REGULATION DEEP-DIVE

Regulation 314: Division of Installation Into Circuits

Every installation must be divided into circuits to avoid danger and minimise inconvenience. This guide covers the regulatory requirements, ring vs radial decisions, circuit separation, maximum demand, and practical circuit schedules for domestic and commercial installations.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

17 min readUpdated 2026-08-07Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

The short answer

What does Regulation 314 of BS 7671 require?

Regulation 314 requires every installation to be divided into circuits. Regulation 314.1 lists six objectives (a–f): avoid danger and inconvenience, allow safe testing and maintenance, limit the effect of a single circuit failing, reduce unwanted RCD tripping, mitigate electromagnetic disturbance, and prevent indirect energising. Regulations 314.2 to 314.4 then require separate circuits for parts needing separate control, set the number of circuits and points, and keep each final circuit electrically separate.

Section 314 is headed "Division of installation" and sits in Chapter 31 of Part 3 (Assessment of General Characteristics) of BS 7671:2018+A4:2026.

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5

Key takeaways

  1. 01Regulation 314.1 requires that every installation shall be divided into circuits, as necessary, to avoid danger and minimise inconvenience in the event of a fault. This is not a suggestion — it is a mandatory design requirement listing six specific objectives, items (a) to (f).
  2. 02Regulation 314.2 requires that separate circuits are provided for parts of the installation that need to be separately controlled, in such a way that those circuits are not affected by the failure of other circuits, with due account taken of the consequences of the operation of any single protective device.
  3. 03Regulation 314.3 sets the number of final circuits and the number of points per final circuit, such that compliance with Chapter 43 (overcurrent), Chapter 46 and Section 537 (isolation and switching) and Chapter 52 (current-carrying capacity) is facilitated.
  4. 04Regulation 314.4 is the one that answers "how do I prevent indirect energising?" — where an installation comprises more than one final circuit, each final circuit shall be connected to a separate way in a distribution board, and the wiring of each final circuit shall be electrically separate from that of every other final circuit. No borrowed neutrals, no shared cables.
  5. 05Ring final circuits for BS 1363 accessories are covered by Regulation 433.1.204: a 30 A or 32 A protective device, copper line and neutral conductors of at least 2.5 mm² (1.5 mm² for two-core mineral insulated cable to BS EN 60702-1), and a cable current-carrying capacity of not less than 20 A. Appendix 15 is the informative guidance that supports it.
  6. 06Regulation 314.1(c) requires the design to take account of hazards that may arise from the failure of a single circuit, such as a lighting circuit — the basis for keeping lighting on a separate protective device from the socket-outlet circuits, so that a trip on a socket circuit does not leave the occupants in darkness.

01 · Regulation Deep-Dive

Division of Installation Into Circuits

Section 314 of BS 7671:2018+A4:2026 is printed under the heading Division of installation. It sits in Chapter 31, Part 3 (Assessment of General Characteristics), and runs to four regulations. Each one does a different job:

RegulationWhat it requires
314.1Every installation shall be divided into circuits, as necessary, to achieve six objectives, items (a) to (f).
314.2Separate circuits for parts of the installation that need to be separately controlled, unaffected by the failure of other circuits.
314.3The number of final circuits, and points per circuit, shall facilitate compliance with Chapter 43, Chapter 46, Section 537 and Chapter 52.
314.4Each final circuit connected to a separate way in a distribution board, and wired electrically separately from every other final circuit.

To prevent indirect energising of a circuit, what must be done?

Regulation 314.1(f) sets the objective — prevent the indirect energising of a circuit intended to be isolated — and Regulation 314.4 says what must actually be done about it. Where an installation comprises more than one final circuit, each final circuit shall be connected to a separate way in a distribution board, and the wiring of each final circuit shall be electrically separate from that of every other final circuit. On site that means no borrowed neutrals, no two circuits sharing a cable, and no arrangement in which isolating one way at the board leaves conductors in that circuit live from another way.

Circuit division is not just about calculating cable sizes and protective device ratings. It is about designing an installation that limits the consequences of a fault, allows safe maintenance, provides operational flexibility, and minimises nuisance tripping. A well-designed circuit arrangement means a fault on one circuit does not plunge the house into darkness, does not disable the fire alarm, and does not defrost the freezer.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Regulation Deep-Dive

Regulation 314.1 — Every Installation Shall Be Divided

Regulation 314.1 is clear: every installation shall be divided into circuits, as necessary, to achieve six objectives. The regulation lists them as items (a) to (f), and a compliant design must satisfy each one that is relevant to the installation:

  • (a)Avoid danger and minimise inconvenience in the event of a fault. A single circuit feeding the whole installation is not acceptable — a fault must not be allowed to disable everything at once.
  • (b)Facilitate safe inspection, testing and maintenance (see also Chapter 46 and Section 537). Dividing the installation lets individual circuits be isolated for safe working without shutting down the whole property.
  • (c)Take account of hazards arising from the failure of a single circuit such as a lighting circuit. This is the regulatory basis for keeping lighting separate from sockets and for dedicating critical circuits (fire alarm, emergency lighting).
  • (d)Reduce the possibility of unwanted tripping of RCDs due to excessive protective conductor (PE) currents not due to a fault. This drives the choice between split-load RCD boards and individual RCBO boards.
  • (e)Mitigate the effects of electromagnetic disturbances (see also Chapter 44). Circuits supplying sensitive equipment (data and communications) are kept apart from circuits supplying disturbance sources (motors, welders).
  • (f)Prevent the indirect energising of a circuit intended to be isolated — supported by Regulation 314.4, which requires each final circuit to be wired electrically separately from every other final circuit.

03 · Regulation Deep-Dive

Regulations 314.2, 314.3 and 314.4 — Separation and Numbers

The remaining regulations in Section 314 turn the broad objectives of 314.1 into concrete design rules. It is worth getting the numbering right, because each one means something different — here they are in full:

  • 314.2Separate circuits shall be provided for parts of the installation that need to be separately controlled, in such a way that those circuits are not affected by the failure of other circuits, and due account shall be taken of the consequences of the operation of any single protective device.
  • 314.3The number of final circuits required, and the number of points supplied by any final circuit, shall be such as to facilitate compliance with Chapter 43 (overcurrent protection), Chapter 46 and Section 537 (isolation and switching) and Chapter 52 (current-carrying capacities of conductors).
  • 314.4Where an installation comprises more than one final circuit, each final circuit shall be connected to a separate way in a distribution board, and the wiring of each final circuit shall be electrically separate from that of every other final circuit, so as to prevent the indirect energising of a final circuit intended to be isolated.

Which loads get their own circuit, and on whose authority

Section 314 is a set of objectives, not a shopping list of circuits, so it is worth being precise about where each everyday separation rule actually comes from:

  • Safety services — the one hard requirement. Regulation 560.7.1 states that, except where the recommendations of other safety standards apply, circuits of safety services shall be independent of other circuits. Its note explains why: an electrical fault, intervention or modification in one system must not affect the correct functioning of the other. Fire alarm and emergency lighting circuits get their own way at the board, and 560.7.2 keeps them out of locations exposed to fire risk (BE2) except as that regulation permits.
  • Lighting and power — not a prohibition, an objective. Regulation 314.1(c) requires the design to take account of hazards arising from the failure of a single circuit, such as a lighting circuit, and 314.2 requires separate circuits for parts that need separate control. Put together, a design that leaves occupants in the dark when a socket circuit trips does not meet 314.1(c). Separate protective devices for lighting and sockets are how competent designers discharge that duty.
  • Cookers, ovens and hobs above 2 kW — Appendix 15 advises connecting them on their own dedicated radial circuit, and advises against supplying immersion heaters or comprehensive electric space heating from a ring final circuit. That is informative guidance supporting Regulation 433.1.204, but it is the reason those loads come off the ring.
  • Showers, EV chargers and other high-current loads — no regulation names them individually. They end up on dedicated circuits because 433.1.1 (Ib ≤ In ≤ Iz) and the voltage drop and Zs limits cannot be met any other way once the load is added to a shared circuit.

Section 314 does not prescribe exactly how to divide circuits — it sets the objectives and leaves the specific design to the competent electrician. That is a feature, not a gap: it is also why an inspector can record a division of circuits as unsatisfactory without pointing at a numeric limit.

04 · Regulation Deep-Dive

Maximum Demand Per Circuit

Each circuit must be designed to carry the maximum demand of the connected load. The protective device rating and cable size are selected from the design current (Ib) of the circuit, and Regulation 433.1.1 sets the coordination that follows: Ib ≤ In ≤ Iz.

Typical domestic circuit design currents

CircuitDesign currentDeviceCable
Ring final circuit (sockets)Varies — diversity applies32 A2.5 mm²
Radial (sockets)Up to 20 A20 A2.5 mm²
LightingUp to 6 A6 A1.5 mm²
Cooker, 12 kW≈ 28 A after diversity (52 A connected)32 A6 mm²
Electric shower, 9.5 kW≈ 41 A45 A10 mm²
Immersion heater, 3 kW≈ 13 A16 A2.5 mm²
EV charger, 7.4 kW≈ 32 A32 A6 mm²

Currents are at 230 V. Cable sizes are the usual starting point, not an answer — the current-carrying capacity that matters is the tabulated Iz for the actual reference method, after the rating factors for ambient temperature, grouping and thermal insulation. Verify every circuit with the cable sizing calculator using the real installation method, run length and rating factors.

Diversity applies to circuits too, not just to the main supply

A common misreading is that diversity belongs only at the origin. Regulation 311.1 says otherwise: in determining the maximum demand of an installation or part thereof, diversity may be taken into account — and Part 2 defines diversity in the same terms, as a means of determining maximum demand for an installation or part thereof, taking account of usage patterns. The cooker row above is exactly that. The On-Site Guide method takes the first 10 A of the appliance's rated current in full, adds 30% of the remainder, and adds a further 5 A if a socket-outlet is incorporated in the control unit. A 12 kW cooker draws roughly 52 A connected, which becomes about 28 A of design current — which is why a 32 A device is normal on a 12 kW cooker and a 52 A one is not.

Diversity is a design allowance, not a get-out. Once assessed, the circuit must still satisfy Ib ≤ In ≤ Iz, the voltage drop limit and the Zs limit for its disconnection time. For the dedicated high-demand circuits, see the sizing guides for the cooker circuit, the electric shower and the EV charger.

05 · Regulation Deep-Dive

Ring vs Radial Circuits: When to Use Each

The choice between ring and radial circuits is one of the most common design decisions for UK electricians. Both are equally compliant with BS 7671 — the choice depends on the application, cable routing, and floor area.

Ring final circuitRadial circuit
ArrangementStarts and finishes at the distribution board, both ends of line, neutral and cpc on the same terminalsStarts at the distribution board and terminates at the last point — no return leg
Protective device30 A or 32 A, to BS 88 series, BS 3036, BS EN 60898, BS EN 60947-2 or BS EN 61009-1 (Reg 433.1.204)Matched to the load — 20 A for a general socket radial, or sized to the appliance
Minimum conductor2.5 mm² copper line and neutral; 1.5 mm² for two-core mineral insulated cable to BS EN 60702-1. Iz not less than 20 ASized for the design current, route length and Zs
Floor area servedHistorically 100 m² (Appendix 15)Historically 50 m² for a 20 A circuit in 2.5 mm² (Appendix 15, Figure 15B)
Why choose itTwo parallel legs, so lower R1+R2, lower Zs and lower volt drop over the same routeSimpler routing, no ring continuity to prove, and the only sensible arrangement for a single fixed load
Use whenMultiple general-purpose socket outlets spread across an area, and the cable can be run as a continuous ringA dedicated load, a small area, or a route where a ring is impractical

Spurs: what Appendix 15 actually says

Spurs are the part of Appendix 15 that gets misquoted most. An unfused spur run in 2.5 mm² cable should feed one single or one twin socket-outlet only, and may be connected at the origin of the circuit in the distribution board as well as out on the ring. Where the connection is made in a junction box, the box should be to BS EN 60670-22 and — if it has screw terminals — it must remain accessible for inspection, testing and maintenance under Regulation 526.3, or use maintenance-free terminals instead.

If several extra socket outlets are needed, either extend the ring itself or fit a fused connection unit to BS 1363-4 with a maximum 13 A fuse. The number of socket outlets a fused spur can supply is not fixed by a rule: Appendix 15 makes it dependent on the load characteristics, having taken diversity into account.

In the app

Try Elec-Mate free for 7 days

16 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.

06 · Regulation Deep-Dive

Circuit Separation Requirements

Beyond ring vs radial, the design has to decide which loads go on which circuits. These are the conventions that discharge the 314.1 objectives in a normal dwelling.

  • Lighting — kept off the socket-outlet circuits, and split into at least two circuits in a dwelling (upstairs and downstairs, or front and back), so that one fault cannot darken the whole property. Typically a 6 A device on 1.5 mm². The driver is 314.1(c), not a numbered prohibition.
  • Socket outlets — at least two general circuits, arranged so a trip on one does not remove all socket power. Upstairs and downstairs, or kitchen and utility on one and living areas on the other.
  • Dedicated circuits — cooker, electric shower, immersion heater, EV charger and heat pump. Appendix 15 specifically puts cookers, ovens and hobs above 2 kW on their own radial and keeps immersion heaters and comprehensive electric space heating off the ring.
  • Safety services — fire alarm and emergency lighting circuits are independent of other circuits under Regulation 560.7.1, and under 560.7.2 must not pass through locations exposed to fire risk (BE2) except as that regulation permits.
  • Outdoor circuits — outdoor socket outlets, garden lighting and outbuilding supplies on their own circuits. Weather-exposed faults and higher standing leakage are exactly the accumulation that Regulation 531.3.2 asks you to keep off a shared RCD.

Circuit division and RCD selection are the same decision

Regulation 531.3.2 requires RCDs to be selected and erected so as to limit the risk of unwanted tripping, and lists what must be considered: subdivision of circuits with individual associated RCDs, the use of RCBOs for individual final circuits in residential premises, and a hard ceiling — the accumulation of protective conductor currents and earth leakage currents downstream of the RCD shall be not more than 30% of the rated residual operating current. On a 30 mA device that is 9 mA across everything downstream. Both of the first two indents cross-refer back to Section 314, which is why the circuit schedule and the board layout have to be designed together.

Type matters as much as count. Regulation 531.3.3 restricts RCD Type AC to fixed equipment where it is known that the load current contains no DC components — the examples given are electric heating appliances and simple filament lighting with no electronic components. A modern dwelling has almost nothing that qualifies, so Type A is the working minimum, with Type F where a frequency-inverter appliance sits on a line-to-neutral circuit and Type B where smooth DC residual current is possible.

07 · Regulation Deep-Dive

Practical Design Approach: Domestic Installations

Here is a practical circuit design for a typical 3-bedroom semi-detached house. This is a starting point — adjust based on the specific property, customer requirements, and installed equipment.

Typical domestic circuit schedule

CircuitTypeProtectionCable
Downstairs socketsRing32 A RCBO Type A2.5 mm²
Upstairs socketsRing32 A RCBO Type A2.5 mm²
Kitchen socketsRing32 A RCBO Type A2.5 mm²
Downstairs lightingRadial6 A RCBO Type A1.5 mm²
Upstairs lightingRadial6 A RCBO Type A1.5 mm²
CookerRadial32 A RCBO Type A6 mm²
Electric showerRadial45 A RCBO Type A10 mm²
Immersion heaterRadial16 A RCBO Type A2.5 mm²
Smoke and fire alarmRadial6 A MCB Type B1.5 mm²
Outdoor socketRadial20 A RCBO Type A2.5 mm²

Ten circuits, ten ways, and every one of them individually isolatable \u2014 which is what Regulation 314.4 is asking for. Add dedicated ways for an EV charger, heat pump or other high-demand equipment, and leave spare ways for future additions. The fire alarm circuit is shown on its own way because Regulation 560.7.1 requires circuits of safety services to be independent of other circuits.

In the app

Design circuit schedules with AI assistance

Elec-Mate's AI circuit designer generates circuit schedules based on property type, room layout, and equipment.

08 · Regulation Deep-Dive

Practical Design Approach: Commercial Installations

Commercial installations follow the same principles as domestic but with additional considerations for three-phase supplies, larger load diversity, and more complex circuit arrangements.

  • Phase balancing — in three-phase installations, circuits are distributed across the three phases to balance the load. Unbalanced loads cause excessive neutral current and voltage imbalance, so allocate single-phase circuits approximately equally across L1, L2 and L3.
  • Sub-distribution — large commercial installations use sub-distribution boards to reduce cable lengths and improve discrimination. The main board supplies sub-boards via sub-mains, and the sub-boards supply final circuits. Each sub-board serves a defined area or function.
  • Essential and non-essential loads — essential loads (servers, fire alarms, emergency lighting, security) are separated from non-essential loads (general lighting, socket outlets, HVAC). Essential loads may be supplied from a UPS or generator, requiring separate distribution, and safety services carry the independence requirement of Regulation 560.7.1 in their own right.
  • Mechanical plant circuits — HVAC equipment, lifts and other mechanical plant take dedicated circuits. Type C or D devices are common because the inrush of an inductive load will trip a Type B on a healthy circuit.

The design process for a commercial installation typically starts with a load schedule (every item of equipment and its power demand), followed by a diversity assessment, then circuit allocation (deciding which loads go on which circuits), and finally cable sizing and protective device selection for each circuit. BS 7671 permits the diversity step at Regulation 311.1 and defines the term in Part 2, but the worked allowance tables are in the IET On-Site Guide (Appendix A, Table A2) — which itself cautions that the values are guidance only, are not recently updated, and that appropriate allowances call for special knowledge and experience. Current-carrying capacity and voltage drop figures for the final step come from BS 7671 Appendix 4. The cable sizing calculator handles the cable sizing and protective device verification for each individual circuit.

Frequently Asked Questions About Circuit Division and Design

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-day free trial

Design Circuit Schedules and Size Cables on Your Phone

Join 1,000+ UK electricians using Elec-Mate for AI-assisted circuit design, cable sizing, and on-site EIC certificates with professional schedules. 7-day free trial, cancel anytime.

Start your free trial

From £6.99/mo after the trial — no charge until day 8.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5
  • 7 days free, then from £6.99/mo
  • Cancel in one tap — no calls, no hassle
  • iOS, Android and web
  • Built to BS 7671:2018+A4:2026

Or download the app

Download on the App StoreGet it on Google Play
Certificate types
16Certificate types
Calculators
70+Calculators
Training courses
46+Training courses
AI specialists
8AI specialists

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy