section 551 (low-voltage generating sets), and a small set of regulations on energy efficiency in Section 818. A4:2026 consolidated and substantially expanded Section 712 to deal with the reality that solar, battery and EV are routinely installed together and interact electrically.

Why this matters in 2026

The Boiler Upgrade Scheme, ECO4 and Smart Export Guarantee tariffs have driven a step-change in UK households fitting batteries and PV together. Domestic battery installs in GB are now in the hundreds of thousands. Section 712 of BS 7671:2018+A4:2026 is the wiring regulation that catches up.

For the broader prosumer concept, see the prosumer’s low-voltage electrical installation guide. This page is the deep dive on Section 712 itself.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · BS 7671 A4:2026 — Section 712

What A4:2026 Changed in Section 712

Amendment 4, published on 15 April 2026 and in force from that date for new installations, made Section 712 one of the most substantially rewritten parts of the 18th Edition. The previous section dealt principally with solar PV; the amended section deals with the whole prosumer installation — generation, storage, export, islanded operation and interaction with the public supply.

  1. Scope broadened beyond solar PV to cover any prosumer’s LV installation, including battery energy storage systems, small-scale combined heat and power, and microwind. Section 712 is now the single section for the prosumer’s LV side.
  2. New requirements for battery energy storage systems (BESS), including selection of the inverter/charger, AC vs DC coupling, battery enclosure ventilation, and isolation arrangements specific to the battery DC side.
  3. Expanded isolation requirements — isolators must be provided on each energy source so that the rest of the installation can be made dead independently. A solar isolator alone is no longer sufficient on a combined PV + battery installation.
  4. Updated earthing arrangements for prosumer installations in TN-C-S systems, with explicit treatment of the case where the installation can operate islanded (disconnected from the public supply) and must establish its own earthing reference.
  5. Cross-reference to Engineering Recommendation G98 and G99 made explicit. The Section 712 regulations now point directly to the ENA documents for grid-connection notification, Loss of Mains protection settings and anti-islanding behaviour.
  6. New labelling and identification regulations — every prosumer installation must carry warning labels at the origin, at each isolator, and at the meter, identifying the presence of additional sources of supply.
  7. New entries on the Schedule of Test Results columns — commissioning of a prosumer installation now requires recording the inverter make/model/firmware, the anti-islanding test result, the DC isolation insulation resistance, and the battery isolation verification.

A4:2026 applies to new design from 15 April 2026

Installations whose design was commenced before 15 April 2026 may still be completed to BS 7671:2018+A3:2024. From 15 April 2026 onwards, any new prosumer installation must comply with the A4:2026 Section 712 requirements. See the BS 7671 A4:2026 summary for the transition rules.

03 · BS 7671 A4:2026 — Section 712

Battery Energy Storage System (BESS) Installation Requirements

A battery energy storage system is an assembly of electrochemical batteries, a battery management system, an inverter/charger, isolation, protection and monitoring — installed as a single functional unit on the prosumer’s LV installation. The Section 712 requirements sit alongside the product standards (IEC 62933 / BS EN 62909 series) and, for MCS-certified installs, MCS 020.

  • Location — enclosure installed per manufacturer instructions, Building Regulations and BS 7671. Lithium-ion batteries should not be installed in habitable rooms; garage, ventilated loft and external wall-mounted enclosures are typical.
  • Ventilation — sufficient natural or mechanical ventilation per manufacturer instructions. Lithium-ion batteries off-gas under thermal runaway and must not be enclosed in airtight cupboards.
  • Fire separation — batteries above the manufacturer’s stated energy threshold should be separated from habitable space by a fire-resisting partition, or located externally.
  • Cable routes — DC cables between the battery and inverter must be in containment that maintains separation from AC cabling, with mechanical protection where exposed.
  • Isolation — means of isolation on both AC and DC sides. The DC isolator must be lockable in the off position and within sight of the battery enclosure.
  • Protection — the AC connection must have a dedicated overcurrent device sized for the inverter’s maximum continuous output, with discrimination from the upstream device.
  • Earthing — the battery enclosure and exposed conductive parts must be connected to the main earthing terminal per Section 712.411 and Chapter 41.
  • Labelling — the consumer unit, meter position and battery enclosure must each carry a warning label per Section 712 and the model labels in Appendix 6.

MCS 020 sits alongside BS 7671

MCS 020 is the Microgeneration Certification Scheme standard for battery energy storage installation. It is mandatory for installations that need to claim Smart Export Guarantee or other grant funding through an MCS-certified installer. MCS 020 references BS 7671 for the wiring side — it does not replace it. See the battery storage guide for the broader scheme picture.

04 · BS 7671 A4:2026 — Section 712

AC-Coupled vs DC-Coupled Battery Topology

A battery can be connected to a solar PV array on the AC side of the PV inverter or on the DC side, sharing the DC bus. The choice has direct consequences for the Section 712 wiring requirements, for isolation, for efficiency and for behaviour on loss of supply.

  • AC-coupled — the battery has its own inverter/charger which connects to the AC consumer unit alongside the solar PV inverter. The battery behaves as a separate microgeneration source. Easiest topology to retrofit onto an existing PV installation. Each inverter has its own DC isolator and its own AC isolator. Double conversion (DC → AC → DC → AC) gives slightly lower round-trip efficiency.
  • DC-coupled — the battery shares a single hybrid inverter with the solar PV array on the DC bus. The hybrid inverter performs both PV MPPT and battery charge/discharge in one device. Single AC connection point. Higher round-trip efficiency for self-consumption (one DC ↔ AC conversion). DC side is more complex — a single DC isolator may not be sufficient.
  • Hybrid AC/DC — some manufacturers offer a hybrid inverter that can also accept an AC input from an existing PV inverter. Used when retrofitting a battery onto an existing PV system but wanting DC-coupled efficiency.

Whichever topology is selected, Section 712.531 requires a dedicated isolator on each energy source — PV array, battery DC, and the AC connection to the consumer unit. The aim is that any one source can be isolated for maintenance without taking the rest of the installation offline, and that on supply failure the installation can be made completely dead from a single, clearly labelled, accessible location.

Retrofit consideration

Most existing solar PV installations in the UK are not DC-coupling-ready — the original string inverter cannot accept a battery on the DC side. Retrofitting almost always means an AC-coupled battery with its own hybrid inverter, or a complete replacement of the PV inverter with a DC-coupled hybrid. Either approach is valid under Section 712; the choice is driven by efficiency targets, budget and roof access.

05 · BS 7671 A4:2026 — Section 712

Isolation Requirements for Prosumer Installations

Section 712.531 sets out the isolation requirements for prosumer installations. Because energy can flow from more than one source, the standard single point of isolation at the consumer unit is not sufficient. Each generator and storage device must be capable of being isolated independently, and the whole installation must be capable of being made dead from a clearly identified location.

  1. DC isolator on the PV array side — lockable, located adjacent to the inverter, rated for the PV array open-circuit voltage and short-circuit current at the design ambient temperature. Required under Section 712.531 and Appendix 4 derating.
  2. AC isolator on the PV inverter output — lockable, located adjacent to the inverter, rated for the inverter’s maximum continuous output current.
  3. DC isolator on the battery side — lockable, located within sight of the battery enclosure, rated for the battery system voltage and the maximum charge/discharge current.
  4. AC isolator on the battery inverter output (AC-coupled topology) — separate from the PV inverter isolator, with its own dedicated overcurrent device on the consumer unit.
  5. Main switch at the consumer unit — the primary point of isolation for the public supply, with appropriate warning that other sources of supply exist on the installation.
  6. Single point of isolation for emergency — the prosumer installation must include a clearly identified, accessible emergency isolation arrangement that disconnects all sources simultaneously. This is typically the inverter’s integrated shutdown function, with a backup AC + DC isolation sequence documented in the user manual handed to the householder.

Multiple sources — multiple warning labels

A4:2026 requires warning labels at the consumer unit, at the meter, at each inverter, at each isolator, and at the battery enclosure, identifying the presence of additional sources of supply. The DNO’s service-fuse pull alone will not make the installation dead — the inverter and battery can continue to energise the customer side. Anyone working on the installation must be able to see, at a glance, that this is a prosumer installation.

06 · BS 7671 A4:2026 — Section 712

Earthing for Islanded Operation

Most UK domestic supplies are TN-C-S (PME, with PNB now a recognised variant under A4:2026). The earthing of a prosumer installation must deal with two scenarios: grid-connected (the supply earth available via the combined neutral-and-earth) and islanded (supply lost, anti-islanding triggered, but the inverter is still energising local loads from the battery).

  • Grid-connected operation — the installation earth is the supply earth via the main earthing terminal. The PV inverter, battery inverter and EV charge point all share this earth.
  • Islanded operation — if the inverter is configured to maintain supply to selected loads during a grid outage (often called "backup mode" or "EPS" — Emergency Power Supply), the inverter must establish its own earth reference for the islanded section. This typically means a neutral-earth bond inside the inverter during island mode, switched in automatically.
  • Backup load panel — most inverters with backup capability provide a separate output for the loads that should be supported during an outage. This output is wired to a separate sub-board, with appropriate RCD protection and bonding.
  • Section 712.411 protection against electric shock — the prosumer installation must satisfy automatic disconnection of supply (ADS) in both grid-connected and islanded modes. The Zs values measured at commissioning must be valid for the highest-impedance source the loads see — normally the inverter in island mode.
  • EV charge point interaction — a TN-C-S installation feeding an EV charge point requires either a separate earth electrode for the charge point (Section 722) or an open-PEN detection device. The presence of a battery and inverter does not remove this requirement — see the cable size for EV charger guide.

Inverter without island-mode capability — do not

Many cheaper PV and battery inverters are grid-tied only — they shut down completely on loss of mains and provide zero output until the grid returns. This is fully compliant with Section 712 and G98/G99. The customer must understand this is not a backup power solution — only inverters explicitly rated for island/EPS operation will keep the lights on during a power cut.

Try Elec-Mate free for 7 days

16 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.

Start free trial
Download on the App StoreGet it on Google Play
07 · BS 7671 A4:2026 — Section 712

EREC G98/G99 — Grid Connection Requirements

BS 7671 governs the prosumer’s side of the meter. The interface with the public distribution network is governed by Engineering Recommendation G98 and G99, issued by the Energy Networks Association (ENA). Any installer commissioning a prosumer installation must engage with one or the other — they are not optional. Section 712 of BS 7671:2018+A4:2026 cross-references them explicitly.

  1. G98 — single-phase generation up to 16 A per phase (~3.68 kW per phase). "Connect and notify" — commission and energise, then notify the DNO within 28 days. Used for most domestic PV and small battery systems.
  2. G99 — anything larger (single-phase > 16 A, all three-phase, multiple sources cumulatively > 16 A per phase). "Apply and connect" — apply to the DNO, receive a connection offer, accept it; only then energise.
  3. Type-tested equipment — inverters used under G98/G99 must be type-tested and listed on the ENA Type Test Register. Off-register inverters cannot be used.
  4. Loss of Mains protection — G98/G99 specify the LoM method (ROCOF or vector shift, depending on inverter age and DNO requirement), detection time and auto-reconnect delay.
  5. Anti-islanding test — commissioning includes proving the LoM function by simulating grid loss. Inverter must disconnect within the specified time and must not reconnect until the grid is stable for the specified delay.
  6. Witness testing — G99 installations above certain thresholds require DNO witness testing before energisation.

A multi-source installation may need G99 even if each

A house with 3.6 kW of solar PV + 5 kW of battery + a 7 kW EV charger that can do V2G (vehicle-to-grid) may exceed the G98 16 A per phase ceiling cumulatively even though each individual source is small. Check the cumulative export capability — if it exceeds 16 A per phase, the installation falls under G99 and the DNO must be applied to before energisation.

08 · BS 7671 A4:2026 — Section 712

DNO Notification Process

The DNO owns the local distribution network — UK Power Networks, Northern Powergrid, SP Energy Networks, SSEN, National Grid Electricity Distribution and Electricity North West cover GB between them. Notification is via the ENA’s Connect Direct service or the DNO’s connections portal.

  1. G98 — commission, then submit the G98 document via the ENA Connect Direct portal within 28 days. The form captures property, installer, inverter make/model/firmware, type-test reference, rated output and LoM settings. No prior DNO consent.
  2. G99 — submit the application before installation. The DNO assesses network capacity and issues a connection offer (which may impose curtailment, witness testing or upgrade contributions). Only after acceptance can the installation be energised.
  3. Witness testing — where required, the installer arranges a DNO engineer to witness anti-islanding, ROCOF and other functional tests at commissioning. The DNO signs off and issues the connection agreement.
  4. Connection agreement — once notification is complete (G98) or witness testing is passed (G99), the DNO issues the connection agreement permitting ongoing export.
  5. Notification timeline — G98 is within 28 days post-commissioning but remains the installer’s responsibility. Failing to notify breaches the Distribution Connection and Use of System Agreement (DCUSA). G99 lead times can be 8–12 weeks.

Notification is the installer’s legal obligation, not

It is a common misconception that the householder notifies the DNO. They do not — the installer does, on behalf of the customer, as part of commissioning. Failing to notify exposes the installer to enforcement, the customer to potential disconnection, and creates a safety hazard for DNO field staff who may believe a property is supply-only.

09 · BS 7671 A4:2026 — Section 712

Solar PV + Battery + EV — Interaction on One Installation

Solar PV on the roof, battery in the garage, EV charge point on the driveway — the defining domestic install of 2026. Section 712 of BS 7671:2018+A4:2026 explicitly recognises this combination and sets out how the design must handle the interaction.

  • Maximum demand — the design current of the installation must consider the worst-case import (PV down, battery flat, EV charging, household load high) and the worst-case export (PV at peak, battery full and discharging, EV not present, household load low). Both directions must be within the cut-out fuse rating and the meter tails ampacity.
  • CT clamps and load management — most modern hybrid inverters include current transformers on the supply tails so the inverter can throttle export to zero if the customer is on an import-only tariff, or modulate battery charge/discharge to follow PV. CT positioning must be on the meter side of all loads, including the EV charge point.
  • Smart EV charging — OZEV-grant-eligible EV charge points include smart control under the Electric Vehicles (Smart Charge Points) Regulations 2021. They can defer charging to off-peak or follow PV. See the smart EV charging guide for the regulatory detail.
  • Diversity — traditional diversity factors (BS 7671 Appendix 1) do not apply cleanly to a prosumer installation. The designer must assess the realistic concurrent load including the EV charge point at full rated current and the household at design demand, against the import capacity of the supply.
  • Discrimination — the protective devices for the PV inverter, battery inverter and EV charge point must discriminate with the main switch, with the cut-out fuse, and with each other. A fault on one circuit must not take the whole installation offline.
  • EV charger earthing on TN-C-S — still subject to Section 722 — PEN-fault detection device or separate earth electrode. The presence of an inverter or battery does not satisfy the Section 722 requirement.

The supply may need upgrading

A typical UK single-phase supply is fused at 60 A or 80 A. Combined PV + battery + EV + household installations can hit cut-out fuse limits during charging. Assess the cut-out fuse against maximum import demand and apply to the DNO for an upgrade where necessary — part of the G98/G99 application on G99 installs.

10 · BS 7671 A4:2026 — Section 712

Disconnection — Loss of Mains Protection

Loss of Mains (LoM) protection detects when the public supply has failed and disconnects the inverter from the AC bus to prevent islanding — the dangerous condition where the inverter continues to energise a section of the network after the DNO has switched it off. Without LoM, a DNO engineer working on a "dead" network could be electrocuted by a prosumer’s inverter still pushing voltage onto the local cable.

  • ROCOF (Rate of Change of Frequency) — the current preferred LoM method per G98/G99. The inverter monitors the rate of change of grid frequency; a step exceeding the configured threshold triggers disconnection within the specified time.
  • Vector Shift — older LoM method, retained for legacy equipment but being phased out. More prone to nuisance tripping during grid disturbances.
  • Active methods — some inverters use active impedance measurement, injecting a small signal and watching for the network impedance change that occurs when the grid disconnects. Permitted under G99.
  • Disconnection time — typically within 500 ms of the loss-of-mains event. The exact figure is specified in G98/G99 and in the inverter’s type-test certificate.
  • Reconnection delay — after grid restoration the inverter must wait, typically 60 seconds, with the grid stable, before reconnecting. This prevents rapid re-tripping during unstable conditions.
  • Commissioning test — the installer must simulate LoM at commissioning, observe the inverter disconnect within the specified time, and verify the reconnect delay after restoration. The result is recorded on the Schedule of Test Results and on the G98/G99 form.

LoM is not optional and cannot be defeated

Some installers, faced with nuisance trips on weak rural networks, have been known to widen the ROCOF settings. This is a serious safety breach — LoM protects DNO field staff from electrocution. If the inverter is nuisance-tripping, the fault is in the network or the inverter selection, not the LoM settings. Notify the DNO and select a more appropriate inverter.

11 · BS 7671 A4:2026 — Section 712

Prosumer Installation — Inspection & Testing

The standard Schedule of Inspections and Schedule of Test Results (Appendix 6) is the starting point for any prosumer installation, but is not sufficient on its own. A4:2026 added prosumer-specific items, and the EIC / EICR model forms have been updated to capture them.

  1. Pre-commissioning visual inspection — confirm labels at consumer unit, meter, inverters, isolators and battery enclosure; confirm cable routes, mechanical protection, DC/AC segregation, enclosure ventilation and fire separation.
  2. DC side insulation resistance — PV array IR to earth, before and after exposure to sunlight, per inverter manufacturer procedure. Battery DC side IR verified per manufacturer guidance; do not megger across the battery itself.
  3. AC side insulation resistance — inverter disconnected for IR testing of AC final circuits, then reconnected and the AC circuit tested as a complete installation.
  4. Continuity and earth fault loop impedance — measured at the furthest point of each circuit including the backup load panel. Zs must satisfy Section 712.411 ADS in both grid-connected and island modes.
  5. RCD testing — each RCD verified to the required disconnection time at 1× and 5× IΔn. Type-A or Type-F as required for inverter-fed circuits with DC components.
  6. Anti-islanding test — simulate grid loss with the inverter exporting; verify disconnection within the specified time; restore grid; verify the reconnect delay.
  7. Inverter shutdown test — verify the documented emergency isolation sequence results in zero voltage at the load side within the inverter’s discharge time.
  8. Functional check — verify the inverter starts, exports, throttles to CT clamp signal, charges/discharges the battery, and (if applicable) enters island mode on simulated grid loss.
  9. Documentation — issue the EIC with the A4:2026 Section 712 columns completed, the G98 / G99 form, inverter type-test reference, LoM test result, battery user manual, and customer handover pack.

Periodic inspection — EICR for prosumer installations

Periodic inspection of a prosumer installation follows the standard EICR cycle (typically 10 years domestic) but the inspector must include the inverter shutdown sequence, the anti-islanding function, the labels, the battery enclosure condition and the DC isolators. An EICR that ignores the generation and storage side is incomplete. Damaged labels, missing DC isolators or non-functional LoM should be coded under Chapter 6 of BS 7671 as appropriate.

How to Design and Commission a Compliant Section 712 Prosumer Installation

The end-to-end sequence from initial customer enquiry to DNO notification and customer handover, anchored to BS 7671:2018+A4:2026 Section 712 and Engineering Recommendations G98/G99.

1

Survey and design the prosumer installation

Survey the existing installation — cut-out fuse rating, meter tails ampacity, consumer unit capacity, earthing arrangement (TN-S, TN-C-S/PME or TT), available roof area, battery location and ventilation, EV charge point location. Decide AC-coupled vs DC-coupled topology and calculate maximum demand in both import and export directions per Section 712.

2

Confirm G98 or G99 and apply if required

Sum the cumulative export capability of all sources (PV + battery + V2G EV if applicable). If single-phase ≤16 A per phase, the installation is G98 — proceed to install and notify within 28 days of commissioning. If anything larger, apply to the DNO under G99 and wait for the connection offer before installing.

3

Specify type-tested equipment and assemble the design pack

Select inverters, batteries and EV charge point from products on the ENA Type Test Register and listed on the MCS register where MCS certification is in scope. Produce the BS 7671 design including cable sizes, protective devices, isolation, earthing and labelling. Reference Section 712.411, 712.421, 712.531 and Appendix 6 throughout.

4

Install, label and document

Install the PV array, battery enclosure, inverter(s), DC and AC isolators, backup load panel and EV charge point. Apply A4:2026 prosumer warning labels at the consumer unit, meter, each isolator, each inverter and the battery enclosure. Keep the installation documentation pack with type-test references, datasheets and commissioning checklists.

5

Commission and prove the anti-islanding function

Carry out the full Section 712 prosumer commissioning sequence — DC and AC insulation resistance, continuity, Zs, RCD operating times, anti-islanding (simulate grid loss and verify inverter disconnection within the G98/G99 time), reconnect delay, and functional checks of import/export/charge/discharge. Record everything on the Schedule of Test Results.

6

Notify the DNO and hand over to the customer

Submit the G98 notification within 28 days (or complete G99 witness testing and the connection agreement) via the ENA Connect Direct portal. Issue the Electrical Installation Certificate with A4:2026 prosumer columns completed, the customer user manual including the emergency isolation sequence, and the MCS handover pack if MCS-certified.

Frequently Asked Questions

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-Day Free Trial — Cancel Anytime, No Hassle

Issue a compliant Section 712 prosumer EIC in minutes

The Elec-Mate EIC tool includes the A4:2026 prosumer columns out of the box — inverter make/model/firmware, LoM test result, DC isolation IR, battery isolation verification and the full Schedule of Test Results. Issue a fully compliant Section 712 EIC and G98 / G99 notification pack alongside it. 7-day free trial, cancel anytime.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical

From £6.99/mo after trial — less than a coffee a week

or download the app
Download on the App StoreGet it on Google Play
7 days free, then from £6.99/moCancel in one tap — no calls, no hassleiOS, Android & WebBS 7671 compliant
16
Certificate Types
70+
Calculators
46+
Training Courses
8
AI Agents

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy