CERTIFICATES

Solar PV Certificate Requirements: MCS UK Guide

Every solar PV installation requires an EIC, MCS certificate, DNO notification, and handover documentation. This guide explains each certificate requirement in detail, covering what must be included, who issues it, and the consequences of missing documentation.

Free for 7 days · No charge until day 8 · Cancel anytime · Used by 1,000+ UK electricians

13 min readUpdated 2026-06-10Andrew Moore, Founder of Elec-Mate

Written and reviewed by Andrew Moore, founder of Elec-Mate, against BS 7671:2018+A4:2026, IET Guidance Note 3 and the IET On-Site Guide.

ShareXinW
Follow

What certificates do you need for a solar PV installation in the UK?

A UK solar PV install needs four things: an Electrical Installation Certificate (EIC) to BS 7671:2018+A4:2026 covering the AC and DC work; an MCS certificate (required for the customer to claim Smart Export Guarantee payments); a DNO notification (G98 up to 16A per phase, G99 above); and a handover pack with commissioning results and warranties. Building Regulations are met via Part P self-certification.

1,000+

UK electricians

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer — DP Electrical

Key Takeaways

  • 1Every solar PV installation requires an Electrical Installation Certificate (EIC) to BS 7671, covering the AC and DC wiring, protective devices, and earthing arrangements.
  • 2MCS certification is required for the customer to access the Smart Export Guarantee (SEG) feed-in payments for exported electricity.
  • 3G98 notification (for systems up to 16A per phase, approximately 3.68kW single-phase) must be submitted to the DNO before commissioning. G99 applies to larger systems.
  • 4Handover documentation must include system design details, commissioning test results, inverter settings, and manufacturer warranty information.
  • 5DC-side cables and equipment remain energised whenever panels are exposed to light — even when the AC supply and inverter are fully disconnected (BS 7671 Reg 712.410.101). The EIC isolation notes and safe-working method must reflect this.
  • 6A permanent warning notice is mandatory at every DC access point (combiner boxes, DC distribution boards) and fixed to every inverter per BS 7671 Regs 712.514.102 and 712.514.103. Absence of these labels is a frequent MCS audit non-conformance.
  • 7DC connectors must be selected to BS EN 62852:2015+A1:2020 per Reg 712.526.101. Where accessible to non-skilled persons, they must require a key or tool to disconnect.
  • 8Elec-Mate provides digital solar PV certificate templates covering the EIC, commissioning record, and handover pack with professional PDF export.
01 · Certificates

Solar PV Certificate Requirements: Overview

Installing a solar PV system in the UK requires a package of certificates and notifications that together demonstrate the installation is safe, compliant, and eligible for export payments. Unlike a straightforward domestic rewire where a single EIC may suffice, a solar PV installation touches multiple regulatory frameworks: BS 7671 for the electrical installation, MCS for the renewable energy certification, and the DNO connection regulations.

The key certificates and documents required for a solar PV installation are:

  • Electrical Installation Certificate (EIC) — confirms the electrical work complies with BS 7671.
  • MCS certificate — confirms the system was installed by an MCS-certified installer and meets MCS standards.
  • DNO notification (G98 or G99) — notifies the Distribution Network Operator that generation equipment is connected to the grid.
  • Handover documentation — system design, commissioning results, warranties, and user instructions.
  • Building regulations notification — Part P self-certification through a competent person scheme or a building regulations application.

This guide explains each requirement in detail, so you know exactly what documentation to produce for every solar PV installation.

Free download

Get the BS 7671 A4:2026 Cheat Sheet — free

Every key change in the 2026 amendment on one page. AFDDs, TN-C-S protection, new schedule columns, model forms. Pinned on your van dash.

  • Every regulation change summarised
  • New model forms (EIC + MEIWC)
  • Free PDF — no subscription

We'll email it once. No spam — unsubscribe any time.

02 · Certificates

Electrical Installation Certificate (EIC)

Every solar PV installation requires an Electrical Installation Certificate (EIC) to BS 7671:2018+A4:2026. The EIC covers all the electrical work associated with the installation — both the DC side (panels, string cables, DC isolator) and the AC side (inverter output, AC isolator, consumer unit connection).

What the EIC Must Cover

  • DC wiring — string cables from panels to inverter, DC isolator, cable type and size, and cable routing. DC connectors must be selected to BS EN 62852:2015+A1:2020 per Reg 712.526.101. Where accessible to non-skilled persons, connectors must require a key or tool to disconnect (Reg 712.526.101).
  • AC wiring — inverter output cable, AC isolator, dedicated circuit breaker (MCB or RCBO) in the consumer unit, and cable type and size.
  • Earthing arrangements — main earthing terminal connection, equipotential bonding of the panel mounting frame (if metallic), and protective conductor sizing.
  • Test results — continuity, insulation resistance (AC and DC), polarity, earth fault loop impedance, RCD operation, and DC string voltage and current measurements.
  • DC-side protective measure — the EIC must record whether double/reinforced insulation (Section 412) or SELV/PELV (Section 414) is applied on the DC side, as required by Reg 712.410.102. This is a mandatory selection, not a default assumption.
  • Mandatory warning labels — a permanent warning notice at every DC live-access point (combiner boxes, DC distribution boards) per Reg 712.514.102, and a warning notice fixed to every inverter per Reg 712.514.103. Both labels must be recorded as installed in the EIC inspection notes.

DC Safety: Always Treat as Live (Reg 712.410.101)

DC cables and equipment on the solar PV side remain energised whenever the panels are exposed to light — even when the AC supply has been isolated and the inverter has been disconnected. BS 7671 Reg 712.410.101 is explicit: electrical equipment on the DC side shall be considered to be energised even when the AC side is disconnected from the grid and even when the inverter is disconnected from the DC side. The EIC isolation notes and any safe-working method statement must reflect this: DC circuits cannot be treated as dead by AC isolation alone.

BS 7671 Section 712 — DC-side requirements to evidence on the EIC

RegulationRequirement
712.410.101DC-side equipment shall be considered energised even when the AC side is disconnected from the grid and the inverter is disconnected from the DC side.
712.410.102Apply one DC-side protective measure: double or reinforced insulation (Section 412) or extra-low voltage SELV/PELV (Section 414). Record which is used.
712.514.102Permanent warning notice at each point of access to DC live parts (distribution boards, combiner boxes), e.g. ‘SOLAR DC — Live parts can remain energised after isolation’.
712.514.103Warning notice fixed to all inverters: ‘WARNING — Isolate both AC and DC sides before servicing’.
712.521.1041DC cables selected and erected to minimise earth-fault and short-circuit risk — e.g. single-core non-metallic-sheathed H1Z2Z2-K to BS EN 50618; cables not laid directly on the roof surface.
712.523.101For cables subject to direct heating under the module, design ambient temperature shall be taken as at least 70°C.
712.526.101DC connectors selected to BS EN 62852:2015+A1:2020. Where accessible to ordinary persons, they must require a key or tool to disconnect (or sit in a key/tool-only enclosure).

The EIC should be issued in accordance with the model forms in BS 7671 Appendix 6. The A4:2026 update to Appendix 6 adds fields for recording surge protective devices (SPDs) and arc fault detection devices (AFDDs) — where an SPD is fitted on the AC side of the inverter, its details must be recorded on the updated EIC form. The EIC requirements for solar PV are the same as for any other new circuit, with the addition of DC-side test results that are specific to PV installations.

Solar PV EIC templates in Elec-Mate

Elec-Mate includes dedicated solar PV EIC templates with DC and AC test result fields, string voltage and current recording…

Try it free for 7 days
Download on the App StoreGet it on Google Play
03 · Certificates

MCS Certificate

The Microgeneration Certification Scheme (MCS) is the UK quality assurance scheme for small-scale renewable energy installations. MCS certification covers both the products (panels and inverters must be MCS-approved) and the installer (the company must hold an MCS installation certification).

The MCS certificate is critical because it enables the customer to:

  • Register for the Smart Export Guarantee (SEG) — energy suppliers with over 150,000 customers must offer a SEG tariff for exported electricity. MCS certification is a prerequisite for registration.
  • Receive an insurance-backed guarantee — MCS-certified installations come with an insurance-backed guarantee that protects the customer if the installer ceases to trade.
  • Add value to the property — an MCS-certified installation with all documentation provides confidence to future buyers and their mortgage lenders.

The MCS certificate is generated through the MCS installation database by the certified installer. It records the system details (panel type, inverter type, total capacity in kWp), the estimated annual generation, and the installer's MCS number. The certificate is uploaded to the MCS database and a copy is provided to the customer.

04 · Certificates

DNO Notification: G98 and G99

Connecting a solar PV system to the electricity grid requires notification to the Distribution Network Operator (DNO). The type of notification depends on the size of the installation.

G98G99
TypeNotification (connect-and-notify)Application (approval before connection)
ThresholdUp to 16A per phaseAbove 16A per phase
Single-phaseUp to approx. 3.68kWAbove approx. 3.68kW
Three-phaseUp to approx. 11.04kWAbove approx. 11.04kW
DNO timescale10 working days to objectSeveral weeks for assessment
Typical useMost domestic (3–4kW) systemsLarge domestic, commercial, multi-string

G98 — Small Systems

Applies to: systems up to 16A per phase (approximately 3.68kW single-phase or 11.04kW three-phase).

G98 is a notification, not an application. The installer submits the notification form to the DNO and can proceed with commissioning unless the DNO objects within 10 working days.

Most domestic solar PV installations fall under G98, as the typical system size of 3-4kW is within the 16A single-phase limit.

G99 — Larger Systems

Applies to: systems exceeding 16A per phase (above 3.68kW single-phase or above 11.04kW three-phase).

G99 is a formal application that requires DNO approval before the system can be connected. The DNO assesses the impact on the local network and may require network upgrades before granting approval.

The G99 process can take several weeks, so it must be started early in the project. Costs for any network reinforcement are borne by the applicant.

The DNO notification or application must be submitted by the installer. A copy of the G98 notification or G99 approval letter should be included in the handover documentation provided to the customer.

05 · Certificates

Commissioning Tests: DC and AC Sides

Commissioning a solar PV system involves two distinct sets of tests: the standard BS 7671 inspection and testing for the AC installation, plus DC-side checks specific to the PV array. Under BS 7671 Reg 712.6.101, once the relevant Part 6 requirements are met, the additional system documentation, commissioning tests and inspection follow the BS EN 62446 series. Both sets of results belong on the certificate and in the handover pack.

SideTest / checkNotes
DC sideOpen-circuit voltage (Voc) per stringCompare against expected value for the string and temperature
Short-circuit current (Isc) per stringOr operational current; confirms string is producing correctly
DC insulation resistanceTreat DC as live at all times (Reg 712.410.101) — test per BS EN 62446 method
PolarityVerify before connecting strings to the inverter
AC sideContinuity, insulation resistance, polarityStandard BS 7671 dead tests for the new AC circuit
Earth fault loop impedance & RCD operationLive tests on the inverter-to-consumer-unit circuit
Earthing & bonding verificationMain earthing terminal; bonding of metallic mounting frame where required
InverterGrid protection settingsVerify voltage/frequency trip limits and anti-islanding; factory defaults may not match UK requirements
Record serial number & firmwareFor warranty, traceability and future settings audits

A common audit finding is incomplete or missing DC results — every string needs its own Voc and current reading recorded. See the solar PV RAMS guide for the safe-working method behind these DC checks.

Record test results hands-free on site

AI board scanner, voice test entry, and automatic BS 7671 validation — finish the certificate before you leave the property. From £6.99/mo.

Try the certificate tools free
Download on the App StoreGet it on Google Play
06 · Certificates

Handover Documentation

MCS standards require the installer to provide comprehensive handover documentation to the customer on completion of the installation. This documentation package enables the customer to understand, operate, and maintain their solar PV system.

Handover Pack Contents

  • System design summary — panel layout drawing, string configuration, inverter location, cable routes, and total system capacity in kWp.
  • Commissioning test results — DC string voltage and current measurements, AC test results, inverter commissioning checks, and grid protection settings verification.
  • Manufacturer documentation — panel datasheets, inverter manual, and warranty certificates for all major components.
  • User guide — how to read the inverter display, what the indicator lights mean, how to shut down the system in an emergency, and who to contact for faults.
  • Copies of all certificates — EIC, MCS certificate, G98/G99 notification, and building regulations notification.

Proper handover documentation protects both the installer and the customer. It demonstrates professionalism, reduces the likelihood of call-backs for operational queries, and provides the evidence needed for warranty claims.

07 · Certificates

Building Regulations Compliance

Solar PV installations are electrical work that falls under Part P of the Building Regulations (England and Wales). The work must be either self-certified through a competent person scheme or notified to building control.

  • Competent person route — MCS-certified installers registered with a competent person scheme (such as NICEIC, NAPIT, or ELECSA) can self-certify the work. The scheme provider notifies building control on the installer's behalf within 30 days.
  • Building regulations application — if the installer is not registered with a competent person scheme, a building regulations application must be made to the local authority before work begins. A building control inspector will inspect the completed work.
  • Planning permission — most domestic solar PV installations are permitted development and do not require planning permission. Exceptions include listed buildings, conservation areas, and ground-mounted arrays exceeding 9m² in area.

The building regulations compliance certificate is an important document for the property owner. It is checked during property sales and mortgage applications. Missing building regulations sign-off can delay or prevent property transactions.

08 · Certificates

Warranty and Insurance-Backed Guarantee

Solar PV installations come with multiple warranties that the installer must document and hand over to the customer. Typical durations vary by component and manufacturer, so always confirm against the actual product documentation:

WarrantyTypical durationWhat it covers
Panel performance25 years (often 30)Guaranteed minimum output (commonly ~80–87% at year 25)
Panel product10–25 yearsManufacturing defects in the module itself
Inverter5–12 yearsMost likely component to need replacement; extensions common
Workmanship2–10 yearsThe installation work, set by the installer
Insurance-backed guarantee (IBG)Matches workmanship termHonours the workmanship warranty if the installer ceases to trade — an MCS benefit

All warranty documents should be included in the handover pack and the customer should be advised to keep them safe. Elec-Mate stores all certificates and warranty records digitally, so they are always accessible and cannot be lost.

Complete solar PV handover packs in Elec-Mate

Create professional solar PV handover documentation with Elec-Mate. EIC, commissioning record, system design summary…

Try it free for 7 days
Download on the App StoreGet it on Google Play
09 · Certificates

Common Solar PV Certificate Mistakes

Solar PV certification errors are a common finding during MCS audits and can result in non-conformance reports. Here are the most frequent mistakes and how to avoid them:

  • Incomplete DC test results — the EIC must include DC string voltage (Voc) and short-circuit current (Isc) measurements for every string. These are often omitted or recorded incorrectly.
  • Missing DC insulation resistance test — the DC cables must be tested for insulation resistance at a minimum test voltage of 500V (1000V preferred). This is a separate test from the AC insulation resistance.
  • G98 not submitted before commissioning — the DNO notification must be submitted before the system is connected and commissioned. Retrospective notification is not acceptable.
  • No grid protection settings verification — the inverter grid protection settings (voltage and frequency trip limits) must be verified and recorded. Factory default settings may not match UK requirements.
  • Building regulations not notified — the work must be notified through a competent person scheme or a building regulations application. Missing this step creates problems for the property owner during future sales.
  • Missing DC access-point warning labels (Reg 712.514.102) — a permanent warning notice is mandatory at every point of access to DC live parts (combiner boxes, DC distribution boards). Example wording: ‘SOLAR DC — Live parts can remain energised after isolation’. Absence of these labels is a frequent MCS audit non-conformance finding.
  • Missing inverter warning notice (Reg 712.514.103) — a warning notice must be physically fixed to every inverter with wording similar to: ‘WARNING — Isolate both AC and DC sides before servicing’. This is a mandatory labelling requirement under BS 7671, not a recommendation.
  • Wrong DC connector type (Reg 712.526.101) — DC connectors must be selected to BS EN 62852:2015+A1:2020. Generic or non-compliant connectors fail this requirement. Where connectors are accessible to non-skilled persons, they must require a key or tool to disconnect.

Elec-Mate's solar PV certificate templates include prompts and validation checks that help you avoid these common errors. The app flags missing test results, reminds you about DNO notification, and ensures all required fields are completed before the certificate can be finalised.

Frequently Asked Questions About Solar PV Certificates

What electricians say

Verified reviews from the UK App Store.

One App for Everything!

Elec-Mate is my go to app for business and electrical work. It's feature rich without feeling cluttered. A true all in one app for quotes, certs, calculations, RAMS, EICRs, and more. I use it every day without fail, and it makes my workflow much smoother since I'm not jumping between apps anymore. The price-to-feature ratio is excellent. Any issues I've had, the developer responds within the hour and usually fixes them the same day. 100% recommend.

Apple App Store · GBR

Fantastic app for electricians

I've used the app and the web based version for a while now and it's well worth the investment. If you're an apprentice or experienced Spark give it a go, you won't be disappointed.

Apple App Store · GBR

Absolutely amazing

I've been using Elec-Mate for a while now, and honestly, it's one of the best apps I've ever downloaded. Every aspect of it feels thoughtfully designed, from the clean and intuitive interface to the powerful features that make everything so easy to manage. It's clear that a lot of care and attention went into building this app, and it shows in every detail.

Apple App Store · GBR

Trusted by electricians across the UK

Real feedback from real sparks

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer

Sole Trader · DP Electrical

“I've won two contracts this month because I could turn quotes around same-day with the AI cost engineer.”

Nathan Perry

Electrician · NP Electrical Services

“The study centre got me through my AM2. Mock exams and flashcards are brilliant.”

Jake Pizey

3rd Year Apprentice · Apprentice

7-Day Free Trial — Cancel Anytime, No Hassle

Solar PV Certificates on Your Phone

Create professional solar PV certificates with Elec-Mate. EIC with DC test results, commissioning records, and complete handover packs with instant PDF export. 7-day free trial.

“Replaced three separate apps with Elec-Mate. Certs, quotes, and scheduling all in one place.”

Daniel Palmer, DP Electrical

From £6.99/mo after trial — less than a coffee a week

or download the app
Download on the App StoreGet it on Google Play
7 days free, then from £6.99/moCancel in one tap — no calls, no hassleiOS, Android & WebBS 7671 compliant
16
Certificate Types
70+
Calculators
46+
Training Courses
8
AI Agents

1,000+ electricians · From £6.99/mo after trial

We use cookies to improve the app and measure what works. Cookie Policy