EV CHARGING GUIDE

IET Code of Practice for EV Charging: The Complete Guide for UK Electricians

Everything you need to know about the IET Code of Practice for Electric Vehicle Charging Equipment Installation. Load assessment, earthing (PME and TT), O-PEN protection, cable sizing, smart charging regulations, OCPP, and documentation requirements.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

14 min readUpdated 2026-06-10Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

What is the IET Code of Practice for EV charging?

The IET Code of Practice for Electric Vehicle Charging Equipment Installation is the UK industry-standard guidance for installing EV charge points. It sits alongside BS 7671 Section 722 and covers supply arrangements, earthing — especially the PME (broken-PEN) risk — load and demand management, RCD selection with DC fault detection, and installation, testing and handover. It is the reference most schemes and manufacturers expect installers to follow.

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer — DP Electrical

Key Takeaways

  • 1The IET Code of Practice for Electric Vehicle Charging Equipment Installation (5th Edition, 2023) is the primary technical reference for EV charger installations in the UK, supplementing BS 7671.
  • 2PME earthing is not permitted for EV charging where the user is outdoors unless additional protective measures (such as O-PEN detection) are installed to disconnect the supply if the PEN conductor is lost.
  • 3Load assessment must consider diversity — not all chargers will operate at full power simultaneously. The CoP provides diversity factors for multiple charger installations.
  • 4Smart charging is now mandatory for private EV chargepoints installed from 30 June 2022 under the Electric Vehicles (Smart Charge Points) Regulations 2021.
  • 5Elec-Mate generates compliant EV charger certificates, calculates cable sizing with voltage drop verification, and includes the specific EV installation checklist from the IET CoP.
  • 6Typical UK install price (2026): £720–£1,875 per job depending on region — £1,035 average in the North West / Yorkshire, £1,093 in the West Midlands, £1,208 in Scotland, £1,438 in London. O-PEN protection, cable run length, and consumer-unit upgrades drive variation.
01 · EV Charging Guide

What Is the IET Code of Practice for EV Charging?

The IET Code of Practice for Electric Vehicle Charging Equipment Installation is a technical guidance document that supplements BS 7671:2018+A4:2026 with specific requirements for the design, installation, verification, and maintenance of EV charging equipment. The current edition is the 5th Edition, published in 2023.

The Code of Practice (CoP) exists because EV charging installations present unique technical challenges that are not fully addressed by BS 7671 alone. These include outdoor earthing risks on PME supplies, the need for load management on multiple charger installations, DC fault current protection, communication protocols, and the interaction between the vehicle, charger, and electrical installation.

While the CoP is not a British Standard and compliance is not a strict legal requirement, it is the accepted industry standard. All major competent person schemes (NICEIC, NAPIT, ELECSA) expect EV charger installations to follow the CoP. Building control bodies and OZEV (the Office for Zero Emission Vehicles, formerly OLEV) grant funding applications reference the CoP as the baseline technical standard. An electrician who installs an EV charger without following the CoP is leaving themselves exposed to liability if something goes wrong.

The CoP covers all types of EV charging: domestic single chargepoints, workplace charging with multiple units, public charging infrastructure, fleet depot installations, and rapid DC charging. It addresses both Mode 3 (AC charging via a dedicated chargepoint) and Mode 4 (DC rapid charging) installations.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · EV Charging Guide

Load Assessment for EV Charging Installations

Before installing any EV charger, a thorough load assessment of the existing electrical installation is essential. The purpose is to determine whether the existing supply has sufficient capacity to support the additional load of the EV charger without exceeding the main fuse or supply capacity.

A domestic 7 kW charger draws 32 A — which is a significant addition to a typical domestic supply protected by a 60 A or 80 A main fuse. If the existing maximum demand (including the cooker, shower, heating, and other large loads) is already close to the main fuse rating, adding a 32 A EV charger could cause the main fuse to blow during periods of high demand.

Load Assessment Checklist

  • Check the main fuse or service cut-out rating — typically 60 A, 80 A, or 100 A for domestic supplies. If the main fuse is 60 A and the existing maximum demand is 40 A, there is only 20 A of headroom — not enough for a 32 A charger at full power.
  • Calculate existing maximum demand — use the maximum demand calculator with diversity applied per BS 7671 Appendix 1.
  • Consider load management / curtailment — BS 7671:2018+A4:2026 Reg 722.311.201 explicitly permits load curtailment (automatic or manual load reduction or disconnection) to be taken into account when determining the maximum demand of an EV installation. A dynamic load management system that reduces charger output when other loads are running can therefore be used to justify a smaller supply or avoid a DNO upgrade. Many smart chargers support this via CT clamp monitoring on the main incoming supply.
  • Apply diversity for multiple chargers — the IET CoP provides diversity factors for installations with more than one charger. Not all chargers will operate at full power simultaneously. Typical diversity allows 1.0 for the first charger, 0.8 for the second, and reducing further for additional units.

If the existing supply cannot support the EV charger even with load management, the options are: request a supply upgrade from the DNO (which can take weeks and cost thousands), install a lower-power charger (for example, 3.6 kW at 16 A instead of 7 kW at 32 A), or install a dedicated three-phase supply if one is available.

03 · EV Charging Guide

Earthing Arrangements: PME, TT, and O-PEN Protection

Earthing is the most technically critical aspect of EV charger installation. The IET CoP dedicates significant attention to this topic because of the specific risks associated with outdoor charging on PME (TN-C-S) supplies.

The fundamental problem: in a PME system, the earth and neutral are combined in the supply cable (the PEN conductor). If this PEN conductor breaks between the DNO transformer and the property, all metalwork connected to the PME earth could rise to mains potential relative to true earth. A person standing outdoors on damp ground while touching the vehicle or charger could receive a fatal electric shock.

PME Earthing and EV Charging — Reg 722.312.2.1

BS 7671:2018+A4:2026 Reg 722.312.2.1 requires that no PEN conductor shall form part of the circuit supplying EV charging equipment. On a TN-C-S (PME) supply this means the EV circuit must originate downstream of the main bonding point where PE and N are already separate conductors — combined PEN wiring must not extend into the EV final circuit. PME earthing must not be used for EV charging where the user is outdoors unless additional protective measures (O-PEN device, TT earth, or separation) are installed. The IET CoP is clear on this point.

Option 1: O-PEN Device

Install an O-PEN detection device that monitors the PEN conductor and disconnects the EV charging circuit if continuity is lost. This allows the PME earth to be used for the general installation while protecting the EV circuit specifically. Most commonly used solution.

Option 2: TT Earth

Install a separate earth electrode (TT earthing) for the EV charging circuit. The EV circuit uses its own earth rod rather than the PME earth. Requires an RCD for fault protection and the earth electrode resistance must be verified. Independent of the supply earth.

Option 3: Class II Charger

Use a charger and charging cable that are double insulated (Class II) throughout the entire charging path, eliminating the need for a protective earth conductor to the charger metalwork. Limited availability — most chargers are Class I.

Option 4: Isolation Transformer

BS 7671:2018+A4:2026 Reg 722.413.1.2 permits a fixed isolating transformer (complying with BS EN 61558-2-4) to supply a Class I EV charging point from a separated, unearthed source. This arrangement is limited to supplying one vehicle from one unearthed source. An example wiring arrangement is shown in Annex A722, Figure A722.

For TN-S earthing systems (where the earth and neutral are separate throughout), the open PEN risk does not exist, and the earthing arrangement can be used directly for EV charging without additional measures. However, TN-S supplies are less common in the UK — most domestic supplies are TN-C-S (PME).

EV charger certificates with O-PEN verification

Elec-Mate's EV charger certificate template includes the O-PEN verification checklist from the IET CoP.

Try it free for 7 days
Download on the App StoreGet it on Google Play
04 · EV Charging Guide

Cable Sizing for EV Charger Circuits

Cable sizing for EV charger circuits follows the standard BS 7671 procedure but with particular attention to cable run lengths (which are often longer than typical domestic circuits) and the continuous nature of the load (EV charging is a continuous duty, not an intermittent load).

A 7 kW charger draws 32 A continuously. This means the cable must be rated for at least 32 A with all applicable correction factors applied — grouping, ambient temperature, thermal insulation, and installation method. The most common cable type for domestic EV installations is 6 mm² SWA (steel wire armoured), which provides mechanical protection for buried or surface-mounted runs. Per BS 7671 Table 4D4A, a 6 mm² 3-core XLPE (90 °C) armoured cable clipped direct (Method C) has a current-carrying capacity of 47 A at reference conditions — note that the 41 A figure sometimes quoted comes from Table 4D1A, which applies to flat PVC twin-and-earth cable, not SWA. All applicable correction factors (ambient temperature, grouping, soil thermal resistivity) must be applied before confirming 6 mm² SWA is adequate for the 32 A continuous EV load.

Typical Cable Sizes for EV Chargers

  • 7 kW (32 A) single-phase: 6 mm² 3-core SWA for runs up to approximately 30 m. 10 mm² for longer runs where voltage drop exceeds the limit.
  • 22 kW (32 A) three-phase: 6 mm² 5-core SWA for moderate cable runs. 10 mm² for longer runs. Check the three-phase voltage drop calculator for specific lengths.
  • 3.6 kW (16 A) single-phase: 2.5 mm² cable may be acceptable for short runs if the reduced charging speed is sufficient.

Voltage drop is frequently the limiting factor for EV charger cable sizing because of the long cable runs involved — the charger is often mounted on the side of a garage or at the end of a driveway, 20 to 40 metres from the consumer unit. Use the voltage drop calculator to verify compliance with the 5% limit (11.5 V on a 230 V single-phase circuit).

05 · EV Charging Guide

Smart Charging and OCPP

The Electric Vehicles (Smart Charge Points) Regulations 2021, which came into force on 30 June 2022, make smart functionality a legal requirement for all private EV chargepoints sold or installed in the UK. The regulations apply to domestic and workplace chargers but not to public rapid chargers above 50 kW.

Smart Charging Requirements

  • Off-peak default: chargers must default to not charging between 08:00 and 11:00 on weekdays, reducing peak demand on the national grid.
  • User override: the owner must be able to override the default schedule and charge at any time if needed.
  • Randomised delay: a random delay of up to 10 minutes on scheduled charging start times to prevent thousands of chargers starting simultaneously.
  • Cybersecurity: chargers must meet cybersecurity standards to prevent unauthorised access to the charging network.

OCPP (Open Charge Point Protocol) is the industry-standard communication protocol for EV chargers. It allows chargers from different manufacturers to communicate with a central management system (CMS) for monitoring, billing, load management, and remote diagnostics. OCPP 1.6 is the most widely deployed version; OCPP 2.0.1 is the latest, adding features such as device management, improved security, and support for ISO 15118 (vehicle-to-charger communication for plug-and-charge).

For commercial installations with multiple chargers, OCPP connectivity is essential for load management, usage tracking, and billing. The IET CoP recommends that electricians ensure the charger has network connectivity (Wi-Fi, Ethernet, or 4G) and that the OCPP back-end system is configured and tested during commissioning.

Try Elec-Mate free for 7 days

16 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.

Start free trial
Download on the App StoreGet it on Google Play
06 · EV Charging Guide

Protection Devices for EV Circuits

EV charger circuits require specific protection devices that may differ from standard domestic circuits. The key considerations are:

  • MCB or RCBO: typically a 32 A Type B or Type C MCB for a 7 kW charger. Type C may be needed if the charger has high inrush current on start-up. An RCBO (combined MCB + RCD) can provide both overcurrent and residual current protection in a single device.
  • RCD type: at minimum, a Type A RCD (30 mA) is required to protect against AC and pulsating DC fault currents. If the charger does not have built-in DC fault detection (6 mA DC residual current device), a Type B RCD may be needed. Check the charger manufacturer instructions — most modern chargers include DC fault detection and require only a Type A RCD.
  • Surge protection (SPD): BS 7671:2018+A4:2026 Reg 443.4.1 requires protection against transient overvoltages where the consequence caused by the overvoltage could result in serious injury to, or loss of, human life (limb (a)) or significant financial or data loss (limb (c)). Limb (b) was deleted by the BS 7671:2018+A2:2022 Corrigendum (May 2023), so these are the two active conditions. For all other cases, protection must be provided unless the owner of the installation declares it is not required because any loss or damage is tolerable and they accept the risk of damage to equipment and any consequential loss. EV chargers with electronic control circuitry are susceptible to surge damage. A Type 2 SPD at the consumer unit provides effective protection.
  • Isolation switch: a means of isolation should be provided to allow the EV circuit to be safely isolated for maintenance. This can be the MCB/RCBO in the consumer unit if it is accessible.

The choice between Type A and Type B RCD is one of the most common questions on EV installations. Type B RCDs are significantly more expensive (often over £200 compared to £30 for a Type A). Most reputable EV charger manufacturers now include a built-in DC residual current monitoring device (RCMU) that detects DC fault currents above 6 mA and disconnects the supply. When this is present, the installation manual will specify that only a Type A RCD is required upstream.

07 · EV Charging Guide

Documentation and Certification

Installing an EV charger is notifiable work under Part P of the Building Regulations (Approved Document P) because it involves adding a new circuit. The following documentation is required:

  • Electrical Installation Certificate (EIC) — issued for the new EV charging circuit. Must include full test results: continuity, insulation resistance, polarity, earth fault loop impedance, prospective fault current, and RCD operation.
  • Building Regulations notification — if registered with a competent person scheme, the electrician self-certifies and notifies building control electronically. If not registered, building control must be notified separately.
  • IET CoP installation checklist — the CoP includes a specific checklist for EV installations covering items such as earthing arrangement verification, O-PEN protection confirmation, load management settings, and charger commissioning checks.
  • OZEV grant documentation — if the installation is funded (or part-funded) through an OZEV grant (such as the Workplace Charging Scheme or EV Infrastructure Grant), additional documentation may be required for the grant claim.

Building Regulations Part S — EV Infrastructure

Alongside Part P notification, electricians working on new dwellings and major renovations must also consider Approved Document S (Infrastructure for the Charging of Electric Vehicles). Part S requires EV charging infrastructure — cable containment and, in some cases, charge points — to be installed as part of the building work. It applies to new residential buildings with associated parking and to existing residential buildings undergoing major renovation where parking is provided. This is a distinct legal requirement from Part P and is noted in the On-Site Guide (OSG) as a cross-discipline consideration for electrical installers.

See also: Building Regulations Electrical — Approved Document P
08 · EV Charging Guide

EV Charger Installations with Elec-Mate

Elec-Mate streamlines the entire EV charger installation workflow — from initial load assessment through to certificate delivery and invoicing. Here is how the app supports each stage:

Cable Sizing and Voltage Drop

Enter the charger power, cable type, and run length. Elec-Mate calculates the minimum cable size with all correction factors applied and verifies voltage drop compliance. Works for both single-phase (7 kW) and three-phase (22 kW) chargers.

EV Charger Certificate

Dedicated EV installation certificate template with the IET CoP checklist built in. Covers earthing verification, O-PEN protection details, load management settings, and full test results. Exports as a professional PDF.

Code of Practice EV Charging 5th Ed PDF

5th edition CoP for EV charging installations. BS 7671:2018+A4:2026 compliant guidance on cable sizing, load assessment, and earthing. Download now.

Try it free for 7 days
Download on the App StoreGet it on Google Play

Frequently Asked Questions About the IET EV Code of Practice

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-Day Free Trial — Cancel Anytime, No Hassle

Install EV Chargers with Confidence

Join 1,000+ UK electricians using Elec-Mate for EV charger installations. Cable sizing, IET CoP checklist, O-PEN verification, and instant certificates. 7-day free trial, cancel anytime.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical

From £6.99/mo after trial — less than a coffee a week

or download the app
Download on the App StoreGet it on Google Play
7 days free, then from £6.99/moCancel in one tap — no calls, no hassleiOS, Android & WebBS 7671 compliant
16
Certificate Types
70+
Calculators
46+
Training Courses
8
AI Agents

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy