REGULATIONS GUIDE

Protective Earthing and Bonding: The Complete BS 7671 Guide

Earthing and bonding are the foundation of electrical safety. This guide covers the main earthing terminal, bonding conductor sizes (10 mm and 6 mm), extraneous-conductive-part identification, UK earthing arrangements, and every test you need to carry out.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

12 min readUpdated 2026-06-10Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

The short answer

What is the difference between earthing and bonding?

Earthing connects exposed-conductive-parts (the metal enclosures of the installation) to earth so that fault current can flow and trip the protective device. Bonding connects extraneous-conductive-parts (incoming metal services such as water and gas) together to keep them at the same potential, reducing the shock risk between them. Both are required under BS 7671 Chapter 54 and Section 411.

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5

Key takeaways

  1. 01Protective earthing connects all exposed-conductive-parts to the main earthing terminal, ensuring that fault current can flow and protective devices can operate within the required disconnection time.
  2. 02Main protective bonding conductors connect extraneous-conductive-parts (water pipes, gas pipes, oil pipes, structural steelwork) to the main earthing terminal — typically 10 mm or 6 mm copper depending on the supply.
  3. 03The main earthing terminal is the central connection point where all earthing and bonding conductors meet — it must be accessible and, where separate from the main switchgear, carry the permanent "Safety Electrical Connection — Do Not Remove" warning notice required by Regulation 514.13.1.
  4. 04Regulation 411.3.2.2 and Table 41.1 require disconnection within 0.4 seconds for final circuits up to 32 A (fixed equipment) or up to 63 A (with socket outlets) in TN systems — earthing must be adequate to achieve these times.
  5. 05Elec-Mate includes calculators for earth fault loop impedance, protective conductor sizing, and bonding requirements to help electricians verify compliance on site.

01 · Regulations Guide

Why Protective Earthing and Bonding Matter

Protective earthing and bonding form the foundation of electrical safety in every installation. Without effective earthing, protective devices (MCBs, RCDs, fuses) cannot operate correctly in the event of an earth fault. Without bonding, dangerous voltage differences can develop between the electrical installation and metallic services such as water pipes, gas pipes, and structural steelwork.

When an earth fault occurs — for example, a live conductor touches the metal casing of an appliance — fault current must flow through the protective conductor back to the supply transformer. This fault current must be high enough to trip the protective device within the required disconnection time (0.4 seconds for final circuits up to 32 A supplying fixed equipment, or up to 63 A where socket outlets are present, in TN systems — per Regulation 411.3.2.2 and Table 41.1). If the earthing path has too much impedance (resistance), the fault current will be too low to trip the device quickly, and the metalwork will remain live — creating a risk of electric shock.

Bonding complements earthing by ensuring that metallic services entering the building are at the same electrical potential as the earthing system. Without bonding, a person simultaneously touching an earthed appliance and an unbonded water pipe could experience an electric shock if there is any potential difference between them. Main protective bonding eliminates this risk by connecting all extraneous-conductive-parts to the main earthing terminal.

These are not theoretical concerns. BS 7671 devotes Chapter 41 (Protection against electric shock) and Chapter 54 (Earthing arrangements and protective conductors) to these requirements, and earthing defects are among the most common C1 and C2 observations recorded on EICR reports.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Regulations Guide

UK Earthing Arrangements: TN-S, TN-C-S, and TT

The earthing arrangement of an installation describes how the exposed-conductive-parts are connected to the general mass of earth. The three arrangements used in the UK are:

TN-S — Separate Neutral and Earth

The supply has a separate earth conductor (typically the lead sheath of the underground supply cable). This provides a reliable, low-impedance earth path. The earthing terminal at the consumer intake is connected to the cable sheath. TN-S is common in older urban areas with lead-sheathed cables. The On-Site Guide assumes a typical maximum external earth fault loop impedance (Ze) of 0.8 Ω for TN-S.

TN-C-S — Combined Neutral and Earth (PME)

The most common arrangement in the UK. The supply uses a combined PEN (Protective Earth and Neutral) conductor, which is separated into individual neutral and earth connections at the consumer intake. This provides very low earth impedance (the On-Site Guide assumes a typical maximum Ze of 0.35 Ω) but carries the risk of open PEN faults. Main bonding is critical in TN-C-S systems to limit touch voltages in the event of a PEN conductor failure.

TT — Earth Electrode

The installation has its own earth electrode (typically a driven rod or buried plate) that provides the connection to earth. TT is used where the DNO does not provide an earth terminal — common in rural areas with overhead supply lines. The earth electrode resistance is typically much higher than a supply earth (often 20 to 200 ohms), so RCD protection is essential for fault disconnection in TT systems. Ze is typically much higher and an RCD is the primary means of shock protection.

Identifying the earthing arrangement is one of the first steps in any inspection. It determines the expected earth fault loop impedance values, the bonding requirements, and the type of fault protection that should be in place. Record the earthing arrangement on the EICR and verify it by measuring Ze at the origin.

03 · Regulations Guide

The Main Earthing Terminal (MET)

The main earthing terminal (MET) is the central connection point for the earthing system. Every earthing conductor, bonding conductor, and circuit protective conductor ultimately connects back to the MET. It is the single point where the installation earthing system meets the supply earth or earth electrode.

  • Location. The MET is normally located at or near the consumer unit, close to the incoming supply position. It must be accessible for inspection, testing, and maintenance — do not bury it behind plasterboard or conceal it in an inaccessible void.
  • Connections. The MET receives the earthing conductor from the supply (or earth electrode), the main bonding conductors (water, gas, oil, structural steelwork), and the circuit protective conductors from all circuits. All connections must be secure, accessible, and made with appropriate terminals or connectors.
  • Disconnecting means. Regulation 542.4.2 requires that the earthing conductor (the connection between the MET and the supply earth or earth electrode) can be disconnected for testing purposes. This is typically achieved with a removable link or a bolted connection that can be opened with a tool. The link allows the electrician to measure Ze (external earth fault loop impedance) by disconnecting the installation earth and testing the supply earth independently.
  • Labelling. Regulation 514.13.1 requires a permanent warning notice marked "Safety Electrical Connection — Do Not Remove" at the connection of every earthing conductor to an earth electrode, at the connection of every bonding conductor to an extraneous-conductive-part, and at the main earthing terminal where it is separate from the main switchgear. The notice may be provided on the BS 951 clamp itself or on the warning label supplied with it, and ensures that anyone working near the MET understands that the connection is safety critical.

During a periodic inspection, check the MET for security of connections, signs of corrosion or overheating, presence of the safety label, and accessibility. A corroded or loose MET connection is a common C2 (Potentially Dangerous) observation on EICR reports.

04 · Regulations Guide

Main Protective Bonding Conductors

Main protective bonding conductors connect extraneous-conductive-parts to the main earthing terminal. Their purpose is to maintain equipotential bonding — ensuring that all metallic services in the building are at the same potential as the earthing system, eliminating dangerous touch voltages.

Under BS 7671 Regulation 411.3.1.2 and Section 544, the following services must be bonded to the MET:

  • Water service pipe. Bond as close as practicable to the point of entry into the building, on the consumer side of the stopcock and meter. Use a BS 951 bonding clamp on a clean section of metallic pipe.
  • Gas service pipe. Regulation 544.1.2 requires the connection to be made as near as practicable to the point of entry into the premises, to the consumer's hard metal pipework and before any branch pipework — where practicable within 600 mm of the meter outlet union, or at the point of entry to the building if the meter is external. Gas industry guidance carries the same requirement.
  • Oil supply pipe. Where a property has an oil-fired heating system with a metallic oil supply pipe, this pipe must be bonded.
  • Structural steelwork. If the building has exposed structural steelwork that is accessible and could introduce an earth potential, it must be bonded.
  • Central heating system. Where the central heating system has metallic pipework that is accessible and could introduce a potential from outside the equipotential zone, it should be bonded. In practice, if the water service is bonded and the heating system connects to the bonded water supply, the heating is effectively bonded through that connection — but a separate bonding connection is often installed for belt-and-braces protection.

Each bonding connection must be made with a BS 951 bonding clamp, fitted to a clean section of pipe, and bear a permanent warning notice: "Safety Electrical Connection — Do Not Remove" (Regulation 514.13.1). Run the conductor unbroken from the MET to the bonding clamp wherever practicable; BS 7671 does not prohibit a joint, but Regulation 543.3.2 requires every connection and joint in a protective conductor to remain accessible for inspection, testing and maintenance, so a buried or concealed joint is not acceptable.

In the app

Verify bonding requirements with AI

Describe the installation to Elec-Mate's AI regulations assistant — supply type, services present…

05 · Regulations Guide

Bonding Conductor Sizes: 10 mm vs 6 mm

The size of main protective bonding conductors is determined by BS 7671 Table 54.8. The key rule is:

  • 10 mm copper — the standard requirement for TN-C-S (PME) installations, which is the most common UK supply type. Under Table 54.8, where the supply PEN conductor is 35 mm² or less, the minimum main protective bonding conductor is 10 mm² copper — this covers virtually all single-phase domestic PME supplies.
  • 6 mm copper minimum (non-PME) — where PME does not apply, Regulation 544.1.1 requires the bonding conductor to be not less than half the cross-sectional area of the installation's earthing conductor, with a minimum of 6 mm² copper (and need not exceed 25 mm² copper). In practice, 6 mm is found in some older or smaller non-PME installations, but 10 mm is now the common standard.

For most domestic work, the answer is simple: use 10 mm copper. It is the default size for TN-C-S (PME) supplies, which account for the majority of UK domestic installations. Using 10 mm eliminates any doubt about compliance and provides a robust connection.

The bonding conductor can be single-core green/yellow cable or twin-core with a green/yellow sheath. Where it is clipped to the surface, it should be run neatly and protected from mechanical damage. Where it passes through walls or floors, use grommets or suitable bushings to protect the cable. The conductor must not be reduced in size at any point along its length.

For larger PME installations (three-phase supplies, commercial premises), refer to Table 54.8 and select the bonding conductor size based on the supply PEN conductor cross-sectional area: 35 mm² or less → 10 mm²; over 35 up to 50 mm² → 16 mm²; over 50 up to 95 mm² → 25 mm²; over 95 up to 150 mm² → 35 mm²; over 150 mm² → 50 mm². These are copper equivalent areas — another metal may be used where it affords equivalent conductance. The note to Table 54.8 warns that the local distributor's network conditions may require a larger conductor, so always check with the DNO for very large supplies.

In the app

Try Elec-Mate free for 7 days

16 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.

06 · Regulations Guide

Identifying Extraneous-Conductive-Parts

One of the most debated topics in electrical inspection is: what constitutes an extraneous-conductive-part? Getting this right determines what needs bonding and what does not.

BS 7671 defines an extraneous-conductive-part as: "A conductive part liable to introduce a potential, generally earth potential, and not forming part of the electrical installation." The key phrase is "liable to introduce a potential" — the part must be capable of conducting a voltage from outside the equipotential zone into the installation.

  • Is an extraneous-conductive-part: Metallic water pipes entering the building from the mains supply, metallic gas pipes entering from the street, oil supply pipes from an external tank, structural steelwork connected to the ground, metallic ventilation ducting connected to external building fabric.
  • Is NOT an extraneous-conductive-part: Internal copper pipework connected only to a plastic cold water supply pipe (no metallic connection to earth outside the building), a metal kitchen sink (if only connected to plastic waste pipes), a metal bath (if only connected to plastic waste pipes and the water supply is plastic), metal window frames that are isolated from the building fabric.

The practical test is: can this metallic part introduce a potential from outside the equipotential zone? BS 7671 answers this directly. The note to Regulation 411.3.1.2 states that where non-metallic pipes — plastic, for example — enter the building and are then connected to metallic pipes within the building, the metallic pipes within the building do not normally require protective bonding, as they are unlikely to be extraneous-conductive-parts. Confirm it by assessment or measurement rather than bonding by default, and record the basis of your decision.

During an EICR inspection, you must assess whether all extraneous-conductive-parts are correctly bonded. Missing bonding on a gas or water pipe is a C2 (Potentially Dangerous) observation. Missing bonding on a service that is not actually an extraneous-conductive-part (for example, internal copper connected only to plastic mains) may be recorded as C3 or noted as not required — but you must document your reasoning.

07 · Regulations Guide

Circuit Protective Conductors (CPCs)

Every circuit in the installation has a circuit protective conductor (CPC) that connects the exposed-conductive-parts on that circuit back to the main earthing terminal. The CPC is the green/yellow conductor in a twin-and-earth cable, or a separate green/yellow conductor in conduit or trunking systems.

  • Sizing CPCs. The CPC must be sized according to BS 7671 Table 54.7 or by calculation using the adiabatic equation. For cables with an integral CPC (twin and earth), the CPC size is determined by the cable manufacturer — for example, a 2.5 mm twin and earth cable has a 1.5 mm CPC, and a 6 mm cable has a 2.5 mm CPC. For separate CPCs in conduit or trunking, use Table 54.7 or the adiabatic equation calculator to verify the CPC is adequate.
  • Continuity. The CPC must be continuous from the earthing terminal in the consumer unit to every exposed-conductive-part on the circuit. Continuity is tested during initial verification (R1+R2 test) and during periodic inspection. A break in the CPC means the circuit has no earth fault protection — a C1 (Danger Present) defect.
  • Identification. CPCs must be identified with green/yellow colouring throughout their length. Where a bare CPC is used (as in the uninsulated earth conductor of twin-and-earth cable), it must be sleeved with green/yellow sleeving at every termination point.

Unsleeved CPCs at termination points are one of the most common observations during periodic inspections. While this is typically a C3 (Improvement Recommended) observation, it indicates a lack of attention to detail during the original installation or subsequent alterations. Always sleeve bare CPCs when working on an installation — it takes seconds and demonstrates professional workmanship.

08 · Regulations Guide

Testing Earthing and Bonding

Testing earthing and bonding is a core part of both initial verification and periodic inspection. The key tests are:

  • Continuity of protective conductors (R1+R2). This dead test verifies that the CPC on each circuit provides a continuous path from the earthing terminal to every point on the circuit. Use a low-resistance ohmmeter. The measured value contributes to the Zs calculation.
  • Continuity of main bonding conductors. Verify that each main bonding conductor provides a continuous, low-resistance path from the MET to the bonding clamp on the service pipe. Guidance Note 3 gives a guideline acceptable value of not exceeding 0.1 Ω for a bonding conductor, and readings across a joint made by an earth clamp should approach 0.05 Ω, allowing for instrument resolution and contact resistance. For reference, 25 m of single-core 10 mm² copper is about 0.05 Ω.
  • External earth fault loop impedance (Ze). Measured at the origin with the installation earthing conductor disconnected at the MET. This gives the impedance of the supply earth path and confirms the earthing arrangement type (the Ze value indicates whether the supply is TN-S, TN-C-S, or TT).
  • Earth fault loop impedance at each point (Zs). Measured at each socket outlet and fixed equipment point. Zs must be low enough to ensure the protective device operates within the required disconnection time. Compare measured values against the maximum Zs tables in BS 7671. Use the Zs calculator to verify compliance.

Record all test results on the schedule of test results for the EICR or EIC. Any earthing or bonding defects found during testing should be classified according to the observation code system: C1 for absent or disconnected earthing, C2 for deteriorated or inadequate earthing/bonding, and C3 for missing earth sleeving or recommendations for improvement.

In the app

BS 7671 Table 54.7 | CPC Sizing 2026

BS 7671 Table 54.7 gives the simplified method for sizing circuit protective conductors. Max Zs values are in Table 41.3 (circuit-breakers) and Tables 41.2/41.4 (fuses). Measure Ze and Zs correctly to pass EICR compliance under…

Frequently Asked Questions About Earthing and Bonding

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-day free trial

Verify Earthing Compliance on Site

Elec-Mate gives you earth loop impedance calculators, protective conductor sizing tools, AI regulations lookup, and digital EICR certificates — everything you need to verify and document earthing and bonding. 7-day free trial.

Start your free trial

From £6.99/mo after the trial — no charge until day 8.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5
  • 7 days free, then from £6.99/mo
  • Cancel in one tap — no calls, no hassle
  • iOS, Android and web
  • Built to BS 7671:2018+A4:2026

Or download the app

Download on the App StoreGet it on Google Play
Certificate types
16Certificate types
Calculators
70+Calculators
Training courses
46+Training courses
AI specialists
8AI specialists

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy