SOLAR PV GUIDE

Solar PV System Sizing — UK Electrician Guide

A complete guide to sizing solar PV systems for UK homes: kWp calculations, orientation and tilt factors, MCS standards, G98/G99 DNO notification thresholds, BS 7671 Section 712 requirements, and battery storage integration.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

10 min readUpdated 2026-06-10Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

What size solar PV system do I need for a UK home?

Match system size to your annual electricity use, roof area and orientation. A typical UK home uses about 3,100 kWh per year and suits a 3.5–4 kWp system, since each 1 kWp generates roughly 850–1,100 kWh annually. Systems up to 3.68 kW single-phase can be notified to the DNO under G98; larger systems need prior G99 approval. Each panel needs around 1.7–2.0 m² of unshaded roof.

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer — DP Electrical

Key Takeaways

  • 1System size in kilowatt-peak (kWp) is determined by the available roof area, the household's annual electricity consumption, and the orientation and tilt of the roof surface. A typical UK 3-bed home uses 3,100 kWh per year and is well served by a 3.5kWp to 4kWp system.
  • 2MCS (Microgeneration Certification Scheme) accreditation is required for solar PV installations where customers wish to access the Smart Export Guarantee (SEG) or claim compliance with MCS standards. Without MCS, the installation cannot be formally certified to the scheme.
  • 3Systems up to 3.68kW single-phase (16A per phase) can be notified to the DNO under the simplified G98 procedure after installation. Larger systems require a G99 application with prior DNO approval — which must be obtained before installation begins.
  • 4BS 7671:2018+A4:2026 Section 712 covers photovoltaic power supply systems and applies to all solar PV electrical installations. Key requirements include DC isolators at the array and inverter, protection against reverse current, and appropriate labelling throughout the installation.
  • 5SAP (Standard Assessment Procedure) calculations are used for new-build solar PV sizing under Building Regulations Part L. For retrofit installations, energy monitoring data or EPC assessments provide the consumption baseline for sizing calculations.
  • 6Battery storage integration requires careful consideration of protection coordination, particularly where export limiting is applied. The PV side is assessed under BS 7671 Section 712, while energy storage falls under the prosumer installation requirements of Section 826, together with the relevant product standards.
01 · Solar PV Guide

Solar PV Sizing Principles for UK Homes

Sizing a solar PV system correctly is the single most important design decision in a domestic solar installation. An undersized system leaves energy potential on the table; an oversized system generates electricity that cannot be consumed or exported within permitted limits. The goal is to match system output to the household's self-consumption pattern and DNO export constraints.

The unit of solar PV capacity is the kilowatt-peak (kWp) — the power output of the array under Standard Test Conditions (STC: 1,000 W/m² irradiance, 25°C cell temperature, 1.5 air mass spectrum). In real UK conditions, the array output is always lower than kWp due to irradiance, temperature, and angle effects.

  • Annual yield estimate: South-facing, 35° tilt, south England — approximately 950 to 1,100 kWh per kWp per year. Scotland — approximately 750 to 900 kWh per kWp per year.
  • Typical UK home consumption: 3,100 kWh per year (Ofgem typical domestic consumption values 2024). High-consumption homes (electric heating, EV charging) may use 5,000 to 10,000+ kWh per year.
  • Self-consumption rate: Without battery storage, typically 25% to 40% of solar generation is self-consumed. With battery storage, this rises to 60% to 80% depending on battery capacity and household demand profile.
Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Solar PV Guide

kWp Calculation Methods

MCS-certified solar PV installers use formal design tools — including the MCS Planning Standards methodology and tools such as PVGIS (Photovoltaic Geographic Information System) — to produce accurate yield estimates and system sizing calculations. The following simplified approach is useful for initial assessments; once the capacity is fixed, the covers string layout, inverter sizing, and DC voltage limits.

Step-by-Step Sizing Method

  • Step 1 — Establish annual consumption: Obtain annual kWh consumption from electricity bills or EPC. Use Ofgem typical values if bills are unavailable (3,100 kWh for medium household).
  • Step 2 — Calculate target generation: For a self-consumption optimised system, target generation of 100% to 130% of annual consumption (excess is exported via SEG). For a net-zero target, account for EV charging and heat pump loads.
  • Step 3 — Estimate kWp required: Divide target annual generation (kWh) by estimated specific yield (kWh/kWp/year from PVGIS for the specific location, orientation, and tilt). Round up to the nearest whole module count.
  • Step 4 — Check roof area: Each 400Wp panel occupies approximately 1.7m² to 2.0m². Multiply panel count by panel area and add 15% for spacing, verge margins, and ridge clearance.
  • Step 5 — Check G98/G99 threshold: If the resulting kWp exceeds 3.68kW single-phase, a G99 application is required before installation can proceed.
03 · Solar PV Guide

Orientation and Tilt Factors

The orientation (azimuth) and tilt (inclination) of a solar array have a significant effect on annual energy yield. The PVGIS tool, maintained by the European Commission's Joint Research Centre, provides location-specific yield estimates for any combination of tilt and orientation.

Orientation Yield Factors (South England Reference)

Indicative relative annual yield versus an optimal south-facing array. Use PVGIS for the specific site, location and tilt.

Orientation & tilt
Relative yield
South (180°), 35–40° tilt
100%
South-East / South-West (135° / 225°), 35° tilt
~95%
East / West (90° / 270°), 25–30° tilt
~80–85%
Flat roof, ballasted at 10–15° tilt
~87%
North-East / North-West, any tilt
~65–70%
North (0°), any tilt — marginal
~50–60%
  • Shading: Even partial shading on a single cell in a string can reduce the output of all modules in that string. Always carry out a shading analysis using a solar pathfinder, SunEye tool, or PVGIS shading assessment before finalising the design. Consider microinverters or DC optimisers for shaded installations.
04 · Solar PV Guide

MCS Standards and G98/G99 Notification Thresholds

Two separate certification and notification frameworks apply to residential solar PV installations in the UK: MCS (Microgeneration Certification Scheme) for quality and SEG eligibility, and G98/G99 for DNO connection requirements.

MCS Requirements

  • MCS 001 — Solar PV product certification standard (modules and inverters must be certified to the relevant IEC standards and registered on MCS)
  • MCS 005 — Installer certification standard. The installation company must hold MCS 005 certification for solar PV to issue an MCS certificate.
  • MCS certificate required for Smart Export Guarantee (SEG) application — without it the customer cannot receive SEG export payments.

G98 — notify after install

Single-phase
Up to 3.68 kW (16 A)
Three-phase
Up to 11.04 kW (16 A/phase)
Approval
Notify DNO within 28 days of commissioning

G99 — apply before install

Applies to
Any system above the G98 thresholds
Standard assessment
Up to 45 working days (residential)
Complex sites
Up to 90 working days

Try Elec-Mate free for 7 days

16 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.

Start free trial
Download on the App StoreGet it on Google Play
05 · Solar PV Guide

BS 7671 Section 712 — Photovoltaic Systems

Section 712 of BS 7671:2018+A4:2026 sets out the specific additional requirements for photovoltaic power supply systems. These requirements supplement the general requirements of BS 7671 and apply to all solar PV electrical installations, regardless of system size.

Regulation
Requirement
712.537.2
Isolation and switchingMeans of isolation must be provided on both the AC and DC sides. Devices without DC breaking capacity (such as fuse carriers and SPD carriages) that could open a DC circuit must be secured against inadvertent operation, for example by a lockable enclosure or padlocking (Regulation 712.537.2.2.104).
712.534
Overvoltage protection (SPDs)Surge protective devices on the DC side must comply with BS EN 61643-31. SPDs are generally Type 2 with a minimum nominal discharge current of 5 kA; Type 1 SPDs apply where lightning separation distance cannot be maintained per BS EN 62305-3.
712.514
Identification and noticesAn instruction notice indicating the presence of a PV system must be fixed at the origin, the metering position and the consumer unit (712.514.101). Each DC access point needs a warning that live parts can remain energised after isolation (712.514.102), and every inverter must be labelled to isolate both AC and DC before servicing (712.514.103).
712.521.101
DC wiring systemDC cables must be selected and erected to minimise earth-fault and short-circuit risk, using single-core non-metallic-sheathed cable such as H1Z2Z2-K to BS EN 50618, or insulated conductors in individually insulated conduit or trunking. Cables must not be placed directly on the roof surface.
712.533.101
DC overcurrent protectionDC-side overcurrent protective devices must be gPV fuses to BS EN 60269-6 or circuit-breakers to BS EN 60947-2 / BS EN 60898-2 / BS IEC 60898-3, and must be bidirectional with a breaking capacity at least equal to the array short-circuit current.
712.542.101
Equipotential bonding of PV structuresWhere bonding is needed to prevent electrostatic charge accumulation, the metallic support structures and cable management must be bonded; functional bonding conductors must be at least 4 mm² copper equivalent (712.542.3.101).

A4:2026 change: the former Regulation 712.443 was deleted by BS 7671:2018+A4:2026. Always cite the current numbering — DC-side overvoltage and SPD requirements now sit under Regulation 712.534. Outdoor PV enclosures must achieve at least IP44 to BS EN 60529 and IK07 to BS EN 62262 (Regulation 712.512.102).

See the for how non-compliance with Section 712 requirements is typically graded on electrical inspection reports.

06 · Solar PV Guide

Battery Storage Integration

Battery storage is increasingly standard in new solar PV installations, and a growing number of existing systems are being retrofitted with battery storage. Integrating battery storage introduces additional electrical design and safety considerations under BS 7671 and the relevant product standards.

Standards and product compliance

Battery storage forms part of a prosumer's electrical installation, addressed in BS 7671:2018+A4:2026 Section 826. The battery system must comply with its relevant product standard, and the combined inverter-battery system must satisfy the PV requirements of Section 712.

AC-coupled vs DC-coupled

AC-coupled batteries have their own inverter-charger and are simpler to retrofit. DC-coupled batteries connect to the PV inverter's DC bus and are more efficient but need a compatible inverter/battery pairing. Both require G98/G99 assessment as a combined system.

Fire safety and siting

Lithium-ion battery systems should not be installed in habitable rooms without fire separation meeting the manufacturer's requirements. Enclosures should vent thermal runaway to outside where practicable. Manufacturer installation instructions must be followed and taken into account as part of equipment selection and erection under BS 7671.

07 · Solar PV Guide

DNO Connection Requirements and Export Limiting

All solar PV systems in Great Britain must be registered with the relevant DNO under G98 or G99. Some DNOs impose export limiting as a condition of G99 approval where the local network has insufficient export headroom.

  • Export limit setting: Where a DNO requires export limiting, the approved export limit (in kW or A) is specified in the G99 agreement. The inverter must be configured with the export limiter active, with a current transformer (CT) clamp on the grid supply cable, before commissioning.
  • Zero export (export prevention): Some DNOs or property types (leasehold, shared supplies) require zero export — the system is configured to prevent any export to the grid. This significantly reduces self-consumption rate and requires careful sizing to avoid wasted generation.
  • Documentation: The G99 agreement (or G98 notification confirmation) must be retained with the installation documentation and provided to the customer alongside the EIC. Use to manage EIC certificates for solar PV installations.

Solar PV System Sizing — Frequently Asked Questions

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-Day Free Trial — Cancel Anytime, No Hassle

Issue EIC certificates for solar PV installations with Elec-Mate

Generate compliant Electrical Installation Certificates for solar PV on your phone. Start your free 7-day trial.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical

From £6.99/mo after trial — less than a coffee a week

or download the app
Download on the App StoreGet it on Google Play
7 days free, then from £6.99/moCancel in one tap — no calls, no hassleiOS, Android & WebBS 7671 compliant
16
Certificate Types
70+
Calculators
46+
Training Courses
8
AI Agents

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy