COST GUIDE

Garage Electrical Installation Cost UK 2026: Garage Wiring Prices

Detailed breakdown of garage electrical installation costs in the UK for 2026 — detached garage from £800, integral garage from £400, SWA armoured cable and trenching costs, garage consumer unit, EV charger add-ons, and Part P compliance.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

10 min readUpdated 2026-08-07Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

The short answer

How much does it cost to wire or rewire a garage in the UK?

A detached garage electrical installation typically costs £800 to £2,000, and an integral garage £400 to £800. Rewiring an existing garage on a sound existing supply also runs £400 to £800. Trenching adds £15 to £25 per metre through a garden, or £30 to £60 through concrete.

The single biggest variable is the SWA cable run from the house and what it has to cross. Adding a 7 kW EV charger while the trench is open costs £200 to £400 rather than £600 to £1,200 as a separate job.

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5

Key takeaways

  1. 01A detached garage electrical installation typically costs £800 to £2,000. The main variable is the length of the armoured cable run from the house and whether trenching through a driveway or garden is required.
  2. 02An integral (attached) garage is simpler at £400 to £800, because the cable run is short and no external trenching is required.
  3. 03A cable buried in the ground must incorporate an earthed armour or metal sheath suitable for use as a protective conductor, unless it is run in a conduit or duct giving equivalent mechanical protection (BS 7671 Reg 522.8.10). In practice that means SWA. Trenching, sand bedding and cable covers add £20 to £50 per metre.
  4. 04BS 7671 sets no numeric burial depth for a domestic supply — Reg 522.8.10 requires only "a sufficient depth to avoid being damaged by any reasonably foreseeable disturbance of the ground". The familiar 600 mm figure comes from the notes to the caravan park and marina sections (Regs 708.521.7.2 and 730.521.101.3.2), and the trade applies it as the working minimum.
  5. 05A garage with more than one final circuit needs its own distribution board, because Reg 314.4 requires every final circuit to be connected to a separate way. Expect £300 to £600 for a small garage consumer unit.
  6. 06Adding a 7 kW EV charger costs an additional £600 to £1,200 as a standalone job (excluding the charger unit), but only £200 to £400 if the cable and consumer unit are being installed anyway.

01 · Cost Guide

Garage Electrical Costs at a Glance

JobTypical costWhat it covers
Detached garage, full install£800 – £2,000SWA cable, trenching through garden, small consumer unit, lighting and socket circuits, testing and certification
Integral (attached) garage£400 – £800Circuits fed from the main house consumer unit through the party wall. No external cable run, no trenching
Rewire an existing garage£400 – £800New lighting and socket circuits on a sound existing supply, small board if needed, testing and certification
EV charger, added to the same job£200 – £400Marginal cost of a 32 A circuit when the supply cable and board are being installed anyway. Charger unit not included
EV charger, standalone job£600 – £1,200Circuit and installation as a separate visit. Charger unit not included
Trenching, per metre£15 – £60£15 – £25 through lawn or soft ground, £30 – £60 through concrete

What actually drives the price

Three things decide where in the range a garage job lands: whether the garage is attached or detached, how far the cable has to travel, and what it has to travel under. A 10-metre run across a lawn and a 25-metre run under a concrete driveway are the same electrical design and completely different jobs on the day.

In England and Wales, installing the new circuit that supplies a garage — and installing or replacing a consumer unit — is notifiable under Part P of the Building Regulations. An electrician registered with a competent person scheme self-certifies the work, so no separate building control application is needed.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Cost Guide

Detached Garage Electrical Costs

A detached garage installation means running an armoured cable from the main house consumer unit to the garage, usually underground. Cost scales almost entirely with the length and difficulty of that run.

Cable runTypical costScope
Up to 10 m, through garden£800 – £1,200Usually one day. 6mm² SWA, trench through lawn, small consumer unit, one lighting circuit, one socket circuit
10 – 25 m, mixed surfaces£1,200 – £1,600Longer run, likely trenching through a path or patio, higher materials cost
Over 25 m, or under a driveway£1,600 – £2,000+Diamond cutting or boring through the slab, significant reinstatement, and possibly a larger cable to hold the voltage drop

Why long runs cost more than the extra cable

Beyond about 25 metres the cable stops being sized purely on current-carrying capacity and starts being sized on voltage drop. Section 525 of BS 7671 requires the voltage at fixed current-using equipment to stay within its product standard, and Regulation 525.202 deems that satisfied where the drop from the origin of the installation to the load point stays inside the figures in Appendix 4, Table 4Ab — 3 % for lighting and 5 % for other uses. Stepping from 6mm² to 10mm² to hold that figure adds material cost across the whole run, not just the extra metres.

03 · Cost Guide

Integral Garage Electrical Costs

An integral or attached garage shares a wall with the house, which removes the external cable run, the armoured cable and the trenching from the job entirely. Circuits are fed from the main house consumer unit through the party wall.

ScopeTypical costWhat it covers
Lighting and sockets only£400 – £600One lighting circuit, one socket circuit (ring final or radial), tested and certified. Assumes the existing board has spare ways
Plus consumer unit upgrade£800 – £1,200New consumer unit in the house to Reg 421.1.201, plus all garage circuits
Plus EV charger£1,000 – £1,800Dedicated 32 A EV circuit, board work if required, charger installation. Charger unit not included

Inside an integral garage, standard 2.5mm² twin and earth is fine for the socket circuit provided it runs in a permitted zone or is mechanically protected. Because the run stays within the building structure, no armoured cable is needed.

Socket-outlets rated up to 32 A need additional protection by a 30 mA RCD under Regulation 411.3.3 — which in a garage matters, because that is exactly where extension leads and outdoor power tools get plugged in.

04 · Cost Guide

SWA Armoured Cable and Trenching

Regulation 522.8.10 is the one that decides the cable. A cable buried in the ground must incorporate an earthed armour or metal sheath — or both — suitable for use as a protective conductor, unless it is installed in a conduit or duct that provides equivalent protection against mechanical damage. For a domestic garage supply that means SWA in practice.

Cable size, depth and marking

DecisionWhat applies
Standard domestic supply6mm² SWA is the usual starting point for lighting, sockets and a small workshop. The final size must be confirmed against the Appendix 4 table for the reference method actually used — direct in the ground and in a duct in the ground are different columns — and against the protective device rating.
EV charger supplyA 7 kW charger draws around 32 A for long periods. On longer runs 10mm² SWA is commonly needed to keep the total voltage drop within the 5 % allowed for “other uses” in Appendix 4, Table 4Ab.
Burial depthReg 522.8.10 requires “a sufficient depth to avoid being damaged by any reasonably foreseeable disturbance of the ground” and gives no figure. The familiar 0.6 m comes from notes to the caravan park and marina sections (Regs 708.521.7.2 and 730.521.101.3.2) and is the working minimum the trade applies to garden runs.
Marking the routeReg 522.8.10 requires the location of buried cables to be marked by cable covers or a suitable marker tape, and buried conduits and ducts to be suitably identified. Sand bedding above and below the cable is good practice rather than a BS 7671 requirement.
Overhead alternativeWhere trenching is not viable, an insulated overhead run on a catenary is an option and is far cheaper than cutting a driveway. BS 7671 gives no general height for a domestic span; the benchmark installers work to is the 3.5 m — and 6 m where vehicles pass beneath — set for caravan parks and marinas in Regs 708.521.7.3 and 730.521.101.3.3.

05 · Cost Guide

Garage Consumer Unit

Once a garage has more than one final circuit it needs a distribution board of its own. Regulation 314.4 requires each final circuit to be connected to a separate way in a distribution board, and Regulation 462.2 requires every circuit to have a means of isolation for all live conductors. A small board where the supply enters the garage satisfies both and keeps a fault in the garage off the house board.

BoardFitted costSuits
Small, 4 way£300 – £450One lighting circuit, one socket circuit, one or two spares. RCBOs or dual RCD
Larger, 6 – 8 way£400 – £600Adds an EV charger circuit, a workshop power circuit, outdoor sockets and security lighting
Lockable isolatorAdd £40 – £90Reg 462.3 lists padlocking and lockable enclosures as ways of preventing inadvertent re-closure. Worth it where the garage is shared or let

What BS 7671:2018+A4:2026 asks for

  • Enclosure. In domestic premises, consumer units and similar switchgear assemblies must comply with BS EN 61439-3 and have a non-combustible enclosure, or sit inside a non-combustible cabinet (Reg 421.1.201). The note to that regulation gives ferrous metal such as steel as an example of a non-combustible material.
  • Certification. Regulation 644.1 requires an Electrical Installation Certificate on the model in Appendix 6 for a new installation, or for an addition or alteration — explicitly including the replacement of a distribution board or consumer unit. Under Reg 644.3 it must carry the Schedule of Inspection and the Schedules of Circuit Details and Test Results.
  • AFDDs. Regulation 421.1.7 requires arc fault detection devices to BS EN 62606 on single-phase AC final circuits supplying socket-outlets rated up to 32 A in high rise residential buildings, houses in multiple occupation, purpose-built student accommodation and care homes. For all other premises — including an ordinary domestic garage — the same regulation recommends them rather than requiring them. Where fitted, they go at the origin of the circuit being protected.

In the app

Price the job in minutes, not evenings

Professional quotes with the remedial estimator, then invoice from your phone the moment the work is done. From £6.99/mo.

06 · Cost Guide

EV Charger Add-On to a Garage Installation

If the garage is being wired anyway, adding an EV charger circuit costs a fraction of what the same charger costs as a standalone visit. The supply cable, the trench and the consumer unit are the expensive parts, and they are already paid for.

RouteCostNotes
Added to the garage job£200 – £4007 kW / 32 A circuit only. Cable and board already covered by the main job
Standalone installation£600 – £1,200Separate visit, separate cable route and board work
Charger unit itself£500 – £900Typical range for a smart charger. Not included in either figure above

Sizing the supply for a charger

A 7 kW charger needs a dedicated 32 A circuit and draws close to that continuously, so the supply SWA has to be sized for the load with the correction factors that apply to its actual reference method — depth of burial, grouping with other circuits and any thermal insulation. On runs over roughly 20 metres, 10mm² SWA is commonly what the voltage drop calculation lands on. Full detail is in the EV charger installation cost guide.

On grants: the domestic Electric Vehicle Homecharge Scheme closed to most homeowners in 2022. The remaining chargepoint grants are aimed at flat owner-occupiers, renters, landlords and workplaces, and are administered by the Office for Zero Emission Vehicles (OZEV). Check current eligibility on GOV.UK before you promise a customer a contribution — the schemes and the amounts change.

07 · Cost Guide

Building Regulations and Part P

In England and Wales, installing a new circuit to supply a garage, and installing or replacing a consumer unit, is notifiable work under Part P of the Building Regulations. That applies whether the garage is detached or integral. Minor work on an existing circuit outside a special location is generally not notifiable. Scotland and Northern Ireland operate their own building standards regimes.

DocumentWhat it is and why it matters
Electrical Installation CertificateThe EIC records the design, construction, inspection and test results, and is required by Reg 644.1. It is the compliance evidence solicitors routinely ask for on garage and outbuilding work when a property is sold.
Building Regulations Compliance CertificateIssued when an electrician registered with a competent person scheme such as NICEIC or NAPIT self-certifies the work and notifies building control on your behalf. Without a registered electrician, the alternative is a building control application before the work starts.
EV chargepoint notificationThe new circuit is notifiable under Part P in the usual way. Separately, a new chargepoint is normally notified to the distribution network operator; most EV installers handle that as part of the job.

08 · Cost Guide

For Electricians: Quoting Garage Electrical Work

Garage installations are good bread-and-butter work. The scope is well defined, the design is routine, and an EV charger is an easy upsell once the supply cable and board are already on the quote.

Walk the cable route before you price it

Never quote a detached garage from the doorstep. Measure the route, note every surface it crosses, and find out what is already under the driveway. Quote the trenching as its own line item so the customer can see what the ground is costing them, and so a change of route does not eat your margin.

Always price the EV option

If the customer has a car, put the charger on the quote as a priced option rather than mentioning it. Adding a 32 A circuit while the trench is open costs a few hundred pounds; coming back for it later costs four figures. Showing both figures side by side is what closes it — the quoting app will produce the with-and-without version for you.

In the app

Quote garage electrical installations professionally with

Create itemised garage electrical quotes with armoured cable, trenching, consumer unit, and EV charger options. Issue EICs on site.

Frequently Asked Questions About Garage Electrical Installation Costs

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-day free trial

Quote Your Garage Electrical Installation in Minutes

Join 1,000+ UK electricians using Elec-Mate to create professional garage electrical quotes with armoured cable, trenching, and EV charger options. 7-day free trial, cancel anytime.

Start your free trial

From £6.99/mo after the trial — no charge until day 8.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5
  • 7 days free, then from £6.99/mo
  • Cancel in one tap — no calls, no hassle
  • iOS, Android and web
  • Built to BS 7671:2018+A4:2026

Or download the app

Download on the App StoreGet it on Google Play
Certificate types
16Certificate types
Calculators
70+Calculators
Training courses
46+Training courses
AI specialists
8AI specialists

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy