TECHNICAL GUIDE

Temporary Installations: BS 7909, Events, and Construction Sites

Temporary electrical installations demand the same rigour as permanent ones — and often more. From construction site supplies to festival power systems, this guide covers which section governs the job, supply design, TT earthing figures, RCD requirements, testing and certification.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

12 min readUpdated 2026-08-07Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

The short answer

What is BS 7909 and how does it relate to BS 7671?

BS 7909:2023 is the UK Code of Practice for temporary electrical systems for entertainment and related purposes — structures, sets and mobile units for events, touring shows and theatrical, radio, TV and film production. BS 7671 Sections 706 and 711 expressly do not apply to systems defined in BS 7909 (Regs 706.1, 711.4). Temporary installations on construction and demolition sites are covered instead by BS 7671 Section 704.

Section 704 states that a PME (TN-C-S) earthing facility shall not be used unless all extraneous-conductive-parts are reliably connected to the main earthing terminal (Reg 704.411.3.1), and that circuits supplying socket-outlets or hand-held equipment up to and including 32 A must use reduced low voltage, automatic disconnection with a 30 mA RCD, electrical separation, or SELV/PELV (Reg 704.410.3.10). Socket-outlet circuits above 32 A need an RCD not exceeding 500 mA (Reg 704.411.3.2.1).

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5

Key takeaways

  1. 01BS 7909:2023 is the Code of Practice for temporary electrical systems for entertainment and related purposes. BS 7671 Sections 706 and 711 expressly do not apply to systems defined in BS 7909 (Regs 706.1, 711.4), and Sections 717 and 740 point to it for guidance.
  2. 02Temporary work on a construction or demolition site is covered directly by BS 7671 Section 704 — not by BS 7909.
  3. 03On construction and demolition sites a PME (TN-C-S) earthing facility shall not be used unless every extraneous-conductive-part is reliably connected to the main earthing terminal (Reg 704.411.3.1) — in practice TT with an earth electrode is the usual answer.
  4. 04On a TT system, fault protection is by RCD: Ra × IΔn must not exceed 50 V (Reg 411.5.3). Table 41.5 gives the maximum Zs — 1667 Ω for a 30 mA RCD, 500 Ω for 100 mA, 167 Ω for 300 mA, 100 Ω for 500 mA.
  5. 05On construction sites, circuits supplying socket-outlets or hand-held equipment up to and including 32 A must use reduced low voltage, ADS with a 30 mA RCD, electrical separation, or SELV/PELV (Reg 704.410.3.10). Socket-outlet circuits above 32 A need an RCD not exceeding 500 mA (Reg 704.411.3.2.1).
  6. 06Where the supply is a portable or temporarily sited generating set, every final circuit must have additional protection by a 30 mA RCD (Reg 551.4.4.2) — not just the socket-outlet circuits.
  7. 07RCD type selection matters: Type A covers pulsating DC, Type F adds composite/mixed-frequency residual currents, Type B adds smooth DC. Type AC may only serve fixed equipment where the load current is known to contain no DC components (Reg 531.3.3).
  8. 08Section 704 does not apply to administrative locations on construction sites — offices, cloakrooms, meeting rooms, canteens, restaurants, dormitories and toilets fall under the general requirements of Parts 1 to 6 and Part 8 (Reg 704.1.1).

01 · Technical Guide

Which Rules Apply to Your Temporary Job

Start here. “Temporary installation” is not one rulebook — BS 7671 splits the work across several Part 7 sections, and BS 7909 sits alongside them for entertainment systems. Find the row that matches the job before you design anything.

What governs which job

Type of temporary workWhat appliesAnchor
Construction and demolition sitesBS 7671 Section 704, on top of the general requirements. Covers new build, repair, alteration, extension, demolition, engineering works and earthworks — fixed and movable installations alike.Reg 704.1.1
Site offices, cloakrooms, meeting rooms, canteens, restaurants, dormitories, toiletsGeneral requirements of Parts 1 to 6 and Part 8 only. Section 704 does not apply to these administrative locations.Reg 704.1.1
Exhibitions, shows and standsBS 7671 Section 711, including mobile and portable displays. It does not cover the fixed installation of the host building.Reg 711.4
Fairgrounds, amusement parks, circuses — repeatedly erected machines and structuresBS 7671 Section 740. The permanent installation on the site is outside its scope.Reg 740.1.1
Mobile or transportable unitsBS 7671 Section 717, whose note directs you to BS 7909 for temporary event and entertainment systems.Reg 717.1
Structures, sets and mobile units for public or private events, touring shows, theatrical, radio, TV and film productionBS 7909:2023. Sections 706 and 711 of BS 7671 expressly do not apply to electrical systems as defined in BS 7909.Regs 706.1, 711.4

BS 7671 Regulation 110.1.1 lists construction and demolition sites, exhibitions, shows and stands, and temporary fairground installations among the installations the Regulations apply to — so the Wiring Regulations are the framework in every row above.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Technical Guide

What Does BS 7909 Cover?

BS 7909:2023 is the British Standard Code of Practice for temporary electrical systems for entertainment and related purposes. BS 7671 cites it by name at Regulations 706.1, 711.4, 717.1 and 740.1.1, so its boundary with the Wiring Regulations is set by BS 7671 itself rather than by custom.

Where BS 7909 is the working code

  • Events and entertainment. Structures, sets and mobile units used for public or private events, touring shows, and theatrical, radio, TV or film productions — the exact wording BS 7671 uses when it excludes these systems from Sections 706 and 711.
  • Temporary structures. Marquees, temporary stages, grandstands and hospitality builds erected for a limited period and needing a supply.
  • Generator-supplied event systems. Where the source is a generating set rather than a DNO supply, BS 7671 Section 551 still governs the earthing and the protective arrangements — see Regulations 551.4.3.2.1 and 551.4.4.2.

Construction and demolition sites are the exception: they are covered directly by BS 7671 Section 704 and by BS 7375:2010, the Code of practice for distribution of electricity on construction and building sites cited in the note to Regulation 704.411.3.1. BS 7909 is not the governing code for that work.

The practical consequence is that BS 7909 does not lower the bar. Every temporary installation still has to be designed, erected and verified to BS 7671; the temporary nature of the work adds risks — cable damage from foot traffic and site plant, water ingress, repeated assembly and dismantling — that the codes then address in detail.

03 · Technical Guide

Temporary Supply Design

A temporary installation usually starts from the opposite end to a permanent one: not “how do I wire this building?” but “where is the power coming from, and how much do we need?”

Design decisions, in order

  • Supply source. A temporary builder’s supply from the DNO, a generating set, or both with changeover. A single construction site may be served by several sources — public supply and generating set together — and equipment must be identified with, and compatible with, the particular supply energising it (Reg 704.313.3). Safety and standby supplies must be connected by devices arranged to prevent interconnection (Reg 704.537.2).
  • Load assessment. Establish maximum demand with diversity applied, covering lighting, tools or stage equipment, heating, welfare and any specialist plant, then size the supply, main cables and protective devices to it with headroom for the site growing.
  • Distribution layout. On a construction site, current-using equipment must be supplied via an Assembly for Construction Sites (ACS) incorporating overcurrent protective devices, devices affording fault protection and socket-outlets where required. Each ACS needs its own means of switching and isolating the incoming supply, suitable for securing in the off position — a padlockable device or a lockable enclosure (Reg 704.537.2). At exhibitions, every separate temporary structure and each distribution circuit supplying outdoor installations needs its own readily accessible, identifiable means of isolation (Reg 711.537.2.1.1).
  • Cable selection. On construction sites, reduced low voltage systems use low temperature 3182/3/4/5A thermoplastic cable to BS 6004 or equivalent flexible cable; anything above reduced low voltage uses H07RN-F to BS EN 50525-2-21 or equivalent heavy duty flexible cable, and flexible cables subject to movement must be H07RN-F or equivalent, resistant to abrasion and water (Reg 704.522.8.11). Rate every cable for the current it will actually carry, allowing for ambient temperature and grouping.
  • Cable routing. Cables should not be run across site roads or walkways; where that is unavoidable, provide adequate protection against mechanical damage and contact with construction plant. Surface-run and overhead cables need particular attention (Reg 704.522.8.101). At exhibitions, flexible cables must not be laid in areas accessible to the public unless protected against mechanical damage, and wiring cables must be copper of at least 1.5 mm² (Reg 711.52).

Equipment standards on construction sites

Regulation 704.511.1 names the standards outright — there is no room for interpretation here.

EquipmentStandard
All assemblies for the distribution of electricity on siteBS EN 61439-4
Plugs and socket-outlets, 16 A up to 125 ABS EN IEC 60309-2
Plugs and socket-outlets above 125 A up to 800 A, where interchangeability is not requiredBS EN IEC 60309-1

Minimum IP ratings by environment

BS 7671 does not publish one IP figure for temporary work — Regulation 704.512.2 requires external influences to be assessed instead. The figures below are the practical working minima. Select for the worst conditions the equipment will actually see.

LocationMinimum IPProtects against
Indoor, under cover, dryIP2X – IP4XContact with solid objects; no specific water protection
Outdoor, general exposureIP44Solid objects of 1 mm and greater, and splashing water from any direction
Heavy rain or hose-down cleaningIP55 – IP65Dust ingress and low-pressure water jets from any direction
Ground level, flooding or standing waterIP67Dust-tight, and temporary immersion

Where BS 7671 does give a figure it is location-specific: at exhibitions, enclosures providing basic protection for SELV or PELV must be at least IP4X or IPXXD (Reg 711.414.4.5), and a floor-mounted socket-outlet must be adequately protected against accidental ingress of water and strong enough for the expected traffic load (Reg 711.55.7).

04 · Technical Guide

Earthing and Bonding for Temporary Installations

Most temporary installations end up on TT, because BS 7671 restricts PME on exactly the kind of work temporary installations involve. That decision then drives everything else: on TT, fault protection is by RCD, so the electrode resistance and the RCD rating have to satisfy Regulation 411.5.3 together.

TT fault protection: the numbers

Regulation 411.5.3 sets two conditions. Disconnection must be within the time required by Regulation 411.3.2.2 or 411.3.2.4, and RA × IΔn must not exceed 50 V. The requirement is met if the earth fault loop impedance meets Table 41.5.

RCD rated residual operating current (IΔn)Maximum Zs — Table 41.5, U0 230 V
30 mA1667 Ω
100 mA500 Ω
300 mA167 Ω
500 mA100 Ω

The 1667 Ω and 500 Ω figures carry a note in Table 41.5: the resistance of the installation earth electrode should be as low as practicable, and a value exceeding 200 Ω may not be stable (see Reg 542.2.4). That 200 Ω is a stability caution, not the compliance limit — the compliance limits are the ones tabulated above. On poor ground, drive more electrodes.

Maximum disconnection times

Table 41.1 applies to final circuits rated up to 63 A with one or more socket-outlets, and up to 32 A supplying only fixed connected equipment (Reg 411.3.2.2). Figures below are for AC at U0 of 230 V.

SystemFinal circuit within Reg 411.3.2.2Distribution circuit
TT0.2 s1 s (Reg 411.3.2.4)
TN0.4 s5 s (Reg 411.3.2.3)

Where disconnection on a TT system is achieved by an overcurrent protective device and the protective equipotential bonding is connected to all extraneous-conductive-parts in accordance with Regulation 411.3.1.2, the TN times may be used instead.

Earthing systems for temporary supplies

SystemSourceSuitability for temporary work
TTMains or generator with an earth electrodeThe usual answer outdoors and on sites. Fault protection relies on RCDs; electrode resistance must be measured (Reg 643.7.2) and satisfy Reg 411.5.3.
TN-SDNO TN-S, or a generator with an earthed star point and a separate protective conductorAcceptable where a sound, dedicated protective conductor runs all the way back to the source.
TN-C-S (PME)DNO combined PENShall not be used on construction and demolition sites unless every extraneous-conductive-part is reliably connected to the main earthing terminal per Reg 411.3.1.2 (Reg 704.411.3.1). At exhibitions and shows, permitted outside a building only under continuous supervision by a skilled or instructed person, with the means of earthing confirmed before connection (Reg 711.411.4).
ITUnearthed generatorRuns on through a first fault, but needs an insulation monitoring device giving audible and visual signals (Reg 538.1) so the first fault is cleared before a second occurs.

Where a generating set provides a switched alternative to the public supply, fault protection shall not rely on the connection to the earthed point of the public distribution system — a suitable means of earthing must be provided (Reg 551.4.3.2.1).

Bonding conductor sizes

  • Main protective bonding, no PME (Reg 544.1.1). Not less than half the cross-sectional area required for the earthing conductor of the installation, at least 6 mm², and need not exceed 25 mm² in copper or equivalent conductance in another metal.
  • Main protective bonding where PME conditions apply (Table 54.8). Selected against the PEN conductor of the supply: 10 mm² for a PEN of 35 mm² or less, 16 mm² over 35 up to 50 mm², 25 mm² over 50 up to 95 mm², 35 mm² over 95 up to 150 mm², and 50 mm² above 150 mm². It is not a flat 10 mm². Where there is more than one source to which PME conditions apply, size against the largest PEN conductor.
  • Supplementary bonding (Reg 544.2). Between two exposed-conductive-parts, conductance not less than the smaller protective conductor (Reg 544.2.1). Between an exposed-conductive-part and an extraneous-conductive-part, not less than half the protective conductor connected to the exposed-conductive-part (Reg 544.2.2). Between two extraneous-conductive-parts, not less than 2.5 mm² (Reg 544.2.3). In every case, where mechanical protection is not provided the minimum is 4 mm².
  • What to bond. Extraneous-conductive-parts — metallic structures, scaffolding, staging and trusses, metallic services — connected to the main earthing terminal. At exhibitions, structural metallic parts accessible from within the stand, vehicle, wagon, caravan or container shall be connected through the main protective bonding conductors to the main earthing terminal within the unit (Reg 711.411.3.1.2).

The earthing arrangement must be shown on the single-line diagram and verified by testing before the installation is energised.

05 · Technical Guide

Protection and RCDs

Temporary installations carry the same overcurrent and fault protection requirements as permanent ones, plus a layer of extra RCD requirements that only apply to temporary work. These are the ones people miss.

RCD requirements by situation

SituationRequirementAnchor
Any AC installation — socket-outlets up to 32 A, and mobile equipment up to 32 A for use outdoorsAdditional protection by an RCD not exceeding 30 mA. The documented risk assessment exception applies only to socket-outlets in “other locations”, never to outdoor mobile equipment.Reg 411.3.3
Construction site — circuits supplying socket-outlets up to 32 A, or hand-held equipment up to 32 AReduced low voltage; or ADS with additional protection by a 30 mA RCD; or electrical separation with an individual transformer or separate winding per item; or SELV/PELV.Reg 704.410.3.10
Construction site — circuits supplying socket-outlets rated above 32 AAn RCD with a rated residual operating current not exceeding 500 mA, operating within the disconnection time of Reg 411.3.2.3 or 411.3.2.4.Reg 704.411.3.2.1
Portable or temporarily sited generating set — TN, TT or ITEvery final circuit must have additional protection by a 30 mA RCD, not just the socket-outlet circuits.Reg 551.4.4.2
Exhibition, show or stand — cable supplying a temporary structureProtected at its origin by an RCD not exceeding 300 mA, time-delayed or type S for selectivity with the final circuit RCDs.Reg 711.410.3.4
Exhibition, show or stand — final circuits up to 32 A for socket-outlets or hand-held equipment, and all lighting final circuitsADS with a 30 mA RCD; or SELV/PELV; or electrical separation. Final circuits of safety services are excepted.Reg 711.410.3.101

On construction sites the reduced low voltage option means a nominal voltage not exceeding 110 V AC RMS between lines — 63.5 V to earthed neutral three-phase, 55 V to earthed midpoint single-phase (Reg 411.8.1.2). Regulation 704.410.3.10 notes that reduced low voltage is strongly preferred for portable handlamps for general use, portable hand tools and local lighting up to 2 kW, and that SELV is strongly preferred for portable handlamps in confined or damp locations.

RCD type selection (Reg 531.3.3)

Choose the lowest type that fully covers the residual-current waveform the load can produce. Type AC shall only be used to serve fixed equipment where it is known that the load current contains no DC components.

TypeTrips onTypical temporary-installation loads
ACAlternating sinusoidal residual current onlyFixed equipment with no DC content — electric heating appliances, simple filament lighting containing no electronic components. Not a default for modern kit.
AAs Type AC, plus residual pulsating direct currentGeneral socket-outlets, single-phase tools, most LED and switch-mode loads — the practical minimum for modern equipment.
FAs Type A, plus composite residual currents and pulsating DC superimposed on smooth DCSingle-phase variable-speed drives, dimmers and stage equipment producing mixed-frequency residual currents.
BAs Type F, plus residual sinusoidal AC up to 1 kHz, rectified DC from two or more phases, and smooth DCThree-phase drives, EV charge points and other equipment that can produce smooth DC residual current.

All RCDs connected in series should be appropriate for the residual currents expected from the loads. Entertainment lighting and stage electronics routinely produce pulsating DC or composite residual currents that a Type AC device will not see — start at Type A and move up.

Overcurrent devices and selectivity

  • Breaking capacity. Every circuit needs an appropriately rated MCB or RCBO providing both overload and fault current protection, with a breaking capacity at least equal to the prospective fault current at the point of installation — which is measured, calculated or otherwise determined at the origin and at other relevant points (Reg 643.7.3.201).
  • Selectivity between RCDs (Reg 536.4.1.4). BS 7671 calls this selectivity, not discrimination, and it is not achieved by rating alone. Two conditions must both be met: the upstream RCD is of selective type — type S, or time-delayed with an appropriate delay setting — and the ratio of upstream to downstream rated residual operating current is at least 3:1. A 100 mA type S device upstream of 30 mA devices satisfies the ratio. At exhibitions, selectivity between RCDs installed in series shall be provided (Reg 711.536.4.1.4).
  • Switchgear access. At exhibitions, shows and stands, switchgear and controlgear must be placed in closed cabinets that can only be opened with a key or a tool, except for parts designed and intended to be operated by ordinary persons (Reg 711.51).

In the app

Try Elec-Mate free for 7 days

16 certificate types, 70+ calculators, RAMS, quoting, invoicing, AI agents, and 46+ training courses — from £6.99/mo.

06 · Technical Guide

Testing and Verification of Temporary Installations

Initial verification of a temporary installation follows BS 7671 Chapter 64 exactly as a permanent one does, with extra visual attention to the risks the temporary nature creates. The dead tests of Regulations 643.2 to 643.6 are carried out in that order before the installation is energised, and where the installation has an earth electrode the test of Regulation 643.7.2 is done as part of that sequence.

The verification sequence

  1. Visual inspection. Cables checked for damage; connections tight and correctly terminated; enclosure IP ratings appropriate to the assessed external influences; routing free of trip hazards, water exposure and plant damage; every circuit and board labelled.
  2. Dead tests. Continuity of protective conductors including main and supplementary bonding; ring final circuit continuity where present; insulation resistance (Reg 643.3) — for circuits up to and including 500 V, 500 V DC test with a minimum of 1.0 MΩ per Table 64; polarity (Reg 643.6).
  3. Insulation resistance where equipment is connected (Reg 643.3.3). Where connected equipment is likely to influence the result or be damaged, the Table 64 test is applied before that equipment is connected. After connection, a 250 V DC test is applied between live conductors and the protective conductor connected to the earthing arrangement, with a value of at least 1 MΩ. On temporary installations full of switch-mode drivers and control gear, this two-stage route is usually the practical one.
  4. Live tests. Earth fault loop impedance to verify disconnection times; prospective short-circuit and earth fault current at the origin and other relevant points (Reg 643.7.3.201); phase sequence on polyphase circuits (Reg 643.9); RCD verification under Regulation 643.8 using equipment to BS EN 61557-6 — a single alternating current test at the rated residual operating current, IΔn, whatever the device type, with 300 ms maximum for a general non-delay device. Amendment 4 deleted Table 3A of Appendix 3, so the ½× and 5× tests are no longer part of the required sequence.
  5. Functional testing (Reg 643.10). Switchgear and controlgear assemblies, drives, controls and interlocks proved to operate correctly; main switches and RCD test buttons operated; generator changeover proved where fitted.

In the app

Complete electrical certificates on your phone

Elec-Mate lets you create EIC, EICR, and Minor Works certificates directly on site. AI board scanner reads distribution board details…

07 · Technical Guide

Documentation Requirements

Temporary installations are certified the same way permanent ones are, plus the records the temporary nature demands. BS 7671 is specific about what has to accompany the certificate.

What has to exist before hand-over

  • Single-line diagram. Supply source, main and sub-distribution, cable types and sizes, protective devices, earthing arrangement and loads. This is the reference for anyone who works on the installation after you.
  • Electrical Installation Certificate. Issued by the persons responsible for design, construction and verification, to the person ordering the work (Reg 644.4), before the installation goes into service.
  • Schedules (Reg 644.3). The Certificate must state the extent of the work and include the Schedule(s) of Inspection and the Schedule(s) of Circuit Details and Test Results, based on the models in Appendix 6.
  • Recommended re-inspection interval. The interval between initial verification and the first periodic inspection must be recorded on the Certificate (Reg 644.4). For temporary work this is the field that carries your inspection regime — set it deliberately.
  • Risk assessment and method statement. Covering installation, commissioning, operation and decommissioning, completed before work begins. Where the documented risk assessment exception to Regulation 411.3.3 is used, it must be provided with the certificate.
  • Periodic records. An Electrical Installation Condition Report on each periodic inspection (Reg 653.1), retained with the project file.

Certificates and Minor Works Certificates may be produced in written or electronic form, provided their authenticity and integrity — and the fidelity of any copy — can be verified by a reliable process (Reg 644.4.202).

In the app

Generate RAMS and certificates with AI

Elec-Mate's AI Health and Safety agent generates complete RAMS documents for temporary installations, while the certificate app produces EIC, EICR…

08 · Technical Guide

Construction Sites vs Events: Key Differences

The design principles are shared, but the governing section, the voltages and the people exposed to the installation are not.

 Construction and demolition sitesExhibitions, shows and stands
Governing sectionBS 7671 Section 704BS 7671 Section 711 — unless the system falls within BS 7909:2023, which Section 711 excludes
Supply voltageReduced low voltage strongly preferred for portable hand tools, handlamps and local lighting up to 2 kW (Reg 704.410.3.10)Shall not exceed 230/400 V AC or 500 V DC (Reg 711.313)
Distribution equipmentAssembly for Construction Sites to BS EN 61439-4, with lockable-off isolation (Regs 704.511.1, 704.537.2)Switchgear in closed cabinets openable only by key or tool (Reg 711.51)
PMENot unless every extraneous-conductive-part is reliably connected to the MET (Reg 704.411.3.1)Outside a building, only under continuous supervision with the earthing confirmed beforehand (Reg 711.411.4)
Who is exposedTrained workers; CDM 2015 duties apply alongside BS 7671Ordinary persons, including children — hence the restrictions on public access to cables and switchgear

Section 704 does not cover the site offices. The particular requirements of Section 704 do not apply to administrative locations on construction sites — offices, cloakrooms, meeting rooms, canteens, restaurants, dormitories and toilets are explicitly excluded, and the general requirements of Parts 1 to 6 and Part 8 apply there instead (Reg 704.1.1). Certifying a site cabin as though it were site distribution gets this wrong in both directions.

The public-safety dimension of event work is what drives the extra restrictions. Flexible cables must not be laid in areas accessible to the public unless protected against mechanical damage (Reg 711.52); a floor-mounted socket-outlet must resist water ingress and the expected traffic load (Reg 711.55.7); and extra-low voltage transformers and electronic converters must be mounted out of arm’s reach of ordinary persons (Reg 711.55.101).

Frequently Asked Questions About Temporary Installations

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-day free trial

Certificates and RAMS for Temporary Installations

Create EIC, EICR, and Minor Works certificates on your phone. Generate RAMS and risk assessments with AI. Designed for electricians working on temporary installations. 7-day free trial.

Start your free trial

From £6.99/mo after the trial — no charge until day 8.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical · 5 out of 5
  • 7 days free, then from £6.99/mo
  • Cancel in one tap — no calls, no hassle
  • iOS, Android and web
  • Built to BS 7671:2018+A4:2026

Or download the app

Download on the App StoreGet it on Google Play
Certificate types
16Certificate types
Calculators
70+Calculators
Training courses
46+Training courses
AI specialists
8AI specialists

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy