PLUG-IN SOLAR

Plug-in Solar and Your DNO: The 28-Day G98 Rule

Telling your distribution network operator about a plug-in solar device is mandatory — but it is connect and notify, not prior approval. You install and commission first, then notify within 28 days using G98 Form B. This page covers how, who to, and the disconnection duty almost nobody knows about.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,600+ UK electricians

7 min readUpdated 2026-09-01Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

The short answer

Do I need to tell my DNO about plug-in solar?

Yes, and it is mandatory — but it is connect and notify, not prior approval. You install and commission the device first, then notify your distribution network operator within 28 days of commissioning using the Installation Document at Form B, Appendix 3 of EREC G98. The operator cannot refuse it.

The 28-day deadline comes from G98, not from the product specification — which makes notification mandatory but sets no time limit. The same obligation applies when you remove the device.

1,600+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5

Key takeaways

  1. 01Notifying your distribution network operator is mandatory. It is not optional and it is not a formality you can skip.
  2. 02It is connect and notify, not prior approval — the device is installed and commissioned first, and the notification follows. It does not hold anything up and the operator cannot refuse.
  3. 03G98 gives 28 days from commissioning, discharged by the Installation Document at Form B, Appendix 3 of EREC G98.
  4. 04The 28-day figure comes from G98, not from the product specification. The specification makes notification mandatory but sets no deadline of its own — the word "days" does not appear in it.
  5. 05The obligation runs both ways: you must also notify when the device is disconnected or removed. Almost nobody does this.
  6. 06The product itself must be marked with a statement that notification of connection and disconnection is mandatory, and the documentation must include a QR code to the registration process.
  7. 07G98 applies to Great Britain. Northern Ireland connects under G98/NI, and the specification records that its application there is subject to further consideration.

01 · Plug-in Solar

The Short Answer

Yes, you must tell them. No, you do not need their permission.

Notification to your distribution network operator is mandatory for plug-in solar — the product itself has to be permanently marked with a statement saying so, including a link to instructions. But it operates on a connect and notify basis: the device is installed and commissioned first and the notification follows within 28 days. It does not hold anything up, and the operator cannot refuse.

The part almost nobody knows: the same obligation runs in reverse. When the device is removed, the operator should be told that too.

Free download

Plug-in Solar — What Actually Changed. Free 8-page guide

The limits, the prohibitions, the RCD question answered from the source, where the notification duty actually comes from, and what the box is legally required to tell your customer.

  • Which document each rule actually comes from
  • Recommended vs required, cited to the source
  • Free PDF — print it, share it, pin it up

We'll email it once. No spam — unsubscribe any time.

02 · Plug-in Solar

Connect and Notify, Not Prior Approval

Engineering Recommendation G98 covers the connection of fully type tested micro-generators in parallel with the public low voltage network. The words “fully type tested” are doing the work: the device has already been tested against the network’s requirements before it was ever sold, which is why the operator needs a record of it rather than an opportunity to assess it.

That is why the specification requires manufacturers to have devices type tested to G98 requirements and registered on the ENA Type Test Register, and to obtain confirmation that the device has been assessed and identified as compliant, before placing it on the market. The assessment happens once, to the product — not every time somebody plugs one in.

So there is no application, no waiting, and no decision to be appealed. Install it, commission it, then tell them.

03 · Plug-in Solar

Where the 28 Days Actually Comes From

Worth being precise, because this gets misattributed constantly — including, briefly, by us.

The Interim Product Specification (§8.2.3.1) requires the product to state that notification about connection and disconnection is mandatory, and requires the documentation to explain how. It sets no deadline at all — the word “days” does not appear anywhere in it.

The 28 days is a G98 requirement. Notification is made using the Installation Document at Form B, Appendix 3 of EREC G98, within 28 days of commissioning, and that is what the network operators themselves publish.

If you are citing this in writing — on a certificate, in a handover pack, in a letter to a managing agent — cite G98 for the clock and the specification only for the duty. Anyone who quotes the specification for the 28 days has not read it.

04 · Plug-in Solar

How to Notify, and Who To

Your distribution network operator is not your electricity supplier. It is the company that owns and maintains the cables in your street, and it is determined by geography rather than by who you pay. If you do not know which one covers you, the Energy Networks Association publishes a postcode lookup.

Most operators provide an online form. In broad terms you will need the address and MPAN, your contact details, the manufacturer and model of the device, its declared output, and the commissioning date. Because compliant devices are on the ENA Connect Direct register, the device details can usually be picked from a list rather than typed.

It typically takes ten to fifteen minutes and gives you an instant acknowledgement. Keep that acknowledgement — it is the only evidence you have that the obligation was met, and it is the sort of thing a purchaser’s solicitor or a managing agent may eventually ask for.

The documentation supplied with the device must include a QR code directing you to the relevant guidance and registration process, so the easiest route is usually the one printed in the manual.

In the app

Try Elec-Mate free for 7 days

19 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.

05 · Plug-in Solar

Telling Them When You Remove It

This is the genuinely overlooked half. The specification requires the product to be marked with a statement that notification about connection and disconnection is mandatory, and requires the documentation to set out current registration and deregistration obligations.

Plug-in solar is designed to be removable — the mounting must be reversible and non-permanent — so devices will be taken down and taken to new addresses far more often than rooftop systems ever are. Each of those moves is a disconnection at one address and a connection at another, and both are notifiable.

If you are handing a property over, or a tenant is leaving with a device they installed, that is the moment to deal with it. Nobody else will.

06 · Plug-in Solar

Northern Ireland

G98 applies to Great Britain only. Northern Ireland connects under G98/NI, and the interim product specification records in a footnote that its application to Northern Ireland is subject to further consideration.

If you are in Northern Ireland, treat everything on this page as indicative and check the current position with NIE Networks before relying on it.

07 · Plug-in Solar

Who Actually Does It

The duty sits with the person installing and operating the device, which for plug-in solar is normally the householder — that is the whole design of the route. In a rented property it is the occupier, not the landlord, though a landlord granting permission would be sensible to make it a written condition.

For an electrician, this is a small thing worth offering. Most customers have no idea the obligation exists, it takes a quarter of an hour, and doing it on their behalf as part of the visit is the kind of detail that gets you recommended. If you are already recording a commissioning date, the 28-day clock runs from it.

The wider rules and limits are on the plug-in solar hub page.

Plug-in Solar DNO Notification — Frequently Asked Questions

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-day free trial

Never Miss the Notification Deadline

Elec-Mate's Plug-in Solar Suitability & Commissioning Certificate records the commissioning date and runs the 28-day G98 clock from it, alongside the assessment, the remedial list and the handover record. Join 1,600+ UK electricians. 7-day free trial.

Start your free trial

From £6.99/mo after the trial — no charge until day 8.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5
  • 7 days free, then from £6.99/mo
  • Cancel in one tap — no calls, no hassle
  • iOS, Android and web
  • Built to BS 7671:2018+A4:2026

Or download the app

Download on the App StoreGet it on Google Play
Certificate types
19Certificate types
Calculators
70+Calculators
Training courses
46+Training courses
AI specialists
8AI specialists

1,600+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy