2391-52 REVISION

2391 Written Exam Questions and Model Answers

50 written-style questions, including worked calculations, for City & Guilds 2391-52 (2391 52) Inspection and Testing, with a model answer and the source in BS 7671:2018+A4:2026, GN3 or the On-Site Guide under every one.

£0 today · 7 days free · cancel in two taps

40 min readUpdated 2026-11-26Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

The short answer

What questions come up in the 2391 written exam?

2391-52 written questions test whether you can plan, carry out and justify inspection and testing to BS 7671:2018+A4:2026: inspection before testing, the test sequence, continuity, insulation resistance, polarity, Zs and fault current, RCDs, TT earth electrodes, certification, periodic inspection, EICR codes, and calculations such as R1+R2 and Zs checks.

3,100+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5

Key takeaways

  1. 01Written 2391-52 questions ask you to explain and justify, not just pick an answer, so practise writing the reason and the regulation behind each step.
  2. 02Inspection comes before testing (Regulation 642.1), and the dead tests are done before the installation is energised (Regulation 643.1).
  3. 03Know Table 64 by heart: 0.5 MΩ at 250 V DC for SELV and PELV, 1.0 MΩ at 500 V DC up to 500 V, 1.0 MΩ at 1000 V DC above 500 V.
  4. 04Under A4:2026, an RCD is verified with one AC test at its rated residual current: 300 ms maximum for a general type, 130 ms to 500 ms for an S type.
  5. 05On an EICR, any C1 or C2 makes the report unsatisfactory; a C3 is advisory and does not change the overall outcome.

01 · 2391-52 Revision

How to use these questions

Cover the answer, write your own in a few sentences, then compare. The marks in a written paper come from the reasoning and the regulation, so check you named both. Every answer here gives its source in BS 7671:2018+A4:2026, IET Guidance Note 3, the IET On-Site Guide or Electrical Safety First Best Practice Guide 4, so you can find it in the book.

In 2391-52, written answers are asked for in Task C of the practical assignment (2391-502): a short-answer paper of 80 minutes with BS 7671, the IET On-Site Guide and GN3 permitted. The knowledge test (2391-052) is separate: 60 multiple-choice questions in 120 minutes, open book, with a pass mark of about 75%. Source: City & Guilds 2391-52 handbook v2.4 (April 2026) and Guide to Assessments and Permitted Materials v3.1 (May 2026).

When you are ready to test yourself against the clock, sit the free 2391-52 mock exam, or the 2391-50 and 2391-51 papers on their own.

Free download · PDF

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam, and you can unsubscribe any time.

02 · 2391-52 Revision

Inspection before testing and initial verification

Q1. What is the purpose of initial verification?

Initial verification is carried out on a new installation before it is put into service. Its purpose is to confirm, by inspection and testing during construction and on completion, that the installation complies with the design and construction aspects of BS 7671, so far as is reasonably practicable. BS 7671 defines verification as all the measures used to check compliance, comprising inspection, testing and certification. On completion, an Electrical Installation Certificate based on the Appendix 6 model is issued to the person ordering the work, with its schedules of inspection, circuit details and test results.

Source: GN3 2.1; BS 7671 Regulations 644.1 and 644.3

Q2. Why must inspection come before testing, and what does the inspection confirm?

Regulation 642.1 requires inspection to precede testing, normally with that part of the installation disconnected from the supply. GN3 explains that defects found on inspection should be corrected before testing, so that tests affected by the corrective work do not have to be repeated and so that no test is carried out where safety might be impaired by a defect. The inspection verifies that equipment complies with Section 511, is correctly selected and erected taking account of manufacturers' instructions, and is not visibly damaged or defective so as to impair safety. Regulation 642.3 lists the minimum items to check, and Part 7 requirements must also be included.

Source: BS 7671 Regulations 642.1, 642.2 and 642.3; GN3 2.1

Q3. What safety precautions should be taken before carrying out dead tests?

GN3 states that where testing does not need the installation to be live, it should be made dead and safely isolated, and that HSE GS38 should be followed for test equipment and leads. The On-Site Guide stresses that all sources of supply must be isolated, and where several points of isolation are used each should be secured in the isolated position. Before each use, check that leads, probes, instruments and the proving unit are clean, undamaged and working, that isolation can be safely effected, and that locks or other securing means are available. Confirm with a voltage indicating device at the point of work that no voltage is present, and post warning notices.

Source: GN3 1.1; On-Site Guide 10.1 and Appendix M

Q4. Which tests must be completed before an installation is energised, and what happens if a test fails?

Regulation 643.1 requires the tests of Regulations 643.2 to 643.6, where relevant, to be carried out in that order before energising: continuity of conductors, insulation resistance, protection by SELV, PELV or electrical separation, insulation resistance or impedance of floors and walls, and polarity. Where the installation has an earth electrode, the electrode resistance test of Regulation 643.7.2 must also be done before energising. If any test shows a failure to comply, that test and any earlier test whose result may have been influenced by the fault must be repeated once the fault has been rectified.

Source: BS 7671 Regulation 643.1; GN3 2.6.4

03 · 2391-52 Revision

Continuity: R1 + R2, ring final circuits and bonding

Q5. Describe test method 1 for verifying continuity of protective conductors on a radial circuit.

Using a low-resistance ohmmeter, temporarily connect the line conductor to the circuit protective conductor at the distribution board, removing both from their terminals to avoid parallel earth paths. Then test between line and earth at each point on the circuit. Null the test leads or deduct their resistance. The reading is (R1 + R2), and the value at the circuit extremity is recorded. Added to Ze it gives Zs. As a guide, GN3 shows that a 55 m radial in 2.5/1.5 mm² cable at 19.51 mΩ/m should read at least 1.07 Ω, with terminations likely to add a little more.

Source: BS 7671 Regulation 643.2.1; GN3 2.6.5 (test method 1)

Q6. How is test method 2 used, and how are main protective bonding conductors tested?

Test method 2, the wandering lead method, connects one instrument lead to the protective conductor at the distribution board through a long test lead, while the other lead touches the protective conductor at each point on the circuit. It measures R2 only. GN3 says test method 2 is used to confirm continuity of bonding and earthing conductors, and it may be necessary to disconnect the conductor at one end to remove parallel paths. Because 15 m of 6 mm² or 25 m of 10 mm² conductor is only about 0.05 Ω, where the expected resistance is below 0.1 Ω a value not exceeding 0.1 Ω is a guideline acceptable reading.

Source: GN3 2.6.5 (test method 2; testing bonding conductors and earthing conductors)

Q7. Describe the three-step test for a ring final circuit.

Step 1: at the distribution board, measure the end-to-end resistance of the line (r1), neutral (rn) and protective conductor (r2) separately. Line and neutral should be similar. For 2.5/1.5 mm² cable, r2 is about 1.67 times r1. Step 2: cross-connect the line and neutral ends, outgoing line to returning neutral, and measure line to neutral at every socket-outlet. Readings should be substantially the same, about (r1 + rn)/4. Step 3: cross-connect line and protective conductor in the same way and measure line to CPC at every socket-outlet. The readings are about (r1 + r2)/4, and the highest value is recorded as the circuit's (R1 + R2).

Source: BS 7671 Regulation 643.2.1; GN3 2.6.6

Q8. During a ring final circuit test, what do unexpected readings indicate?

In step 1, an open circuit, or a reading higher than the meter's range, suggests a damaged conductor or poor connections. Readings lower than expected suggest the ring is incorrectly configured, possibly as a figure of eight, which step 2 can confirm. Readings higher than expected point to a termination problem. In step 2, socket-outlets wired as spurs give higher readings. Where single-core cables are used, readings that rise towards the midpoint and then fall again show that the wrong ends have been cross-connected. Parallel paths through metal boxes or containment can lower r2 but not r1 or rn. In GN3's worked example, r1 and rn of 0.6 Ω each give a step 2 reading of 0.3 Ω.

Source: GN3 2.6.6 (steps 1 and 2, Figure 2.19)

04 · 2391-52 Revision

Insulation resistance

Q9. State the test voltages and minimum insulation resistance values in Table 64 of BS 7671.

For SELV and PELV circuits the test voltage is 250 V DC and the minimum insulation resistance is 0.5 MΩ. For circuits up to and including 500 V, other than SELV and PELV, the test voltage is 500 V DC and the minimum is 1.0 MΩ. Above 500 V, the test voltage is 1000 V DC and the minimum is 1.0 MΩ. Insulation resistance is measured between live conductors, and between live conductors and the protective conductor connected to the earthing arrangement. The result is satisfactory if the main switchboard and each distribution circuit, tested separately with its final circuits connected but current-using equipment disconnected, meets the Table 64 value.

Source: BS 7671 Regulations 643.3.1 and 643.3.2, Table 64

Q10. What should be checked and disconnected before an insulation resistance test?

The protective conductor must be connected to the main earthing terminal, which must be connected to the means of earthing. Pilot or indicator lamps and capacitors should be disconnected. Voltage-sensitive electronic equipment such as dimmers, touch switches, delay timers, power controllers, electronic starters, drivers for luminaires and lamps, emergency lighting and RCDs should be disconnected, as should the functional earth leads of RCBOs. The incoming neutral should be disconnected where necessary, taking great care in case of a borrowed neutral. Test with the main switch off, fuses in, switches and circuit-breakers on and lamps removed. Two-way and intermediate switches must be operated and tested in each position.

Source: GN3 2.6.7 (checks before the test, Figures 2.21 and 2.22)

Q11. How is insulation resistance verified on a circuit with equipment that could be damaged by, or influence, the test?

Regulation 643.3.3 sets a two-stage approach. First, test the circuit wiring before the vulnerable equipment is connected, at the Table 64 test voltage, between live conductors and between live conductors and the protective conductor connected to the earthing arrangement. Second, after the equipment is connected, apply 250 V DC between the live conductors (linked together) and the protective conductor connected to the earthing arrangement. The result must be at least 1 MΩ. GN3 adds that the test voltage should be recorded on the schedule of test results. Manufacturers' instructions may recommend disconnecting some equipment even for the 250 V DC test.

Source: BS 7671 Regulation 643.3.3; GN3 2.6.7

Q12. On a new installation a circuit reads 2 MΩ at 500 V DC. Is this acceptable?

It meets the Table 64 minimum of 1.0 MΩ, so it complies with BS 7671 for that test. However, GN3 advises that, although a value as low as 1 MΩ would comply, a new installation should not give a result this low, and any value below 20 MΩ on a new installation should be investigated. Results should always be judged against what is expected for conductors of similar length installed in a similar arrangement. Large or complex installations that give a low overall value may need to be split into their parts and tested separately to find the cause.

Source: BS 7671 Table 64; GN3 2.6.7

05 · 2391-52 Revision

Polarity, earth fault loop impedance and prospective fault current

Q13. What must a polarity test verify?

Regulation 643.6 requires polarity at the origin to be verified before the installation is energised. The test must show that every fuse and single-pole control and protective device is connected in the line conductor only. In circuits with an earthed neutral, centre-contact bayonet and Edison screw lampholders must have the outer or screwed contacts connected to the neutral, except E14 and E27 lampholders to BS EN 60238. Wiring must be correctly connected throughout. GN3 says polarity is checked at all points on a circuit with a low-resistance ohmmeter or by checking core colours, with other lamps removed so they cannot give a false continuity path.

Source: BS 7671 Regulation 643.6; GN3 2.6.12

Q14. How is Ze measured, and how is Zs then determined for a final circuit?

Ze is measured at the origin with an earth fault loop impedance tester, between the line conductor of the supply and the means of earthing, with the main switch open or all circuits isolated. The means of earthing is disconnected from the main earthing terminal for the test to remove parallel paths, and must be reconnected before the installation is energised. Zs can be measured live with a loop tester, or found as Zs = Ze + (R1 + R2) using the continuity results. GN3 prefers the second method for final circuits, but it cannot be used where steel armour, conduit or trunking is the CPC.

Source: BS 7671 Regulation 643.7.3.1; GN3 2.6.15

Q15. What is the maximum Zs for a 32 A Type B circuit-breaker to BS EN 60898, and how is a measured value checked against it?

Table 41.3 gives 1.37 Ω for a 32 A Type B circuit-breaker at Uo of 230 V. Other values from the same table include 7.28 Ω for a 6 A Type B, 2.73 Ω for a 16 A Type B and 0.68 Ω for a 32 A Type C. The values come from Zs × Ia ≤ Uo × Cmin, with Cmin of 0.95 for a supply under the ESQCR. They apply at conductor operating temperature, so a reading taken at ambient needs adjusting. Appendix 3 of BS 7671 gives one method: the measured value should not exceed 0.8 × Uo × Cmin / Ia.

Source: BS 7671 Regulations 411.4.4 and 411.4.202, Table 41.3, Appendix 3; GN3 Appendix A2

Q16. What does BS 7671 require for prospective fault current, and what value is recorded?

Regulation 643.7.3.201 requires the prospective short-circuit current and the prospective earth fault current to be measured, calculated or determined by another method, at the origin and at other relevant points. GN3 explains that the breaking capacity of each protective device must be not less than the prospective fault current where it is installed. The greater of the two values is recorded on the certificate or report and the schedule of test results. Where line-to-line voltage cannot be measured, the three-phase value can be taken as roughly twice the single-phase value. Measurements should be made downstream of a device rated for the expected fault current, since fused leads alone are not suitable.

Source: BS 7671 Regulation 643.7.3.201; GN3 2.6.16

06 · 2391-52 Revision

Earthing, bonding and TT systems

Q17. On a TT installation where an RCD provides fault protection, what does Regulation 411.5.3 require, and what earth electrode resistance values does BS 7671 give?

Two conditions apply. The disconnection time must meet Regulation 411.3.2.2 or 411.3.2.4, and RA × IΔn must not exceed 50 V. RA is the sum of the resistances of the earth electrode and the protective conductor connecting it to the exposed-conductive-parts, and IΔn is the RCD's rated residual operating current. Where RA is not known it may be replaced by Zs. Table 41.5 gives maximum Zs values for non-delayed and S type RCDs, for example 1667 Ω for 30 mA and 167 Ω for 300 mA. Note 2 to the table says the electrode resistance should be as low as practicable, and a value above 200 Ω may not be stable. Regulation 643.1 requires the electrode resistance to be measured before the installation is energised.

Source: BS 7671 Regulation 411.5.3, Table 41.5 and its notes; GN3 2.6.13 (results of earth electrode testing, Table 2.16); GN3 Figure 2.12 note on Regulation 643.1

Q18. Describe how an earth electrode is tested using a dedicated fall of potential earth electrode tester (GN3 test method E1).

Securely isolate the installation from the supply, then disconnect the earthing conductor from the electrode or MET so the test current flows only through the electrode, with no parallel paths. Connect the electrode to C1 and P1 of a four-terminal tester (or X of a three-terminal tester). Drive a current spike well away, at least ten times the maximum dimension of the electrode system, and a potential spike midway between. Take three readings: potential spike midway, then moved back by 10 % of the electrode-to-current spike distance towards the electrode, then 10 % towards the current spike. Compare the readings to find the percentage deviation. Test in the least favourable ground conditions if possible, never water the electrode under test with brine, and reconnect the earthing conductor before energising.

Source: GN3 2.6.13 (test method E1, Figure 2.26); BS 7671 Regulations 542.4.2 and 643.7.2

Q19. Where is main protective bonding required, and how is the minimum size of a main protective bonding conductor found?

Regulation 411.3.1.2 requires extraneous-conductive-parts liable to introduce a dangerous potential difference to be connected to the MET. Examples include metallic water and gas installation pipes, other metallic pipework and ducting, central heating and air conditioning systems, and exposed metallic structural parts. Metallic pipes fed by a plastic service pipe do not normally need it. Where PME conditions do not apply, the conductor must be at least half the csa required for the earthing conductor, not less than 6 mm² and need not exceed 25 mm² copper. Where PME conditions apply, size it from the PEN conductor using Table 54.8, for example 10 mm² for a PEN of 35 mm² or less. Connect as near as practicable to the point of entry, on the consumer's hard metal pipework after any meter, isolation point or union, before any branch pipework.

Source: BS 7671 Regulations 411.3.1.2, 544.1.1 (Table 54.8) and 544.1.2; GN3 Chapter 2 inspection guidance on ADS (presence of protective conductors)

Q20. What minimum sizes does BS 7671 set for supplementary bonding conductors?

Regulation 544.2 sets three cases. Between two exposed-conductive-parts, a sheathed or mechanically protected conductor must have a conductance not less than that of the smaller protective conductor connected to them. Between an exposed-conductive-part and an extraneous-conductive-part, a protected conductor must have a conductance not less than half that of the protective conductor connected to the exposed part. Between two extraneous-conductive-parts, a protected conductor must be at least 2.5 mm². In every case, where mechanical protection is not provided, the minimum is 4 mm². Where one of two extraneous-conductive-parts is also connected to an exposed-conductive-part, the exposed-to-extraneous rule applies to that conductor too.

Source: BS 7671 Regulations 544.2.1, 544.2.2 and 544.2.3

Q21. What should be inspected at the earthing conductor and main earthing terminal during initial verification?

Check that an earthing conductor is present and sized to Section 543, and where PME conditions apply that it also meets the main bonding size in Regulation 544.1.1. A buried earthing conductor must meet Table 54.1. The connection to the electrode or other means of earthing must be sound, electrically and mechanically, protected against corrosion and labelled. A MET must be provided, connecting the CPCs, protective bonding conductors and any functional earthing and lightning protection bonding conductors. It must be readily accessible and identified where separate from switchgear. There must be accessible means to disconnect the earthing conductor for testing, removable only with a tool. Regulation 514.13.1 requires a 'Safety Electrical Connection - Do Not Remove' notice at the electrode connection, at each bonding connection to an extraneous-conductive-part and at a separate MET.

Source: BS 7671 Regulations 542.3.1, 542.3.2, 542.4.1, 542.4.2 and 514.13.1; GN3 2.5.3 inspection checklist items (r) and (s)

07 · 2391-52 Revision

Other initial verification tests

Q22. How are SELV and PELV circuits verified, and how do the tests differ?

Regulation 643.4 requires separation to be confirmed by insulation resistance measurement, with values to Table 64. For SELV, the live parts must be separated from other circuits and from Earth, so GN3 Table 2.13 lists two tests at 250 V DC with a minimum of 0.5 MΩ: between SELV live conductors and all other circuits, including other SELV, PELV and low voltage circuits, and between SELV live parts and Earth. PELV is earthed, so only the separation from other circuits is tested (GN3 Table 2.14). Where SELV or PELV conductors are separated only by insulation covering conductors of both voltage bands, such as in a multicore cable with LV circuits, the test voltage rises to 500 V DC and the minimum to 1 MΩ.

Source: BS 7671 Regulations 643.4, 643.4.1 and 643.4.2, Table 64; GN3 2.6.8 (Tables 2.13 and 2.14)

Q23. How is protection by electrical separation verified, including a separated circuit supplying more than one item of equipment?

First inspect the source to confirm it complies and, if in doubt, measure the voltage to confirm it does not exceed 500 V. Then carry out insulation resistance tests at 500 V DC with a minimum of 1.0 MΩ: between the separated live conductors and the transformer secondary live conductors, and between exposed-conductive-parts of the separated circuit and other protective conductors, exposed-conductive-parts or Earth. Where more than one item is supplied, also test continuity between all exposed-conductive-parts to show they are bonded together, and test the non-earthed bonding conductor at 500 V DC against other circuits' protective conductors and extraneous-conductive-parts (not less than 1.0 MΩ). Inspect socket-outlets and flexible cables for the unearthed bonding conductor, and measure fault loop impedances between live conductors to confirm the protective device operates.

Source: BS 7671 Regulation 643.4.3 and Section 418.3; GN3 2.6.9 (Table 2.15)

Q24. What does functional testing under Regulation 643.10 involve?

Equipment is operated to verify that it is properly mounted, adjusted and installed and works correctly. BS 7671 gives examples: switchgear and controlgear assemblies, drives, controls and interlocks, emergency switching off and emergency stopping systems, and insulation monitoring, and states the list is not exhaustive. Protective devices are tested for function as necessary to check they are properly installed and adjusted. GN3 adds that the settings of adjustable relays and controls should be checked against the designer's requirements. The test facility of any RCD must be verified, and any manually operated test facility on an AFDD verified to the manufacturer's recommendations. GN3 notes that an AFDD with only an automatic test facility cannot be functionally tested. This test does not replace the functional tests required by product standards.

Source: BS 7671 Regulation 643.10 (and Notes 1 and 2); GN3 2.6.19

Q25. What is the difference between checking phase sequence and testing phase rotation, and how is each done?

Regulation 643.9 requires verification that, for polyphase circuits, the phase sequence is maintained at all relevant points throughout the installation. GN3 says this is achieved in practice by checking polarity and connections. With the circuits isolated it can be confirmed by continuity testing in the same way as R1 + R2, linking each line conductor to the protective conductor one at a time. Phase rotation describes which way a correctly wired three-phase induction motor will run. Swapping any two line conductors reverses it. GN3 recommends testing rotation at the point closest to the load before the load is energised, for example for three-phase laundry equipment, using a phase rotation tester of the rotating disc or indicator lamp type.

Source: BS 7671 Regulation 643.9; GN3 2.6.17 (Figure 2.30)

In the app

Practise with unlimited mock exams

AI-generated mocks, instant marking, and explanations on every question — targeted at your weakest topics. From £6.99/mo.

Download on the App StoreGet it on Google Play

08 · 2391-52 Revision

RCD testing under BS 7671:2018+A4:2026

Q26. When must the operation of an RCD be tested, and where is 30 mA additional protection required?

GN3 says RCD operating times must be tested where the RCD is relied on for disconnection under Chapter 41 (Regulation 643.7.1), and where it provides additional protection (Regulation 643.8). If the circuit meets Chapter 41 without the RCD, testing is not essential unless the RCD is specified for additional protection. Under Regulation 411.3.3, additional protection by an RCD not exceeding 30 mA is required for socket-outlets rated up to 32 A and for mobile equipment rated up to 32 A used outdoors. A documented risk assessment exception applies only to sockets in other locations. Regulation 411.3.4 requires it for AC final circuits supplying luminaires in domestic premises.

Source: GN3 2.6.18; BS 7671 Regulations 411.3.3, 411.3.4, 643.7.1 and 643.8

Q27. What test does BS 7671 require to verify an RCD, and what are the pass criteria?

Regulations 643.7.1 and 643.8 require the RCD to be verified with test equipment to BS EN 61557-6, confirming that Chapter 41 is met. The notes say that, regardless of RCD type, effectiveness is deemed verified where the RCD disconnects within these times with an AC test at its rated residual operating current (IΔn): 300 ms maximum for a general non-delay type, and between 130 ms and 500 ms for a delay S type. GN3 confirms that only the 1 × IΔn test with the instrument set to Type AC is required. It is done at both 0° and 180°, and the longer time is recorded. Tests at 5 × IΔn and Type A, F or B tests are optional.

Source: BS 7671 Regulations 643.7.1 and 643.8 (Notes); GN3 2.6.18, Table 2.18

Q28. What safety checks come before an RCD test, and when would the upstream/downstream method be used?

Press the RCD test button first to confirm the device works. Then test earth fault loop impedance, because test method 1 applies a residual current between line and CPC on the load side, and this can put a dangerous voltage on exposed-conductive-parts if the earth path is poor. Disconnect the load during the test. Test method 2, the upstream/downstream test, is applied between a live conductor on the supply side and another on the load side. It can be used where method 1 is not conclusive, for example with an upstream RCD and no selectivity, protective conductor currents or an IT system, or where an EFLI test first is not practicable. Check the instrument supports it.

Source: GN3 2.6.18 (RCD test methods 1 and 2)

Q29. What does the RCD integral test button prove, and what does it not prove?

Regulation 643.10 requires the effectiveness of any test facility built into an RCD to be verified. GN3 explains that the test button confirms the mechanical parts of the RCD work. It does not check the continuity of the earthing conductor or CPCs, any earth electrode or other means of earthing, any other part of the installation earthing, or the sensitivity of the device. The button only works when the RCD is energised. The notice in Regulation 514.12.2 tells users to test six-monthly with the test button, although that notice need not be fitted in domestic premises where certification or an EICR with guidance for recipients has been issued.

Source: BS 7671 Regulations 643.10 and 514.12.2; GN3 2.6.18 (integral test device)

09 · 2391-52 Revision

Certification and alterations

Q30. When is an Electrical Installation Certificate required, and when may a Minor Electrical Installation Works Certificate be used instead?

Regulation 644.1 requires an Electrical Installation Certificate (EIC) for a new installation, or for an addition or alteration, including the replacement of a distribution board or consumer unit. Regulation 644.4.201 allows a Minor Electrical Installation Works Certificate (MEIWC) as an alternative only where the work does not include a new circuit or the replacement of a distribution board or consumer unit. Typical minor works are adding a socket-outlet or lighting point to an existing circuit, moving a light switch, or replacing accessories or luminaires. GN3 says several minor works on one circuit can go on one MEIWC, but work on several circuits needs a separate MEIWC for each circuit, or an EIC. Appropriate inspection and testing is still needed however small the job.

Source: BS 7671 Regulations 644.1 and 644.4.201; Appendix 6 notes for the person producing the MEIWC; GN3 2.2

Q31. Who signs an Electrical Installation Certificate, and what must be issued with it?

Under Regulation 644.4 the person or persons responsible for the design, construction and verification issue the Certificate, reflecting their respective responsibilities, to the person ordering the work. The multiple-signature EIC lets different people sign for design, construction and inspection and testing, with two design signatures where responsibility is shared. Where one person is responsible for all of it, the single-signature declaration in Appendix 6 may be used. Regulation 644.5 requires the signatories to be skilled persons competent to verify that BS 7671 has been met. Regulation 644.3 requires the Schedule(s) of Inspection, Circuit Details and Test Results, based on the Appendix 6 models. The recommended interval to the first periodic inspection must also be recorded on the Certificate.

Source: BS 7671 Regulations 644.3, 644.4 and 644.5; Appendix 6 Introduction items (a), (e) and (h); GN3 2.2

Q32. What must be checked on an existing installation before an addition or alteration is made, and how are defects in the existing installation dealt with?

Regulation 132.16 says no addition or alteration may be made unless the rating and condition of existing equipment, including the distributor's equipment, are adequate for the altered circumstances, and the earthing and bonding needed for the protective measure are adequate. GN3 1.4 adds that the new work must meet the current edition and must not impair the safety of the existing installation. The relevant parts of the existing installation are inspected and tested, for example protective device types and ratings, conductor sizes, the means of earthing, protective conductor continuity and earth fault loop impedance. Under Regulation 644.1.2, defects affecting the safety of the new work are corrected before the certificate is issued. Other defects seen are recorded on the EIC or MEIWC.

Source: BS 7671 Regulations 132.16 and 644.1.2; GN3 1.4

10 · 2391-52 Revision

Periodic inspection in practice

Q33. What is the purpose of periodic inspection and testing?

Regulation 651.1 states the aim is to determine, so far as is reasonably practicable, whether the installation is in a satisfactory condition for continued service. Under Regulation 651.2 the inspection is carried out without dismantling, or with partial dismantling, supported by appropriate tests from Chapter 64. It covers the safety of persons and livestock against electric shock and burns, protection of property against fire and heat, the correct rating and setting of protective and monitoring devices, damage or deterioration that impairs safety, and defects and non-compliances that may give rise to danger. An installation built to an earlier edition is not necessarily unsafe. The work must not itself cause danger (651.3), and findings are recorded in a report (651.4).

Source: BS 7671 Regulations 651.1 to 651.4 (including NOTE 2 to 651.2)

Q34. Who decides the interval between periodic inspections, what factors are considered, and what maximum intervals does GN3 suggest?

The designer recommends the interval to the first periodic inspection on the EIC (644.4). Each later interval is recommended by the inspector on the EICR, with the reason (653.4). Regulation 652.1 lists the factors: the type of installation and equipment, its use and operation, the frequency and quality of maintenance, external influences, and the results of previous certificates and reports. GN3 Table 3.2 gives recommended maximum initial periods, for example: domestic, change of occupancy or 10 years; rented houses and flats, 5 years; industrial, 3 years; swimming pools, 1 year; construction sites, 3 months. These are recommendations, not legal requirements, and the person responsible for the installation decides when the next inspection takes place.

Source: BS 7671 Regulations 644.4, 652.1 and 653.4; GN3 2.4, 3.7 and Table 3.2

Q35. Apart from the end of the recommended interval, when should a periodic inspection be considered, and what should the inspector arrange before starting?

GN3 says periodic inspection should also be considered to assess compliance, on a change of occupancy (especially rented homes), on a change of use, before additions and alterations, after a significant increase in load, and where damage is suspected, for example after flooding. Before starting, the inspector meets the client to agree the scope, programme, access, disruption and how much disconnection is acceptable, and to learn of health and safety, security and fire requirements. Drawings, schedules, the original EIC, previous reports and maintenance records should be obtained and taken into account (Regulation 651.1). Where none exist, investigation is needed first. A visual inspection is made before testing or opening enclosures.

Source: GN3 3.2 and 3.8.1; BS 7671 Regulation 651.1

Q36. On a periodic inspection the installation cannot be fully isolated. How does this affect testing of earthing, bonding and insulation?

GN3 says periodic testing need not repeat the full range of initial tests, and good previous records can reduce it. If the installation is isolated, earthing and bonding conductors may be disconnected from the main earthing terminal to prove continuity. If it cannot be isolated, they must not be disconnected, because under fault conditions exposed-conductive-parts and extraneous-conductive-parts could rise to a dangerous voltage. Earth fault loop impedance is measured with them connected. A wandering lead test with the conductors still connected confirms connection, not continuity, and this should be noted. Where isolation for insulation resistance testing is not practicable, a leakage current clamp meter can give some information. Regulation 651.3 requires that testing does not cause danger.

Source: GN3 3.10.1, 3.10.3 and Table 3.4 Note 10; BS 7671 Regulation 651.3

Q37. During an EICR you find exposed live parts in a consumer unit where blanks are missing. What should you do?

This is immediate danger. BPG4 says immediate action, even temporary, is needed to make it safer before continuing, for example fitting suitable temporary barriers. It is not enough to mention the danger in the report: the client must be told at the time of discovery and, under the Health and Safety at Work etc Act 1974 and the Electricity at Work Regulations 1989, every effort should be made, with the owner's or user's agreement, to make it safe before leaving site. Action might include switching off and isolating the affected part. The On-Site Guide says the client should be told immediately and in writing. Unless the defect has been permanently put right, it is still recorded on the report and coded C1.

Source: Electrical Safety First BPG4 Sections 5 and 6; On-Site Guide Appendix G3.3

11 · 2391-52 Revision

Sampling, reports and EICR codes

Q38. How should sampling be applied during periodic inspection and testing?

GN3 recommends a walk-round survey to set initial sample sizes, which are then increased if the detailed inspection shows problems. Samples should represent the whole installation, and areas more likely to have problems should come first. Factors include age, work done since the last inspection, usage, environment, maintenance and the quality of records. Sampling the testing of circuits is not generally acceptable: all circuits need inspection and testing within the maximum recommended period. A small domestic installation is likely to be covered 100 %. In large installations the sample can change between visits, for example 20 % over 5 years, as long as the sampled equipment is clearly recorded.

Source: GN3 3.8.2 and 3.8.3

Q39. What must an Electrical Installation Condition Report contain, and how are limitations recorded?

Regulation 653.1 requires an EICR based on the Appendix 6 model. Under Regulation 653.2 it must include the parts inspected and tested, any limitations, any damage, deterioration, defects or dangerous conditions, non-compliances that might give rise to danger, the schedules of inspection, circuit details and test results, and guidance for recipients. Section D records the extent, which should be agreed before work starts, and any agreed limitations with their reasons, confirmed with the person ordering the report. Operational limitations, such as being unable to access part of the installation, are also recorded there. Regulation 653.4 requires a recommended interval to the next inspection, with an explanation.

Source: BS 7671 Regulations 653.1, 653.2 and 653.4; Appendix 6 notes for the person producing the Report

Q40. Explain codes C1 and C2, giving an example of each.

C1 means 'Danger present': there is a risk of injury and immediate remedial action is required. The client should be told straight away, and in writing, without waiting for the full report. BPG4 C1 examples include a missing protective device with no blank fitted, leaving live parts open to touch, and incorrect polarity at the origin. C2 means 'Potentially dangerous': urgent remedial action is required, because the defect would become an immediate danger if a fault or other foreseeable event occurred. BPG4 C2 examples include no reliable means of earthing, a gas or water pipe used as the means of earthing, insulation resistance below 1 MΩ to Earth, and a borrowed neutral.

Source: Electrical Safety First BPG4 Sections 6 and 9; BS 7671 Appendix 6

Q41. When is C3 or FI used, and how do the codes decide the overall outcome of an EICR?

C3 means 'Improvement recommended'. The item is not a source of immediate or potential danger, but improving it would make the installation safer. BPG4 C3 examples include a Type AC RCD where a Type A is required, no RCD for AC lighting circuits in a dwelling, and inaccessible main bonding to a pipe. FI means further investigation is advised: the inspector has found a potential issue but cannot give a code because of the extent or limitations. BPG4 gives no FI examples for domestic installations. Each observation gets one code, the most serious that applies. Any C1 or C2 makes the report unsatisfactory, while a report with only C3 observations can be satisfactory.

Source: Electrical Safety First BPG4 Sections 6, 7 and 9; BS 7671 Appendix 6 notes for the person producing the Report

12 · 2391-52 Revision

Inspection checks and EICR coding

Q42. What should be checked in a location containing a bath or shower, and when may supplementary bonding be left out?

Zone 0 is the inside of the bath or shower basin. Zone 1 extends to the higher of the highest fixed shower head or 2.25 m above the floor, and zone 2 extends 0.60 m beyond zone 1. Equipment needs at least IPX7 in zone 0 and IPX4 in zones 1 and 2. Socket-outlets, other than SELV or shaver supply units, are not allowed within 2.5 m horizontally of zone 1. Low voltage circuits serving the location need RCD additional protection. Regulation 701.415.2 requires supplementary bonding, but it may be omitted in a building with main protective bonding where all final circuits meet automatic disconnection, all have RCD additional protection, and all extraneous-conductive-parts are effectively connected to the main bonding. BPG4 codes missing bonding where required as C2.

Source: BS 7671 Regulations 701.32.2 to 701.32.4, 701.411.3.3, 701.415.2, 701.512.2 and 701.512.3; Electrical Safety First BPG4 Section 9 (Bathrooms)

Q43. When inspecting protective devices, what restrictions apply to Type AC RCDs, and where are AFDDs required?

Regulation 531.3.3 sets out RCD Types AC, A, F and B. A Type AC RCD may only serve fixed equipment where the load current is known to contain no DC components, such as electric heating or simple filament lighting without electronic parts. Type AC RCDs must not be used in group 1 and group 2 medical locations. Under Regulation 421.1.7, AFDDs to BS EN 62606 are required on single-phase AC final circuits supplying socket-outlets rated up to 32 A in high rise residential buildings, HMOs, purpose-built student accommodation and care homes, and are recommended elsewhere. BPG4 codes a missing AFDD in those buildings as C3 and elsewhere as an observation. AFDDs with a test button are given a functional check.

Source: BS 7671 Regulations 531.3.3 (including NOTE 5), 710.531.3.3.101 and 421.1.7; Electrical Safety First BPG4 Section 9 (AFDD); GN3 Table 3.4

Q44. Code these EICR observations: (a) the cable sheath stops short of a socket-outlet box and the unsheathed cores can be touched; (b) the same fault at a switch where the cores cannot be touched or reach metalwork; (c) unenclosed connections at a luminaire.

(a) is C2, potentially dangerous. BPG4 lists a sheath not taken inside an accessory enclosure as C2 where the unsheathed cores are accessible to touch or likely to contact metalwork, because a fault would make it an immediate danger. (b) is C3, improvement recommended. The same defect is listed as C3 where the cores are not accessible to touch and not likely to contact metalwork. (c) is C2: BPG4 lists unenclosed electrical connections, such as at luminaires, as C2 and notes they can contribute to a fire. Each observation gets a single code, the most serious that applies, and any C2 makes the overall condition unsatisfactory.

Source: Electrical Safety First BPG4 Sections 6, 7 and 9 (Installation Faults)

Q45. Code these consumer unit observations: (a) a blank is not secure and the unit has no lockable lid; (b) the same, but the unit has a lockable lid; (c) a circuit-breaker of another make, not verified by the manufacturer, shows signs of heat damage.

(a) is C2. BPG4 lists a blank that is not suitably secured or durable in a consumer unit without a lockable lid as C2, because there is potential access to live parts. (b) is C3, because the lockable lid reduces the risk. (c) is C2. Mixed-brand components not verified by their manufacturers are C2 where any one of these applies: thermal damage, a modified enclosure, a component not securely fitted or with poor connections, incorrect manual operation, or toggles working in a different direction. Where none of those apply the same mix is C3. If a device were missing with no blank and live parts open to touch, that would instead be C1.

Source: Electrical Safety First BPG4 Section 9 (Equipment/Accessories; Access to Live Parts)

Q46. On an EICR the 'Safety Electrical Connection Do Not Remove' notice is missing from a bonding clamp, and the distributor's service head cover is cracked. How is each recorded?

Regulation 514.13.1 requires this notice at the connection of every earthing conductor to an earth electrode, at every bonding connection to an extraneous-conductive-part, and at the main earthing terminal where separate from the main switchgear. BPG4 codes its absence as C3, the same as missing circuit identification at the consumer unit or a missing notice for an alternative source of supply. The distributor's intake equipment gets a visual inspection only. A defect there is marked 'X' with a comment in Section K, but it does not decide the overall outcome unless live parts are accessible. The client should be told to report a dangerous or potentially dangerous condition urgently to the network operator or supplier on 105.

Source: BS 7671 Regulations 514.13.1 and 514.15.1; Electrical Safety First BPG4 Sections 8 and 9 (Notices)

13 · 2391-52 Revision

Worked calculations

Q47. A TT installation is protected by a 30 mA RCD. A fall of potential test gives readings of 98 Ω, 100 Ω and 102 Ω. Is the result reliable, and does the electrode satisfy Regulation 411.5.3?

  1. Step 1, average: (98 + 100 + 102) / 3 = 100 Ω.
  2. Step 2, maximum deviation from the average: 2 Ω, which is 2 / 100 × 100 = 2 %.
  3. Step 3, accuracy is typically 1.2 × the percentage deviation: 1.2 × 2 = 2.4 %. GN3 advises against accepting readings that differ by more than 5 %, so this result is acceptable.
  4. Step 4, maximum RA: 50 V / 0.03 A = 1667 Ω, the same value given in Table 41.5.
  5. Step 5, check: RA × IΔn = 100 × 0.03 = 3 V, well under 50 V.

The electrode complies. At 100 Ω it is also below the 200 Ω above which Table 41.5 Note 2 warns the value may not be stable. RA should strictly include the earthing conductor resistance, which is small here.

Source: GN3 2.6.13 (test method E1, results of earth electrode testing); BS 7671 Regulation 411.5.3, Table 41.5 and Note 2

Q48. A 16 A Type B circuit-breaker to BS EN 60898 protects a 60 m radial in 2.5/1.5 mm² copper cable. Measured Ze is 0.80 Ω. Using GN3 Table B1, find the expected Zs and check it with the Appendix 3 rule.

  1. Step 1, R1 + R2: GN3 Table B1 gives 19.51 mΩ/m for 2.5/1.5 mm² copper at 20 °C. 60 × 19.51 / 1000 = 1.17 Ω.
  2. Step 2, Zs = Ze + (R1 + R2) = 0.80 + 1.17 = 1.97 Ω.
  3. Step 3, limit: Table 41.3 gives 2.73 Ω for a 16 A Type B device at Uo of 230 V. That value applies at conductor operating temperature, so Appendix 3 applies a factor of 0.8 to the measured value: 0.8 × 2.73 = 2.18 Ω.
  4. Step 4, compare: 1.97 Ω does not exceed 2.18 Ω, so the circuit complies, although with little margin.

A measured R1 + R2 noticeably above 1.17 Ω would point to poor terminations, and should be investigated before relying on this result.

Source: GN3 2.6.5 and Appendix B Table B1; BS 7671 Table 41.3(a), Appendix 3; GN3 Appendix A2

Q49. A ring final circuit in 2.5/1.5 mm² cable gives end-to-end readings of r1 = 0.40 Ω and rn = 0.40 Ω. What r2 should be expected, and what readings should steps 2 and 3 give?

  1. Step 1, expected r2: the CPC is smaller, so r2 = r1 × (2.5 / 1.5) = 0.40 × 1.67 = 0.67 Ω. A reading close to this confirms the CPC loop.
  2. Step 2, line to neutral cross-connected: about (r1 + rn) / 4 = (0.40 + 0.40) / 4 = 0.20 Ω at every socket-outlet.
  3. Step 3, line to CPC cross-connected: about (r1 + r2) / 4 = (0.40 + 0.67) / 4 = 1.07 / 4 = 0.27 Ω.

With a reduced CPC, step 3 readings rise slightly towards the midpoint of the ring, but GN3 says the difference is typically negligible for 2.5/1.5 mm² rings up to 60 m. Any socket-outlet reading noticeably higher is likely to be a spur. The highest step 3 value is recorded as R1 + R2 for the circuit.

Source: GN3 2.6.6 (steps 1, 2 and 3, Figure 2.19); BS 7671 Regulation 643.2.1

Q50. A radial circuit to fixed equipment has a full load current of 28 A. The measured line plus neutral resistance is 0.30 Ω at about 20 °C, in 70 °C thermoplastic cable. Estimate the voltage drop and check it against BS 7671 Appendix 4.

Voltage drop is not normally verified at initial verification; it is usually enough to check the design calculations. Where it is needed, GN3 allows a calculation from the measured live conductor resistance and full load current, corrected for temperature.

  1. Step 1, uncorrected: 28 × 0.30 = 8.4 V.
  2. Step 2, temperature factor: 1 + 0.004 × (70 − 20) = 1.20.
  3. Step 3, corrected: 8.4 × 1.20 = 10.08 V.
  4. Step 4, limit: for an installation supplied from a public LV network, Table 4Ab allows 3 % for lighting and 5 % for other uses. 5 % of 230 V is 11.5 V.
  5. Step 5, 10.08 V is about 4.4 %, within 5 %, so the circuit complies.

Had it supplied lighting, the 6.9 V (3 %) limit would be exceeded.

Source: BS 7671 Regulations 643.11 and 525.202, Appendix 4 Table 4Ab; GN3 2.6.20; On-Site Guide Appendix F (voltage drop) and Appendix I (Table I3 note 3); GN3 Appendix A3

Frequently Asked Questions

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from electricians and apprentices

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7 days free

Revise every 2391 topic in one place

The Study Centre has the full inspection and testing course, 60+ mock exams and 20,000+ practice questions. Try it free for 7 days. £0 today, card required.

Start your free week

£0 today, then from £6.99/mo after your free week.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5
  • 7 days free, then from £6.99/mo
  • Cancel in two taps, no phone calls
  • iOS, Android and web
  • Built to BS 7671:2018+A4:2026

Or download the app

Download on the App StoreGet it on Google Play
Certificate types
19Certificate types
Calculators
70+Calculators
Training courses
46+Training courses
AI tools
20+AI tools