UK Solar Data

Solar Panel Sizing Calculator — Design PV Systems for UK Roofs

Calculate the optimal solar panel system size for any UK property. Enter the roof dimensions, orientation, and electricity consumption. Get a recommended kWp capacity, estimated annual yield, battery sizing guidance, and G98/G99 grid connection classification.

kWp CalculationOrientation FactorBattery SizingG98/G99 Limits

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

15 min readUpdated 2026-06-10Andrew Moore, Founder of Elec-Mate
ShareXinW
Follow

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer — DP Electrical

Key Takeaways

  • 1A typical UK domestic solar PV system is 3-4kWp, using 8-10 panels of 400-430W each, and generates approximately 3,000-4,000kWh per year depending on location and orientation.
  • 2South-facing roofs at a tilt of 30-40 degrees produce the highest annual yield in the UK — approximately 850-1,050kWh per kWp installed, depending on geographic location.
  • 3East and west-facing systems produce approximately 85-90% of the yield of a south-facing system, but spread generation more evenly across the day, which can improve self-consumption.
  • 4Systems up to 3.68kW (single-phase) or 11.04kW (three-phase) can connect under G98 (simplified notification). Larger systems require G99 (full application) to the DNO.
  • 5Battery storage of 5-10kWh is typical for domestic systems, allowing surplus daytime generation to be stored for evening use and increasing self-consumption from 30-40% to 60-80%.
  • 6DC strings remain live and at hazardous voltage whenever panels are in daylight — even with the AC isolator off and the inverter disconnected. All DC-side equipment must have double or reinforced insulation (BS 7671 Reg 712.410.101–102).
  • 7BS 7671:2018+A4:2026 has extensively revised Section 712. All current solar PV designs must use the A4:2026 edition. Commissioning requires IR test per string (≥1MΩ at 500V DC), Voc and polarity checks, and a recorded commissioning report.

Solar Panel Sizing Basics for UK Installations

A4:2026 Compliance Alert — Section 712 Extensively Revised

BS 7671:2018+A4:2026 has extensively revised and expanded Section 712 (Solar Photovoltaic Power Supply Systems). All current PV system designs must use the A4:2026 edition. Earlier editions of Section 712 are superseded and do not reflect current regulatory requirements. (BS 7671 Reg 711.42)

Solar panel sizing is the process of determining the optimal system capacity (measured in kilowatts peak, or kWp) for a specific property. The goal is to match the solar generation to the property's electricity consumption, available roof space, and budget — while complying with grid connection regulations and building regulations.

In the UK, solar panel installations have grown significantly. With electricity prices remaining above 20p per kWh, a well-sized solar PV system can save a typical household between £500 and £1,200 per year on electricity bills, depending on the system size, self-consumption rate, and whether battery storage is included.

For electricians, solar PV represents one of the fastest-growing areas of work. The electrical installation must comply with BS 7671 Part 712 (Solar Photovoltaic Power Supply Systems), and the grid connection must meet Engineering Recommendation G98 or G99. The EIC certificate for the solar installation must record the system details, inverter specifications, and AC/DC isolation arrangements.

The Elec-Mate solar sizing calculator handles the design calculations, while the cable sizing calculator and voltage drop calculator verify the AC and DC cabling for the installation.

Size Solar PV Systems in Minutes

Enter the roof dimensions, orientation, and electricity consumption. The calculator recommends the optimal kWp, estimates annual yield…

Try it free for 7 days
Download on the App StoreGet it on Google Play

kWp Calculation — How Many Panels Do You Need?

The system capacity in kilowatts peak (kWp) is determined by the number and wattage of the solar panels. Modern residential solar panels typically range from 370W to 430W per panel. A standard UK domestic system uses 8-12 panels, giving a total capacity of 3-5kWp.

The kWp calculation starts with either the available roof space or the desired annual generation. Working from roof space:

Number of panels = Available area / Panel area

System kWp = Number of panels x Panel wattage / 1000

Standard panel size: approximately 1.7m x 1.0m (1.7m²)

Typical panel wattage: 400W (0.4kWp)

10 panels: 10 x 0.4 = 4.0kWp system

Working from electricity consumption: a typical UK household uses 3,000-4,000kWh per year. In southern England, each kWp generates approximately 900-1,000kWh per year on a south-facing roof. So a 3.5-4.0kWp system roughly matches the annual consumption of an average household — though not all generation will be consumed on site due to the mismatch between generation (daytime) and consumption (evening).

Roof Orientation and Tilt Angle

The orientation (compass direction) and tilt angle of the roof have a significant impact on the annual energy yield of a solar PV system. In the UK, the optimal orientation is due south (180° azimuth) at a tilt angle of 30-40 degrees. This maximises exposure to the sun throughout the year.

Orientation factors (relative to south-facing at 30° tilt):

  • South (180°): 100% — optimal orientation
  • South-east / South-west: 95-97% — minimal loss
  • East (90°) / West (270°): 85-90% — good for spreading generation
  • North-east / North-west: 65-75% — reduced but viable
  • North (0°): 55-65% — generally not recommended

East and west-facing systems are increasingly popular because they spread generation across the morning and afternoon, improving self-consumption rates. A split system — panels on both east and west-facing roof slopes — can generate similar total energy to a south-facing system while providing a more useful generation profile for households that are occupied during the day.

Shading from trees, chimneys, dormers, and neighbouring buildings reduces yield. Even partial shading of a single panel can significantly reduce the output of the entire string (unless optimisers or microinverters are used). A thorough site survey is essential before finalising the panel layout.

Estimating Annual Yield in the UK

The annual energy yield of a solar PV system depends on the system size (kWp), geographic location (solar irradiance), orientation, tilt, shading, and system losses. In the UK, the expected yield varies significantly by region:

Typical annual yield per kWp installed (south-facing, 30° tilt):

  • South-west England: 1,000-1,050 kWh/kWp
  • South-east England: 950-1,000 kWh/kWp
  • Midlands: 880-930 kWh/kWp
  • North England: 830-880 kWh/kWp
  • Scotland: 780-850 kWh/kWp
  • Northern Ireland: 800-870 kWh/kWp

System losses typically account for 10-20% reduction from the theoretical maximum yield. These include inverter efficiency (typically 96-98%), cable losses (1-2%), panel degradation over time (0.5% per year), soiling (1-3%), and temperature losses (panels are less efficient above 25°C). The Elec-Mate calculator applies standard loss factors to give a realistic yield estimate.

For financial calculations, multiply the annual yield by the current electricity rate (typically 20-30p per kWh) to estimate the annual saving. The power consumption calculator can help assess the household consumption profile to determine what proportion of solar generation will be consumed on site versus exported to the grid.

UK-Specific Yield Estimates

The solar calculator uses UK solar irradiance data by region to give accurate yield estimates.

Try it free for 7 days
Download on the App StoreGet it on Google Play

Battery Storage Sizing

Battery storage allows surplus solar generation during the day to be stored and used in the evening when household consumption is highest. Without a battery, a typical household self-consumes only 30-40% of solar generation — the remainder is exported to the grid at a lower rate (typically 4-15p per kWh under the Smart Export Guarantee). With a correctly sized battery, self-consumption can increase to 60-80%.

The optimal battery size depends on the daily surplus generation and evening consumption pattern. For a typical 4kWp system generating 10-12kWh per day in summer, a 5-10kWh battery captures most of the surplus without being oversized for winter when generation is lower.

Typical battery sizing guidance:

  • Small system (2-3kWp): 3-5kWh battery
  • Medium system (3-5kWp): 5-10kWh battery
  • Large system (5-8kWp): 10-13kWh battery
  • Very large (8kWp+): 13-20kWh or multiple units

Battery installations carry specific regulatory obligations beyond standard Part 712 requirements. The IET Code of Practice for Electrical Energy Storage Systems is the required reference for determining testing regimes, acceptance criteria, and safety tests (including battery isolation, DC earthing arrangements, and battery management system considerations) — see GN3 Reg 1.7.

Where a stationary secondary battery is installed, mandatory warning notices must be fixed at the origin of the installation, at the metering position (if remote from the origin), and at each consumer unit or distribution board supplied from the battery — per GN3 Reg 2.37. Additionally, Reg 712.514.102 requires a permanent warning notice at every point of access to DC live parts (distribution boards, combiner boxes) stating that live parts may remain energised after isolation.

Isolation, ventilation, and fire safety must also be considered. The electrical testing calculators in Elec-Mate include tests specific to battery energy storage systems.

Try Elec-Mate free for 7 days

16 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.

Start free trial
Download on the App StoreGet it on Google Play

G98 and G99 Grid Connection Requirements

Any solar PV system connected to the electricity grid must comply with the relevant Engineering Recommendation for grid connection. The classification depends on the total generation capacity:

G98 — Simplified

For systems up to and including:

  • 3.68kW per phase (single-phase)
  • 11.04kW total (three-phase)

Notification only — inform the DNO within 28 days of commissioning. No pre-approval required.

G99 — Full Application

For systems exceeding:

  • 3.68kW per phase (single-phase)
  • 11.04kW total (three-phase)

Full application to the DNO required before installation. May require network studies and reinforcement works.

The G98 limit of 3.68kW per phase is based on 16A at 230V. This means most domestic single-phase systems of up to approximately 9 panels (9 x 410W = 3.69kWp) are close to the G98 boundary. The Elec-Mate calculator checks the inverter AC output against the G98/G99 threshold and flags when a G99 application is required.

It is important to note that the G98/G99 limit applies to the inverter AC output power, not the panel DC capacity. A 4kWp panel array with a 3.6kW inverter would qualify under G98 because the AC export is limited to 3.6kW. The BS 7671 eighteenth edition provides the regulatory framework for the electrical installation side.

DC-Side Safety — Critical Considerations for Electricians

Safety Warning — DC Strings Remain Live After AC Isolation

Under BS 7671 Reg 712.410.101, all electrical equipment on the DC side of a PV installation shall be considered to be energised — even when the AC side is disconnected from the grid and even when the inverter is isolated from the DC conductors. PV arrays continue to generate voltage in daylight regardless of isolation state.

This is one of the most critical safety distinctions between solar PV and conventional electrical work. Switching off an AC isolator or the inverter does not make the DC strings safe to work on. DC cable runs, combiner boxes, and string fusing remain at hazardous voltages (potentially 600V DC or higher on residential systems) whenever the panels are exposed to daylight.

To provide shock protection on the DC side, BS 7671 Reg 712.410.102 requires that one of the following protective measures is applied to all DC-side equipment:

  • (a) Double or reinforced insulation (Section 412): DC wiring, enclosures, and equipment use double insulation or reinforced insulation to provide protection against electric shock without relying on earthing.
  • (b) SELV or PELV (Section 414): The DC side is arranged so that voltage is maintained within extra-low voltage limits. This is only practicable for very small systems.

In practice, the double insulation route (option a) is used for virtually all residential and commercial PV installations. This means specified double-insulated DC cable (typically to EN 50618 / H1Z2Z2-K), double-insulated connectors (such as MC4 or compatible), and double-insulated DC isolators throughout the DC string runs. Single-insulated cable is not acceptable for exposed DC string wiring.

Commissioning and Testing — BS EN 62446 Requirements

Every PV system requires a commissioning test sequence before handover. BS 7671 Part 712 and BS EN 62446 (Grid-connected PV systems — minimum requirements for system documentation, commissioning tests, and inspection) define the acceptance test regime. The following tests must be completed and recorded in the commissioning report:

  • Insulation resistance (IR) test: Each string tested at 500V DC between live conductors and earth. Acceptance criterion: ≥1MΩ (per PWI acceptance criteria for PV strings).
  • Open-circuit voltage (Voc) check: Measure the open-circuit voltage of each string and compare against the expected value calculated from the panel datasheets and site temperature. A significant deviation indicates a wiring fault or damaged panel.
  • Polarity check: Verify correct polarity of all PV string connections, including MC4 connectors, before connecting to the inverter. Reversed polarity can damage the inverter.
  • Earth continuity: Verify continuity of all protective bonding conductors (dead test) prior to energisation.
  • AC output verification: Commission the inverter per manufacturer instructions and verify AC output voltage and frequency are within supply limits.

All test results must be recorded in the commissioning report. Failing to record results is a common error on PV installations and means the system cannot be formally signed off. The EIC certificate for the installation should reference the commissioning report and record the system details, inverter type, string configuration, and verification results.

Generate PV System EIC Certificates

Elec-Mate EIC certificates support solar PV system details, commissioning test results, and BS 7671 Part 712 compliance sign-off.

Try it free for 7 days
Download on the App StoreGet it on Google Play

How to Size a Solar PV System

Five steps to calculate the optimal solar panel system size for a UK property.

1

Survey the roof

Measure the available roof area, note the orientation (compass bearing), tilt angle, and any shading obstructions. Each panel requires approximately 1.7m² of unshaded roof space.

2

Determine electricity consumption

Check the property electricity bills or smart meter data to find the annual consumption in kWh. A typical UK household uses 3,000-4,000kWh per year. Higher consumption supports a larger system.

3

Calculate the system size

Divide the available roof area by the panel area to find the maximum number of panels. Multiply by the panel wattage to get the system kWp. Compare against the consumption to check the system is appropriately sized.

4

Estimate the annual yield

Multiply the system kWp by the location-specific yield factor (800-1,050kWh per kWp depending on UK region) and adjust for orientation and tilt. Apply system loss factors (typically 15-20%).

5

Check G98/G99 classification

Compare the inverter AC output power against the G98 limit (3.68kW single-phase, 11.04kW three-phase). If the system exceeds these limits, a G99 application to the DNO is required before installation.

Solar Sizing Calculator Features

Complete solar PV system design tool for UK electricians — from panel layout to grid connection classification.

kWp System Sizing

Calculate the optimal system capacity based on roof space, electricity consumption, and budget. Supports panels from 300W to 450W with standard dimensions.

Orientation and Tilt Factors

Apply UK-specific orientation and tilt correction factors. Calculates yield for south, east, west, and split-orientation systems with any roof pitch.

Annual Yield Estimation

Region-specific UK yield data from Cornwall to Scotland. Applies standard system loss factors for realistic energy generation predictions.

Battery Sizing Guidance

Recommends battery capacity based on surplus generation and consumption patterns. Calculates self-consumption improvement with and without storage.

G98/G99 Classification

Automatically checks the inverter AC output against G98/G99 grid connection limits and advises whether simplified notification or full DNO application is…

Financial Payback Estimate

Estimates annual savings based on current UK electricity rates and export tariffs. Calculates simple payback period for the system investment.

Frequently Asked Questions

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-Day Free Trial — Cancel Anytime, No Hassle

Design solar PV systems with precision

Join 1,000+ UK electricians using Elec-Mate for solar sizing, cable calculations, and certification. 7-day free trial, cancel anytime.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical

From £6.99/mo after trial — less than a coffee a week

or download the app
Download on the App StoreGet it on Google Play
7 days free, then from £6.99/moCancel in one tap — no calls, no hassleiOS, Android & WebBS 7671 compliant
16
Certificate Types
70+
Calculators
46+
Training Courses
8
AI Agents

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy