EV Charger Installation UK Requirements, Regulations & Cost
EV charger installation is one of the fastest-growing areas of domestic electrical work. This guide covers everything an electrician needs to know — charger types, cable sizing, earthing requirements, RCD selection, IET Code of Practice compliance, grants, DNO notification, and realistic costs.
“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”
Key takeaways
01A standard domestic EV charger is 7kW single-phase (32A) and requires a dedicated circuit from the consumer unit with no diversity applied — the cable and protective device must be rated for 32A continuously.
02On a PME (TN-C-S) supply, Regulation 722.411.4.1 bars the PME earth for an outdoor charge point unless one of methods (b) to (e) is used. Most domestic jobs use a charger with built-in open-PEN protection, so no earth rod is needed.
03RCD protection must be at least Type A with 6mA DC detection, or Type B RCD if the charger does not have built-in DC residual current monitoring.
04The OZEV flats and renters grant gives up to £500 per socket until 31 March 2027. The customer applies on GOV.UK and must wait for OZEV to confirm eligibility before the charger is installed; an OZEV-authorised installer then claims it.
05Typical all-in cost for a domestic 7kW EV charger installation is £800 to £1,500 including the charger unit, cable, protective devices, earth rod (if needed), testing, and certification.
01 · High Value Guide
Types of EV Charger
Electric vehicle chargers are categorised by their power output and the type of electrical supply they require. For domestic and small commercial installations in the UK, there are three main options.
3.6 kW
Slow Charger (16A Single Phase)
Draws 16A from a single-phase supply. Adds approximately 10-15 miles of range per hour of charging. Suitable for overnight charging where the vehicle is parked for 8-12 hours. Less common for dedicated wallbox installations but sometimes used where the supply capacity is limited and load management is not possible. Cable sizing is simpler due to the lower current demand.
7 kW
Fast Charger (32A Single Phase)
The standard for domestic installations. Draws 32A from a single-phase supply. Adds approximately 20-30 miles of range per hour. Fully charges most EVs overnight in 6-8 hours. This is the charger type covered by the OZEV grant scheme and the IET Code of Practice. Requires a dedicated 32A circuit with no diversity, appropriate cable sizing, and RCD protection.
22 kW
Fast Charger (32A Three Phase)
Requires a three-phase supply, which most domestic properties do not have. Adds approximately 60-80 miles of range per hour. Primarily used in commercial settings — workplaces, car parks, fleet depots. The vehicle must also support three-phase AC charging (many do not — they have a single-phase onboard charger regardless of the supply). Installation is significantly more complex and expensive.
For the vast majority of domestic installations, the 7 kW single-phase charger is the correct choice. It provides a practical charging rate for overnight use and is compatible with the standard single-phase supply available to almost every UK property. The rest of this guide focuses primarily on 7 kW single-phase installations.
Free download · PDF
Get the BS 7671 A4:2026 Cheat Sheet — free
Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.
Every regulation change summarised
New model forms (EIC + MEIWC)
Free PDF — no subscription
02 · High Value Guide
Installation Requirements
Installing an EV charger is not simply mounting a wallbox and running a cable. BS 7671 Section 722 sets out specific requirements for EV charging circuits, and the IET Code of Practice for Electric Vehicle Charging Equipment Installation provides detailed guidance. The key requirements are:
BS 7671 Section 722 Requirements
Dedicated circuit (Regulation 722.533.101) — Each EV charging point must be supplied by its own dedicated circuit from the distribution board. The circuit must not supply any other load.
Continuous duty rating — The cable, protective device, and all connections must be rated for the full load current (32A) drawn continuously. No diversity is applied to EV charging circuits because the vehicle can charge at maximum rate for extended periods.
Cable sizing — Size the cable from BS 7671 Appendix 4 for the route, method and length. For a 32 A charger, 6mm² twin-and-earth is a common start, and 10mm² is often needed on longer runs to meet the 5% voltage drop limit. SWA (steel wire armoured) cable for external underground runs.
PME earthing restrictions (Regulation 722.411.4.1) — On PME supplies, an outdoor charge point may only use the PME earth with one of methods (b) to (e): usually a charger with built-in open-PEN protection, or an earth electrode on the main earthing terminal sized to the 70 V limit.
30 mA RCD protection (Regulation 722.531.3.101) — A 30 mA Type B RCD, or a Type A or F RCD where the charger has a built-in 6 mA DC detection device (RDC-DD) to BS IEC 62955.
Local switching — Not always required, because the 30 mA RCD covers emergency switching. The IET Code of Practice (6.11.1) asks for a readily accessible means of switching off where the car charges inside a garage; follow the charger maker's instructions.
In the app
Cable Sizing Calculator for EV Circuits
Elec-Mate's cable sizing calculator handles EV charger circuits with all the specific requirements — 32A continuous load, voltage drop calculation…
03 · High Value Guide
Earthing and PME Considerations
The earthing arrangement is one of the most critical — and most commonly misunderstood — aspects of EV charger installation. The majority of UK domestic properties have a TN-C-S (PME) earthing system, which creates a specific safety concern for EV charging.
On a PME supply, the neutral and earth are combined in the supply cable as a single PEN conductor. If this PEN conductor breaks (an "open PEN" fault), the voltage on the PME earth terminal can rise to a dangerous level — potentially up to 230V. Because an EV charging cable provides a direct metallic connection between the installation earth and the vehicle chassis (which a person may be touching), this creates a risk of fatal electric shock.
BS 7671 Regulation 722.411.4.1 addresses this: a PME earth may not be used for an outdoor charge point unless one of methods (b) to (e) is applied. Method (b) connects the main earthing terminal to an earth electrode sized so the voltage to Earth stays at or below 70 V under an open PEN (Annex A722, Item A722.3). Methods (c) and (d) are devices that disconnect the vehicle, including its earth, when the voltage goes out of limits, and (e) is an equivalent device. Most domestic chargers now have open-PEN protection built in, and the IET Code of Practice (6.6.2.2) says this will often be the most appropriate solution.
Critical Installation Point
Method (b) is not a TT conversion: the installation stays on PME and the electrode is added to the main earthing terminal. Making the EV circuit TT is a separate option that BS 7671 (NOTE 3 to 722.411.4.1) and the IET Code of Practice warn may not be the safest, and it needs a risk assessment covering separation from PME-earthed metalwork.
For properties with an existing TN-S earthing system (earth provided by the cable sheath) or TT system (existing earth electrode), the PME rule in 722.411.4.1 does not apply, but the 30 mA RCD protection is still mandatory. Always check the earthing arrangement before specifying the installation design.
04 · High Value Guide
RCD and Circuit Protection
The circuit protection for an EV charger must address both overcurrent and earth fault conditions. The standard protective device arrangement for a domestic 7 kW charger is:
Standard Arrangement
32A Type A RCBO (30 mA) — where the charger has built-in 6 mA DC residual current detection. Most modern domestic chargers (Zappi, Ohme, Pod Point, Easee, Wallbox) include this DC detection, allowing the use of a Type A device rather than the more expensive Type B.
The charger monitors for DC residual currents internally and disconnects if the DC component exceeds 6 mA. The Type A RCBO in the consumer unit then provides protection against AC and pulsating DC fault currents.
Alternative Arrangement
32A Type B RCD + MCB (or Type B RCBO) — where the charger does not have built-in DC detection. A Type B RCD detects smooth DC fault currents that a Type A cannot. This is more expensive (Type B RCDs cost £150-£300 compared to £30-£50 for a Type A RCBO) but is essential where the fault current may have a DC component.
Always check the charger manufacturer's installation manual for the specific RCD type required.
The circuit breaker rating should be 32A for a standard 7 kW single-phase charger. A Type C characteristic is typically specified (rather than Type B) because the charger may draw brief inrush currents on start-up that could nuisance trip a Type B device. Again, check the manufacturer's specification.
05 · High Value Guide
IET Code of Practice for EV Charging
The IET Code of Practice for Electric Vehicle Charging Equipment Installation is the definitive guidance document for EV charger installations in the UK. It supplements BS 7671 Section 722 with detailed, practical guidance on every aspect of the installation. While the Code of Practice is not a regulation in itself, it is widely regarded as the industry standard and is referenced by competent person schemes, manufacturers, and grant bodies.
The Code of Practice covers:
Charging modes and connector types — Detailed explanation of Mode 1, 2, 3, and 4 charging and the Type 1, Type 2, CCS, and CHAdeMO connectors.
Supply assessment — How to assess whether the existing supply can accommodate the additional load, including maximum demand calculation and load management options.
Earthing assessment — The PME earthing considerations, TT earth electrode installation, and earth electrode resistance testing.
Circuit design — Cable selection, voltage drop, protection coordination, and installation methods.
Certification requirements — What must be documented on the EIC and the additional EV-specific documentation required.
In the app
EV Charger Certificate in Elec-Mate
Elec-Mate has a dedicated EV Charger Certificate form that follows the IET Code of Practice structure.
In the app
Try Elec-Mate free for 7 days
30+ certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 50+ training courses — from £6.99/mo.
06 · High Value Guide
How Much Does an EV Charger Installation Cost in 2026?
The total cost of a domestic EV charger installation depends on the charger unit chosen, the complexity of the cable run, whether an earth rod is needed, and any upgrades required to the existing electrical installation.
Typical UK Costs (2026)
Charger unit (7 kW wallbox)
Ohme, Zappi, Pod Point, Easee, etc.
£300 - £800
Installation labour
Including cable, protective device, testing, EIC
£400 - £700
Earth rod (only if method (b) is used)
Copper-clad rod, connections, testing
£80 - £150
Consumer unit upgrade (if needed)
Additional way, new board if full
£100 - £600
Total installed (typical)
Standard domestic installation
£800 - £1,500
The wide range reflects the variability of installations. A simple job — charger next to the consumer unit, short cable run, existing spare way in the board — can be at the lower end. A complex job — charger in a detached garage requiring a long SWA cable run, earth rod, consumer unit upgrade, and load management — will be at the higher end or potentially above it.
In the app
AI Cost Engineer for EV Installations
Get an accurate quote for any EV charger installation in seconds. Elec-Mate's AI Cost Engineer factors in charger type, cable run length…
07 · High Value Guide
OZEV Grants for Home Chargers (2026)
The Office for Zero Emission Vehicles (OZEV) — formerly the Office for Low Emission Vehicles (OLEV) — runs the home and workplace chargepoint grants. The old Electric Vehicle Homecharge Scheme (EVHS) has closed. From 1 April 2026 the grants pay up to £500 per socket, and funding runs until 31 March 2027.
Since 1 April 2026 the customer applies on GOV.UK, and must not have the charger installed until OZEV confirms they are eligible. An OZEV-authorised installer then claims the grant. The current grants cover:
Flats and renters grant — Flat owners and renters with their own off-street parking. Owner-occupiers of houses are not eligible. Landlords can use the residential landlord grant, and households with on-street parking have their own grant.
Workplace Charging Scheme — Businesses can claim up to £500 per socket (up to 40 sockets) for workplace EV charger installations.
Local authority schemes — Some local councils offer additional grants or funding for residential EV charging, particularly for on-street charging solutions.
To claim any OZEV grant, the installer must be OZEV-authorised and registered with a competent person scheme. The installation must comply with BS 7671 and the IET Code of Practice. Comprehensive documentation is required — including the EV charger certificate, photographs, and DNO notification evidence. Incomplete documentation is the most common reason for grant rejection.
08 · High Value Guide
DNO Notification and Part P Requirements
EV charger installation involves two separate notification requirements: the Distribution Network Operator (DNO) and Building Regulations Part P.
DNO Notification
Every EV charger must be notified to the DNO, through ENA Connect Direct. If the property's maximum demand with the charger stays at or below 13.8 kVA (about 60 A), notify within 28 days of installing. If it goes above that, or the service head looks inadequate, apply before you install (IET Code of Practice, Section 11).
The DNO notification serves two purposes: it allows the DNO to check that the local network can handle the additional load, and it helps with network planning as EV uptake grows. In some cases, the DNO may require a supply upgrade (e.g., from 60A to 100A fuse) before the charger can be connected.
Part P Notification
Installing a new circuit for an EV charger is notifiable under Part P of the Building Regulations. The work must be either self-certified through a competent person scheme or notified to building control.
A full Electrical Installation Certificate (EIC) is required for the new circuit. The EIC must include all the Section 722 specific requirements — PME assessment, earthing details, load management documentation, and complete test results. A Minor Works Certificate is not appropriate.
The maximum demand of the property — including the new EV charger — must be assessed before installation. Elec-Mate includes a maximum demand calculator that factors in the EV charger load and checks it against the supply fuse rating.
How to Install an EV Charger — Step-by-Step Process
1
Site survey and supply assessment
Visit the property and assess the existing electrical installation. Record the earthing arrangement (TN-C-S, TN-S, or TT), supply fuse rating, and current maximum demand. Determine the cable route from the consumer unit to the charger location. Identify the PME protection method if the supply is PME (most chargers have built-in open-PEN protection), whether the consumer unit has a spare way, and whether the supply capacity is adequate for the additional 32A load.
2
Notify DNO and check grant eligibility
Check the maximum demand: if it will exceed 13.8 kVA with the charger, apply to the DNO through ENA Connect Direct before starting work (otherwise notify within 28 days of installing). If the customer wants an OZEV grant, they must apply and receive confirmation of eligibility before you install. Confirm the charger specification with the customer — charger make and model, tethered vs untethered cable, smart charging features, and colour options.
3
Choose the PME protection method
On a PME supply, choose a method from Regulation 722.411.4.1(b) to (e). Most domestic chargers have open-PEN protection built in, so no rod is needed. If you use method (b), connect an earth electrode to the main earthing terminal and size it so the voltage to Earth stays at or below 70 V under an open PEN (Annex A722, Item A722.3).
4
Install the cable and protective device
Install the cable from the consumer unit to the charger location using the correct installation method. For internal runs, use twin-and-earth cable (sized from Appendix 4; 6mm² is common on short runs and 10mm² on longer runs). For external underground runs, use SWA cable buried at minimum 500mm depth with cable covers and route marker tape. Install a 32A RCBO in the consumer unit: Type B, or Type A where the charger has a built-in RDC-DD.
5
Mount the charger and connect
Mount the wallbox at the correct height (manufacturer specification, typically 1-1.5m from ground to centre). Connect the supply cable to the charger following the manufacturer installation instructions. Fit a local means of switching off where the car charges inside a garage or the maker asks for one. Commission the charger — connect to Wi-Fi, set up the smart charging schedule, and configure load management if a CT clamp is fitted.
6
Test, certify, and notify
Carry out the full testing sequence: continuity of protective conductors, insulation resistance, polarity, earth fault loop impedance, prospective fault current, and RCD operating time. Complete the Electrical Installation Certificate with all Section 722 specific documentation. Submit Part P notification through your competent person scheme. Issue the certificate to the customer and retain your copy.
Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.
Fantastic app for electricians
I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.
Absolutely amazing
I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.
Trusted by electricians across the UK
Real feedback from electricians and apprentices
“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”
Daniel Palmer
Sole Trader · DP Electrical
“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”
Nathan Perry
Electrician · NP Electrical Services
“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”
Jake Pizey
3rd Year Apprentice · Apprentice
7 days free
Install EV Chargers With Confidence
EV charger certificates, cable sizing, maximum demand calculator, and AI Circuit Designer — all in Elec-Mate. 7-day free trial, cancel any time.