INSTALLATION GUIDE

First Fix Electrical: Getting the Hidden Infrastructure Right

First fix is the foundation of every electrical installation. Cable routing, back boxes, containment, and coordination with other trades must be right before the plaster goes on — because mistakes discovered after plastering are expensive to fix. This guide covers everything you need to know.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

12 min readUpdated 2026-06-10Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

What is first fix in electrical installation?

First fix is all the electrical work done before the walls are plastered and floors laid: running cables, fitting back boxes, installing containment (conduit, trunking, capping) and drilling or notching joists within the permitted zones. It must be right first time and coordinated with the other trades, because anything wrong is buried and expensive to put right once the plaster is on. Second fix — accessories, the consumer unit and testing — follows later.

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer — DP Electrical

Key Takeaways

  • 1First fix electrical covers all cabling, containment, back boxes, and infrastructure installed before plastering — getting it wrong means chasing out finished walls later.
  • 2Cable routes must comply with BS 7671 safe zones (Regulation 522.6.202) to prevent future damage from nails, screws, and fixings driven into walls by other trades or occupants.
  • 3A4:2026 (BS 7671:2018+A4:2026) introduces two new requirements that affect consumer unit design at first fix: Regulation 411.3.4 mandates 30mA RCD protection for all domestic lighting circuits; Regulation 421.1.7 recommends AFDD installation on AC final circuits.
  • 4Coordination with plumbers, plasterers, and carpenters is essential — agree back box positions, chase depths, and board access points before anyone starts work.
  • 5Part P notification is required for new circuits in dwellings, new consumer units, and work in special locations (bathrooms, kitchens with new circuits, swimming pools, saunas).
  • 6Elec-Mate's AI circuit designer helps plan the full first fix layout — circuit allocation, cable routes, and containment — before you pick up a drill.
01 · Installation Guide

What Is First Fix Electrical?

First fix electrical is the stage of an electrical installation that takes place before the walls are plastered and the floors are finished. It is the hidden infrastructure — the cables, containment, back boxes, and mounting points that will be concealed behind the finished surfaces. Everything installed at first fix must be correct before it is covered up, because accessing it afterwards means damaging the finished building.

On a typical domestic new build or full rewire, first fix accounts for roughly 60-70% of the total installation time. It involves running all cables from the consumer unit position to every switch, socket, light, and fixed appliance position in the property. It also includes installing containment (conduit, trunking, or cable tray), fitting back boxes into walls, and pulling cables for smoke detectors, data points, and any specialist systems.

The quality of first fix directly determines the quality of the finished installation. Cables routed outside BS 7671 safe zones risk damage from future fixings. Back boxes fitted at the wrong height or in the wrong position mean awkward accessory placements that the customer will notice. Containment that is too small for the number of cables creates overheating risks and makes pulling cables difficult.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Installation Guide

Cable Routing and Safe Zones

Cable routing is the most critical aspect of first fix. Every cable must follow a route that minimises the risk of damage during and after construction, complies with BS 7671 safe zone requirements, and allows the cable to carry its design current without overheating.

BS 7671 Safe Zones (Regulation 522.6.202)

  • Zone (a) — top of wall — within 150mm of the top of the wall or partition (the ceiling line).
  • Zone (b) — wall corners — within 150mm of an angle formed by two adjoining walls or partitions.
  • Zone (c) — from accessories — horizontally and vertically from any accessory, point, or switchgear on the wall (i.e. directly above, below, or to the side of a socket, switch, or spur).
  • All concealed cables (regardless of zone) — Table 52.1 applies to every cable in a wall. Cables in a prescribed zone must additionally be protected by a 30mA RCD (Reg 415.1.1) or comply with Reg 522.6.204 (e.g. earthed metallic enclosure). There is no "floor line" prescribed zone — plan routes accordingly.

A4:2026 First Fix Planning Requirements

BS 7671:2018+A4:2026 introduced two regulations that directly affect consumer unit design and circuit allocation — both must be considered at first fix stage before the board position is fixed and cable sizes are ordered.

  • Reg 411.3.4 — 30mA RCD on domestic lighting circuits (mandatory) — within domestic (household) premises, additional protection by an RCD with a rated residual operating current not exceeding 30mA shall be provided for all AC final circuits supplying luminaires. This is mandatory ("shall"), not advisory. At first fix it means every lighting circuit cable run must be assigned to an RCD-protected way on the board schedule.
  • Reg 421.1.7 — AFDDs on AC final circuits (recommended) — BS 7671 recommends installation of arc fault detection devices (AFDDs) to mitigate the risk of fire in AC final circuits of a fixed installation due to arc fault currents. The wording is advisory ("recommending"), not mandatory. At first fix, AFDD provision affects the consumer unit type and the number of ways required — factor this into the board schedule before ordering the unit.

In practice, planning cable routes before starting drilling and chasing saves significant time. Mark out accessory positions on the walls, plan the cable runs from each position back to the consumer unit, and identify any crossings or shared routes where containment will be needed.

For timber-framed properties, cables are typically run through drilled holes in joists and studs rather than chased into masonry. Holes in joists must be positioned in the centre third of the joist depth, drilled on the neutral axis, and spaced at least three diameters apart. Notches are generally avoided in modern construction — drilled holes are stronger.

03 · Installation Guide

Back Boxes and Mounting Points

Back boxes (also called pattress boxes) are installed at first fix to provide a mounting point for the accessories that will be fitted at second fix. Getting back box selection and positioning right at first fix avoids problems later.

  • Metal back boxes (for masonry walls) — 25mm or 35mm deep for standard switches and sockets, 47mm deep for dimmer switches and some smart switches that have deeper mechanisms. Use galvanised steel boxes with earth terminals.
  • Dry-lining boxes (for plasterboard walls) — cavity-fixing boxes that grip the plasterboard when tightened. Available in single, double, and triple gang sizes. Ensure the box depth does not exceed the plasterboard-to-stud gap.
  • Standard heights — sockets at 450mm from finished floor level (centre of box), switches at 1200mm from finished floor level (centre of box). These are not regulatory requirements but industry standard and Building Regulations Approved Document M recommendations for accessibility.
  • Cooker switch position — within 2m of the cooker but not directly above it (to avoid reaching over hot surfaces). Typically fitted at 1350mm from finished floor level.

Allow sufficient cable at each back box position for the second fix electrician to work comfortably. Leave at least 200mm of cable protruding from each box. This gives enough length to strip, terminate, and push back into the box without straining the connections.

04 · Installation Guide

Containment Systems: Conduit, Trunking, and Cable Tray

Containment protects cables from mechanical damage, simplifies cable management, and provides a professional finish in exposed or surface-mounted installations. The choice of containment depends on the installation environment, the number of cables, and whether the containment will be concealed or visible.

PVC Conduit

Round PVC conduit (20mm or 25mm) is used for concealed runs in masonry walls and floors. Cables are pulled through after the conduit is fixed. Maximum fill rate is 40% of the internal cross-sectional area (BS 7671 Regulation 522.8.1). PVC conduit is not suitable for high-temperature environments or where mechanical impact resistance is needed — use steel conduit instead.

Steel Conduit

Galvanised steel conduit provides mechanical protection and can serve as a CPC (circuit protective conductor) if properly installed with bush, coupler, and earth continuity. Used in commercial and industrial environments where PVC would not provide adequate protection. Steel conduit must be earthed throughout its length.

PVC Trunking

Mini-trunking and dado trunking are used for surface-mounted cable management, commonly in commercial offices and retail premises. Available in various sizes from 16x16mm to 100x50mm and larger. Use Elec-Mate's trunking fill calculator to check the cable count does not exceed the 45% fill rate.

Cable Tray and Basket

Cable tray (perforated or ladder type) and cable basket are used in commercial and industrial installations for running large numbers of cables over long distances. Cables are laid on top of the tray rather than enclosed. Cable tray provides good ventilation, which reduces derating for grouping.

When calculating containment fill rates, use Elec-Mate's conduit fill calculator to verify the cables fit within the maximum permitted fill percentage. Overfilled containment makes cable pulling difficult, can damage cable insulation, and reduces current-carrying capacity due to inadequate heat dissipation.

05 · Installation Guide

Coordination with Other Trades

First fix electrical rarely happens in isolation. On any building project — whether a new build, extension, or rewire — the electrician must coordinate with plumbers, plasterers, carpenters, and the main contractor. Poor coordination is one of the most common causes of delays and rework.

  • Plumber — agree positions for boiler supply, cylinder immersion, unvented cylinder controls, underfloor heating manifold, and any mechanical ventilation. Avoid running cables directly above or below hot water pipes.
  • Plasterer — all first fix must be complete and signed off before plastering starts. Back boxes should be flush with the finished plaster surface (not recessed behind it, and not protruding). Agree the plaster thickness and set back boxes accordingly — typically 12-15mm for one-coat plaster.
  • Carpenter — coordinate stud positions for dry-lining boxes, agree joist drilling positions for cable runs, and confirm kitchen unit layout for worktop socket and switch positions. Cables run through joists must be in the centre third of the joist depth.
  • Main contractor — agree the programme, access arrangements, and any temporary supplies needed for the build. First fix typically follows structural work and precedes plastering in the build sequence.

Use Elec-Mate's quoting app to produce a clear first fix specification and quote that details every accessory position, circuit allocation, and containment requirement. Sharing this with the builder and other trades at the start of the project prevents misunderstandings and keeps the programme on track.

1st and 2nd Fix Electrical: Stage Guide 2026

Elec-Mate's quoting app lets you build a detailed first fix specification with material lists, labour estimates, and professional quotes.

Try it free for 7 days
Download on the App StoreGet it on Google Play

Try Elec-Mate free for 7 days

16 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.

Start free trial
Download on the App StoreGet it on Google Play
06 · Installation Guide

Part P Notification for First Fix Work

Part P of the Building Regulations (England and Wales) makes certain domestic electrical work notifiable. This means the work must either be carried out by a registered competent person (who can self-certify) or notified to Building Control before it starts.

First fix work that is notifiable under Part P includes:

  • Installation of a new circuit — any new circuit added to an existing or new consumer unit.
  • Consumer unit replacement or relocation — including the installation of a new consumer unit in a new build.
  • Any electrical work in a special location — bathrooms, rooms containing a shower, swimming pools, saunas, and hot tub enclosures.
  • A full rewire or new build electrical installation — the entire installation is notifiable.

If you are registered with NICEIC, NAPIT, ELECSA, or another competent person scheme, you can self-certify the work. You complete the installation, carry out initial verification testing, issue the Electrical Installation Certificate, and notify Building Control through your scheme. The scheme issues a Building Regulations Compliance Certificate to the customer.

If you are not registered with a competent person scheme, you must notify Building Control before starting the work. They will inspect at first fix stage (before plastering) and at completion. Building Control charges a fee for this inspection — the amount varies by local authority.

07 · Installation Guide

Common First Fix Mistakes to Avoid

First fix mistakes are expensive because they are hidden behind finished surfaces. By the time a mistake is discovered, it often requires opening up walls or ceilings to fix. These are the most common first fix errors:

  • Cables outside safe zones without protection — running cables diagonally across walls or at random heights without RCD protection or earthed metallic containment. This is a direct breach of BS 7671 Regulation 522.6.202.
  • Not leaving enough cable at back box positions — leaving only 50-100mm of cable makes second fix termination difficult and increases the risk of poor connections. Leave at least 200mm.
  • Wrong back box depth — fitting a 25mm back box for a dimmer switch that needs 35mm or 47mm. The switch mechanism will not fit, requiring the box to be replaced after plastering.
  • Forgetting smoke detector cables — Building Regulations require interlinked smoke and heat detectors. The interconnect cable must be run at first fix. Adding it after plastering means surface-mounted cable or chasing out walls.
  • Not photographing cable routes — take photos of every cable run before plastering. This provides a record for future reference and can be attached to the EIC as supporting evidence.
08 · Installation Guide

First Fix Completion Checklist

Before signing off first fix and allowing plastering to proceed, work through this checklist to ensure nothing has been missed:

  • All cables are run to every accessory position — sockets, switches, lights, spurs, cooker, shower, smoke detectors, data points, EV charger, outdoor lighting.
  • EV charger circuit cable sized with consumer unit capacity assessed — Regulation 722.311.201 permits load curtailment (smart charging / automatic demand management) to be taken into account when determining maximum demand, which can reduce the required cable and board capacity. Required for new builds under Building Regulations Part S.
  • All cables follow safe zone routes (vertical/horizontal from accessories, within 150mm of corners or ceiling line — not floor line).
  • All back boxes are fitted at the correct height and depth, with at least 200mm of cable protruding.
  • Containment is installed where required, with cable fill within maximum limits.
  • Cables are labelled or identified at both ends (at the accessory position and at the consumer unit position). This saves hours at second fix.
  • Continuity and insulation resistance tests carried out on all circuits before plastering — results recorded as part of initial verification. GN3 Regulation 2.5.1 requires that elements likely to be covered are inspected and tested before being made inaccessible; this is part of compliance with Regulation 641.1.
  • Photos taken of all concealed cable routes before plastering.
  • Consumer unit position marked and cables dressed ready for second fix board installation.

Design the full installation before you start drilling

Elec-Mate's AI circuit designer creates a complete circuit schedule, cable sizing, and board layout from your job specification.

Try it free for 7 days
Download on the App StoreGet it on Google Play

Frequently Asked Questions About First Fix Electrical

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-Day Free Trial — Cancel Anytime, No Hassle

Plan First Fix Jobs Properly

Elec-Mate's AI circuit designer, cable sizing calculator, and quoting app help you plan, price, and deliver first fix work professionally. Join 1,000+ UK electricians. 7-day free trial.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical

From £6.99/mo after trial — less than a coffee a week

or download the app
Download on the App StoreGet it on Google Play
7 days free, then from £6.99/moCancel in one tap — no calls, no hassleiOS, Android & WebBS 7671 compliant
16
Certificate Types
70+
Calculators
46+
Training Courses
8
AI Agents

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy