RENEWABLES

Ground Source Heat Pump Electrical: Wiring Guide for UK Electricians

Ground source heat pumps have higher electrical demands than air source — often requiring three-phase supplies, multiple circulation pump circuits, and careful earthing around the ground loop. This guide covers everything an electrician needs to know.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

15 min readUpdated 2026-06-10Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

What electrical supply does a ground source heat pump need?

A domestic ground source heat pump usually needs a dedicated compressor circuit plus separate circuits for the ground-loop and heating circulation pumps, zone valves, the controller, and any buffer-tank immersion heater. Single-phase models run to roughly 10kW electrical input; larger units typically need a three-phase supply, which means a DNO application booked early in the project.

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer — DP Electrical

Key Takeaways

  • 1Ground source heat pumps (GSHPs) typically have higher power demands than air source units — domestic systems range from 6 to 16kW electrical input, with larger properties often requiring three-phase supplies.
  • 2Three-phase supply is commonly needed for GSHPs above 10kW. A DNO application for a three-phase supply upgrade can take 8 to 16 weeks and should be initiated at the earliest project stage.
  • 3GSHPs require additional electrical circuits for circulation pumps (ground loop and heating circuits), zone valves, buffer tank immersion heaters, and the main compressor unit.
  • 4Ground loop isolation must be considered carefully — the ground loop is in contact with earth, and bonding the heating-system metalwork to the main earthing terminal is essential to prevent touch voltages. BS 7671 Reg 411.3.1.2 requires extraneous-conductive-parts liable to introduce a dangerous potential difference (its examples include central heating systems) to be connected to the MET by protective bonding conductors.
  • 5MCS certification is mandatory for the installer to access the Boiler Upgrade Scheme (BUS) grant, which provides up to £7,500 for ground source heat pump installations.
01 · Renewables

Ground Source Heat Pump Electrical Work: What Electricians Need to Know

Ground source heat pumps (GSHPs) extract heat from the ground via a buried loop of pipe and use a compressor to upgrade that heat to a temperature suitable for space heating and hot water. They are the most efficient heat pump type (with a COP of 3.5 to 5.0), but the installation cost is significantly higher than air source due to the ground loop (borehole or trench).

GSHPs are typically installed in larger properties with sufficient land for the ground loop — detached houses, rural properties, and new-build developments. The electrical installation is more complex than air source because of higher power demands, multiple circulation pumps, three-phase supply requirements, and the ground loop isolation considerations.

This guide covers the electrical supply requirements, three-phase considerations, circulation pump and zone valve wiring, buffer tank circuits, ground loop isolation, MCS certification, and the relevant BS 7671 regulations.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Renewables

Power Demands and Supply Requirements

Ground source heat pumps have higher electrical demands than air source units because they are typically sized for larger properties. The electrical load includes:

LoadTypical ratingNotes
Compressor3–8kW inputMain power consumer. Starting current 3–5× running current; soft-start reduces inrush on many units.
Ground-loop circulation pump100–500WPumps the water-glycol mixture through the buried loop. Rating scales with loop length.
Heating circulation pump50–200WDistributes heated water to radiators or underfloor heating.
Immersion heater(s)3kW eachBackup heating in the buffer tank or cylinder. Some systems fit two (upper and lower).
Controller and ancillaries50–100WZone valves, outdoor sensor, room thermostats, and the control panel.

Total electrical demand for a typical domestic GSHP installation is 5 to 12kW. Carry out a thorough maximum demand assessment to determine whether the existing supply can cope.

03 · Renewables

Three-Phase Supply: When and Why

Three-phase supply is commonly needed for ground source heat pump installations. The key triggers for a three-phase upgrade are:

  • GSHP rated above 10kW electrical input — most manufacturers only offer three-phase models at this power level. The compressor motor is three-phase for smoother operation and lower starting currents per phase.
  • Insufficient single-phase supply capacity — if the existing 60A or 80A single-phase supply cannot accommodate the GSHP plus existing loads, a three-phase supply provides 3 times the capacity (3 x 100A is typical).
  • Voltage drop concerns — on long cable runs (common in rural properties where the GSHP plant room may be some distance from the supply intake), three-phase reduces the current per conductor and therefore the voltage drop.
FactorSingle-phaseThree-phase
Typical GSHP sizeUp to ~10kW electrical input12kW and above (common)
Supply capacity60A or 80A — check spare headroom~3× capacity (e.g. 3×100A)
Starting current per phaseHigher — can cause voltage dipsLower — load shared across phases
Long-run voltage dropHigher current per conductorReduced current per conductor
DNO lead timeUsually existing supply8–16 weeks for an upgrade

A three-phase supply upgrade requires a DNO application and typically takes 8 to 16 weeks. The cost is £1,500 to £3,000 depending on the distance from the existing supply point. Apply to the DNO immediately after the site survey — this is usually the critical path item that determines the overall project timeline.

The three-phase consumer unit (or distribution board) must be designed to balance the load across the three phases. The GSHP compressor takes the three-phase supply; single-phase circuits (immersion heaters, circulation pumps, lighting) are distributed across the phases.

04 · Renewables

Circulation Pump Wiring

A GSHP system has at least two circulation pumps — one for the ground loop and one for the heating distribution. Larger systems may have additional pumps for separate heating zones or a dedicated hot water cylinder pump.

  • Ground loop pump — typically powered from the heat pump controller (which manages the pump speed via a 0-10V signal or PWM control). The electrical connection is usually a 3-pin plug or hardwired connection to the controller terminal strip. Rated at 100 to 500W.
  • Heating circuit pump — distributes heated water from the buffer tank to the heating system. May be controlled by the GSHP controller or by a separate heating controller. Typically 50 to 200W, powered from a fused spur or the controller.
  • Wiring — follow the manufacturer wiring diagram for pump connections. Most pumps are 230V single-phase with a standard 3-core flex. Variable speed pumps may require an additional signal cable from the controller. Route pump cables away from power cables to avoid interference with speed control signals.

Cable Segregation: Power vs Signal Cables

A common site mistake is routing 230 V power cables alongside low-voltage signal cables (0–10 V pump speed, PWM control, room thermostat wiring, outdoor sensor). Electromagnetic interference from the power cables can cause erratic pump speeds, false thermostat readings, and nuisance controller faults. BS 7671 Reg 444.4.2 requires segregation, screening, or other mitigation measures where EMI could affect equipment operation. In practice: run power and signal cables in separate conduit or cable trunking, or maintain a minimum 50 mm separation. Where crossing is unavoidable, cross at 90°.

05 · Renewables

Zone Valve and Controller Wiring

The GSHP controller manages heating zones, hot water production, and weather compensation. The electrical wiring for the controller and zone valves follows the same principles as air source heat pump installations, but GSHP systems often have more zones due to the larger property size.

  • Zone valves — 230V motorised valves that control the flow of heated water to different zones (ground floor, first floor, hot water cylinder). Each valve has live, neutral, earth, and a switched live return. Wire to the controller wiring centre per the manufacturer diagram.
  • Room thermostats — one per heating zone, wired or wireless. Wired thermostats use a 2-core cable to the controller. Wireless thermostats need a receiver at the controller, which requires a power supply.
  • Outdoor sensor — mounted on a north-facing wall and wired to the controller for weather compensation. 2-core signal cable, typically up to 50m run.
  • Buffer tank sensors — temperature sensors in the buffer tank wired to the controller. These are low-voltage signal connections.
06 · Renewables

Buffer Tank and Immersion Heater Circuits

A buffer tank is almost always required with a GSHP to prevent compressor short-cycling. The buffer tank stores thermal energy and decouples the heat pump output from the heating demand. Most buffer tanks include one or two immersion heater elements for backup heating.

  • Immersion heater circuits — each 3kW immersion heater requires a dedicated 16A or 20A circuit with 2.5mm cable and a local double-pole switch or FCU. If the buffer tank has two immersion heaters (upper and lower), they may need separate circuits unless interlocked.
  • Hot water cylinder — if the system uses a separate hot water cylinder (in addition to the buffer tank), it may also have its own immersion heater requiring a dedicated circuit.
  • Control — immersion heaters are typically controlled by the GSHP controller (energised only when the heat pump cannot maintain the required temperature). The controller activates the immersion heater circuit via a relay or contactor.

Typical GSHP circuit schedule (indicative)

Indicative only — always size every circuit to the manufacturer data and confirm with a cable sizing calculation against your install method, grouping, and run length.

CircuitSupplyProtectionIsolation
Compressor1-ph or 3-ph per modelSized to manufacturer FLC/MCALocal isolator at the unit
Immersion heater (3kW)230V single-phase16A or 20A, ~2.5mm² cableDouble-pole switch / FCU
Circulation pumps230V single-phaseOften fed from controllerFused spur / controller isolation
Controller / ancillaries230V single-phaseSwitched fused connection unitLocal FCU

Try Elec-Mate free for 7 days

16 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.

Start free trial
Download on the App StoreGet it on Google Play
07 · Renewables

Ground Loop Isolation Considerations

The ground loop introduces a unique electrical safety consideration. The loop pipe is buried in direct contact with the earth, and the water-glycol mixture inside the loop is in thermal contact with the ground. While HDPE pipe is non-conductive, the metalwork of the heat pump (heat exchanger, compressor casing, manifold connections) is connected to the fluid circuit.

  • Bonding requirement — Regulation 411.3.1.2 requires extraneous-conductive-parts liable to introduce a dangerous potential difference to be connected to the main earthing terminal (MET) via protective bonding conductors complying with Chapter 54. Where metallic manifolds, buffer vessels or connected heating pipework meet that test, they are bonded; the heat pump casing is assessed individually rather than assumed.
  • Extraneous conductive parts — metallic manifolds, buffer vessels, and pipework connected to the ground loop may be classified as extraneous conductive parts and must be bonded to the MET. Assess each installation individually.
  • TT earthing systems — in rural properties with TT earthing (common for properties that need GSHPs), the earth fault loop impedance may be higher. Verify that the protective devices will disconnect within the required time. RCD protection is essential.
08 · Renewables

MCS Certification for Ground Source Heat Pumps

As with air source heat pumps, MCS certification is mandatory for the lead installer to access the Boiler Upgrade Scheme (BUS) grant. The grant provides up to £7,500 towards the cost of a GSHP installation.

  • MCS for GSHP — the MCS standard for ground source heat pumps is MIS 3005. It covers system design (including ground loop sizing), installation, commissioning, and handover. The MCS installer is responsible for the overall system design and performance.
  • Electrical subcontractor — electricians working as subcontractors to an MCS-certified installer do not need their own MCS certification for the electrical work. However, the electrical work must comply with BS 7671 and be covered by an EIC. The EIC is part of the MCS documentation package.
09 · Renewables

Regulations and Standards

The electrical installation must comply with BS 7671:2018+A4:2026. The same regulations that apply to air source heat pumps also apply to ground source, with additional considerations for the ground loop:

  • Regulation 411.3.1.2 — extraneous-conductive-parts liable to introduce a dangerous potential difference shall be connected to the main earthing terminal by protective bonding conductors complying with Chapter 54. The regulation's listed examples include central heating systems and other metallic installation pipework, which captures the heating side of a GSHP where those parts are extraneous-conductive-parts.
  • Regulation 411.3.2.2 — sets that the maximum disconnection times in Table 41.1 apply to final circuits rated up to 63 A with one or more socket-outlets, and up to 32 A supplying only fixed connected current-using equipment. Compressor circuits above 32 A are assessed against the TN-system requirements of Regulation 411.4.
  • Regulation 462.2 — every circuit shall be provided with a means of isolation for all live conductors (except as detailed in Reg 461.2). The GSHP compressor circuit, immersion heater circuits, and circulation pump circuits each benefit from a local means of isolation to permit safe servicing without de-energising unrelated circuits.
  • Regulation 421.1.7 — recommends arc fault detection devices (AFDDs) on AC final circuits. Where a GSHP supply upgrade triggers new circuits or rewires in domestic premises, AFDD installation is recommended on those circuits.
  • Regulation 411.3.4 (A4:2026) — within domestic (household) premises, AC final circuits supplying luminaires shall have additional protection by a 30 mA RCD. Where new lighting circuits are added as part of a GSHP supply upgrade, this requirement applies.

BS 7671:2018+A4:2026 Updates Relevant to GSHP Installations

  • AFDD — Reg 421.1.7: Where a GSHP supply upgrade involves adding new circuits or rewiring in domestic premises, arc fault detection devices (AFDDs) are recommended on those AC final circuits. GSHP control electronics are sensitive to supply-side arc faults; AFDDs provide an additional layer of protection.
  • 30 mA RCD on lighting — Reg 411.3.4: New domestic lighting circuits added as part of a GSHP supply upgrade shall have additional protection by a 30 mA RCD. This A4:2026 addition is mandatory for new circuits in household premises.
  • SPDs for GSHP control electronics: GSHP controllers, inverter drives, and outdoor sensors are sensitive to transient overvoltages. Where the risk assessment indicates exposure (Reg 443.4), surge protective devices (SPDs) should be installed at the distribution board supplying the GSHP to protect sensitive control electronics.

The work is notifiable under Part P of the Building Regulations. Notify through your competent person scheme or via Building Control.

10 · Renewables

For Electricians: The GSHP Opportunity

Ground source heat pump installations are high-value projects. The electrical package alone is typically worth £1,000 to £2,500, and the overall project values are £20,000 to £35,000. Building relationships with MCS-certified GSHP installers provides a steady stream of well-paid work.

Indicative electrical cost breakdown

Indicative UK market guidance, not a quote — actual prices vary by region, access, and supply distance.

ItemIndicative range
GSHP electrical package (circuits, pumps, controller)£1,000–£2,500
Three-phase supply upgrade (DNO + board)£1,500–£3,000
Whole GSHP project (loop, pump, distribution)£20,000–£35,000
Boiler Upgrade Scheme (BUS) grantup to £7,500 off

Cable Sizing Calculator

Size the compressor circuit, circulation pump circuits, and immersion heater circuits with the cable sizing calculator. Three-phase calculations included.

Quoting App

Price GSHP electrical work with Elec-Mate's quoting app. Compressor circuit, three-phase supply, circulation pumps, zone valves, immersion heaters — all itemised.

EIC Certificate on Your Phone

Complete the EIC for GSHP circuits on site. AI board scanning, voice test entry, and instant PDF export for the MCS documentation package.

Verification Checklist for GSHP Circuits

  • Zs verification — GN3 0.8 factor: On long compressor cable runs (plant room to supply intake), apply the GN3 Appendix 3 acceptance criterion: measured Zs shall not exceed 0.8 × the tabulated maximum for the protective device type and rating. This accounts for conductor temperature at full load.
  • Insulation resistance: Carry out IR testing (500 V d.c.) on all GSHP circuits before energising. Disconnect the GSHP controller and electronic components — these are not rated for 500 V test voltage. Test each circuit with associated equipment disconnected; minimum 1 MΩ per Reg 643.3.
  • RCD trip time: Verify that any 30 mA RCDs protecting GSHP-related circuits operate effectively (Reg 643.8). Under BS 7671:2018+A4:2026 the historic Appendix 3 Table 3A and the 5 × IΔn / 40 ms test have been withdrawn: a single a.c. test at the rated residual operating current (1 × IΔn) now applies, and a general non-delay RCD must disconnect within 300 ms. Record results on the Schedule of Test Results.

Quote, install, and certify GSHP electrical work

Join 1,000+ UK electricians using Elec-Mate for cable sizing, professional quoting, and on-site EIC certification.

Try it free for 7 days
Download on the App StoreGet it on Google Play

Frequently Asked Questions About GSHP Electrical Installation

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-Day Free Trial — Cancel Anytime, No Hassle

Size Cables and Certify GSHP Installations on Your Phone

Join 1,000+ UK electricians using Elec-Mate for cable sizing, professional quoting, and on-site EIC certificates for ground source heat pump installations. 7-day free trial, cancel anytime.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical

From £6.99/mo after trial — less than a coffee a week

or download the app
Download on the App StoreGet it on Google Play
7 days free, then from £6.99/moCancel in one tap — no calls, no hassleiOS, Android & WebBS 7671 compliant
16
Certificate Types
70+
Calculators
46+
Training Courses
8
AI Agents

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy