Free mock exam
Asbestos and CDM 2015 — Level 3 Health & Safety Practice
Free topic-focused mock exam: all 25 questions on Asbestos and CDM 2015, drawn from the wider Level 3 Health & Safety bank. 35-minute timer, 70% to pass, worked explanation on every question. Use this when you've taken the full mock once and want to drill the topics you got wrong.
- Questions
- 25
- Time limit
- 35 min
- Pass mark
- 70% · 18/25
- Question bank
- 25
Free, no sign-up. Retake as many times as you like — the questions are reshuffled, with the answer order changed.
Sample questions
01Under CDM 2015 Regulation 9, what is the principal designer's duty when planning the pre-construction phase?
- ATo prepare the construction phase plan before work begins and keep it under review for the whole of the build
- BTo supervise the day-to-day construction work physically on site and sign off each contractor's method statement before it starts
- CTo notify the HSE on an F10 form before any construction work starts and update it if the project changes
- DTo plan, manage, monitor and coordinate health and safety in the pre-construction phase, including identifying and eliminating foreseeable risks
Why: CDM 2015 Reg 9 places the principal designer in charge of health and safety during pre-construction. They must plan, manage, monitor and coordinate work to identify, eliminate or control foreseeable risks for those building, using and maintaining the structure.
02Under CDM 2015 Reg 13, when does a contractor become a principal contractor?
- AWhenever the contractor directly employs more than ten workers on the site at any one time
- BAutomatically on any project scheduled to last longer than 30 working days, regardless of how many contractors are engaged on the site
- CWhen more than one contractor is, or is reasonably foreseeable to be, working on the project at the same time — the client must appoint one in writing
- DWhenever the total contract value exceeds £100,000, at which point the client must make a written appointment under Reg 5
Why: CDM 2015 Reg 5 requires the client to appoint a principal contractor in writing whenever more than one contractor is involved (or foreseeably will be). The principal contractor then takes on Reg 13 duties — planning, managing, monitoring and coordinating the construction phase.
03Under CDM 2015 Reg 15, what must a contractor do before starting work on site?
- ACompile the health and safety file for handover to the client and keep a copy of it for the whole life of the structure
- BObtain written confirmation from the client that the whole site has been surveyed and is entirely free of asbestos-containing materials
- CAppoint a principal designer and a principal contractor on the client's behalf, and notify the HSE on an F10 form before any work begins
- DPlan, manage and monitor construction work under their control so it is carried out without risks to health and safety, and provide site-specific induction
Why: CDM 2015 Reg 15 says every contractor must plan, manage and monitor their own work and ensure workers under their control receive a site-specific induction, suitable training and information before starting.
Common questions
Is the Asbestos and CDM 2015 mock exam free?
Yes — 100% free, no sign-up needed. Questions are pulled at random from a substantial bank, with a worked explanation on every question after you submit.
Can I retake the mock exam?
Yes. Every attempt picks a different random selection and reshuffles the options, so each retake gives you genuinely new questions. No limit on retakes.
Does this count towards the real qualification?
No — this is independent practice material. To gain the actual qualification you need to sit the official assessment through an approved provider.